621 projects are registered in Dakshina Kannada district: 30,038 units across the 549 that file a count, 56 registered in the last 12 months. Sales and inventory trends accumulate from each future quarterly update; this page shows the first one.

621Projects covered
56Registered, last 12 months
30,038Units declared
190Completion dates revised
1With declared litigation

Of the 621 covered registrations, 190 have revised their promised completion date and 1 declare litigation. Of the 163 that file a booking figure, the median is 38% booked as of the current data. Every figure comes from the projects' own RERA Karnataka filings.

How far Dakshina Kannada possession dates have moved

Builders may revise the possession date they filed at registration. Each bar is the year a project first promised, split by how far that date has since moved. 190 of 621 projects (31%) have moved at least once; the median move is 9 months and the longest is 46 months.

Kept the original dateMoved by under 2 yearsMoved by 2 years or more

0255075100Originally due 2017: 10 projects kept the original date, 91% of the yearOriginally due 2017: 1 projects moved by under 2 years, 9% of the year’17Originally due 2018: 38 projects kept the original date, 57% of the yearOriginally due 2018: 29 projects moved by under 2 years, 43% of the year’18Originally due 2019: 32 projects kept the original date, 56% of the yearOriginally due 2019: 25 projects moved by under 2 years, 44% of the year’19Originally due 2020: 15 projects kept the original date, 27% of the yearOriginally due 2020: 41 projects moved by under 2 years, 73% of the year’20Originally due 2021: 11 projects kept the original date, 20% of the yearOriginally due 2021: 42 projects moved by under 2 years, 76% of the yearOriginally due 2021: 2 projects moved by 2 years or more, 4% of the year’21Originally due 2022: 22 projects kept the original date, 46% of the yearOriginally due 2022: 24 projects moved by under 2 years, 50% of the yearOriginally due 2022: 2 projects moved by 2 years or more, 4% of the year’22Originally due 2023: 35 projects kept the original date, 70% of the yearOriginally due 2023: 13 projects moved by under 2 years, 26% of the yearOriginally due 2023: 2 projects moved by 2 years or more, 4% of the year’23Originally due 2024: 24 projects kept the original date, 89% of the yearOriginally due 2024: 3 projects moved by under 2 years, 11% of the year’24Originally due 2025: 42 projects kept the original date, 93% of the yearOriginally due 2025: 3 projects moved by under 2 years, 7% of the year’25Originally due 2026: 36 projects kept the original date, 95% of the yearOriginally due 2026: 2 projects moved by under 2 years, 5% of the year’26Originally due 2027: 38 projects kept the original date, 100% of the year’27Originally due 2028: 43 projects kept the original date, 100% of the year’28Originally due 2029: 38 projects kept the original date, 100% of the year’29Originally due 2030: 23 projects kept the original date, 100% of the year’30Originally due 2031: 16 projects kept the original date, 94% of the yearOriginally due 2031: 1 projects moved by under 2 years, 6% of the year’31Originally due 2032: 3 projects kept the original date, 100% of the year’32Originally due 2033: 1 projects kept the original date, 100% of the year’33

Read down a bar to see how much of that year's cohort held its promise. Facts as per filings on RERA website.

01,2502,5003,7505,000Originally due 2017: 248 flats kept the original date, 91% of the yearOriginally due 2017: 8 flats moved by under 2 years, 9% of the year’17Originally due 2018: 1,246 flats kept the original date, 57% of the yearOriginally due 2018: 1,934 flats moved by under 2 years, 43% of the year’18Originally due 2019: 1,014 flats kept the original date, 56% of the yearOriginally due 2019: 2,027 flats moved by under 2 years, 44% of the year’19Originally due 2020: 420 flats kept the original date, 27% of the yearOriginally due 2020: 1,754 flats moved by under 2 years, 73% of the year’20Originally due 2021: 233 flats kept the original date, 20% of the yearOriginally due 2021: 2,129 flats moved by under 2 years, 76% of the yearOriginally due 2021: 76 flats moved by 2 years or more, 4% of the year’21Originally due 2022: 572 flats kept the original date, 46% of the yearOriginally due 2022: 1,648 flats moved by under 2 years, 50% of the yearOriginally due 2022: 209 flats moved by 2 years or more, 4% of the year’22Originally due 2023: 1,084 flats kept the original date, 70% of the yearOriginally due 2023: 781 flats moved by under 2 years, 26% of the yearOriginally due 2023: 167 flats moved by 2 years or more, 4% of the year’23Originally due 2024: 813 flats kept the original date, 89% of the yearOriginally due 2024: 190 flats moved by under 2 years, 11% of the year’24Originally due 2025: 1,512 flats kept the original date, 93% of the yearOriginally due 2025: 426 flats moved by under 2 years, 7% of the year’25Originally due 2026: 1,447 flats kept the original date, 95% of the yearOriginally due 2026: 47 flats moved by under 2 years, 5% of the year’26Originally due 2027: 1,638 flats kept the original date, 100% of the year’27Originally due 2028: 3,651 flats kept the original date, 100% of the year’28Originally due 2029: 1,825 flats kept the original date, 100% of the year’29Originally due 2030: 1,361 flats kept the original date, 100% of the year’30Originally due 2031: 829 flats kept the original date, 94% of the yearOriginally due 2031: 128 flats moved by under 2 years, 6% of the year’31Originally due 2032: 272 flats kept the original date, 100% of the year’32Originally due 2033: 63 flats kept the original date, 100% of the year’33

Hatched years are ones where most builders never filed a flat count, so the bar understates the real total. Read down a bar to see how much of that year's cohort held its promise. Facts as per filings on RERA website.

Where in Dakshina Kannada: projects by taluka

621 of the 621 registrations on this page name their taluka.

TalukaProjectsShare
Mangalore49480%
Dakshina Kannada6711%
Bantwala244%
Puttur193%
2 other talukas173%

Projects in Dakshina Kannada

Showing 1 to 60 of 621 projects.

Largest first, by the unit count in the filing.

ProjectDeveloperUnitsBookedRegisteredStatus
ROHAN CITY575003ROHAN CORPORATION INDIA PRIVATE LIMITED852-21 Nov 2022Registration approved
Bearys Turning PointBearys Properties and Developments Private Limited359-23 Nov 2017Registration approved
YAMUNA SKY CITY575019YAMUNA HOMES AND DESIGN PRIVATE LIMITED29915%17 Oct 2023Registration approved
The Marian ParkMarian Projects Pvt Ltd293-5 Sep 2018Registration approved
Sai Matha GardenMatha Developers Pvt Ltd283-8 Feb 2018Registration approved
ROHAN MARINA ONE575025ROHAN PLAZA PRIVATE LIMITED2670%18 Jun 2025Registration approved
PRESTIGE VALLEY CREST PHASE IPRESTIGE ESTATES PROJECTS LIMTED260-14 Oct 2017Registration approved
Green GatesPreethi Shenoy258-5 Feb 2019Registration approved
PRESTIGE VALLEY CREST PHASE 2PRESTIGE ESTATES CONSTRUCTIONS LIMITED250-21 Oct 2017Registration approved
WATER FRONTu b corporation23411%11 Jan 2021Registration approved
CANOPYM/s Mohtisham Complexes Private Limited233-26 Oct 2017Registration approved
NORTHERNSKY CITY B blockNORTHERNSKY PROPERTIES PVT LTD224-22 Dec 2017Registration approved
NORTHERNSKY CITY TOWER CNORTHERNSKY PROPERTIES PVT LTD224-1 Jun 2018Registration approved
HIGH RISE APPARTMENTMOHAMMED FAYAZUDDIN K216-29 Mar 2018Registration approved
SMART CITYSOUTHERN BUILDERS & DEVELOPERS21446%28 Mar 2024Registration approved
PRESIDENCY LIFE STYLEPRESIDENCY BUILDERS & DEVELOPERS210-26 Oct 2017Registration approved
REB GRAND VIEW575008RAI ESTATES AND BUILDERS PRIVATE LIMITED20124%14 Jun 2022Registration approved
VAILANKANNI'S HEIGHTSSL INDUSTRIES200-6 Nov 2020Registration approved
KANKANADY GATEMS BUILDTECH DEVELOPERS189-4 Jan 2022Registration approved
Provident Skyworth Phase 2Provident Housing Limited180-16 Sep 2017Registration withdrawn
MAHALAXMI575003Land Trades Builders and Developers17235%4 May 2024Registration approved
SOMESHWARA VISTA PHASE-II575005SOMESHWAR PROMOTERS AND DEVELOPERS1680%30 Jun 2025Registration approved
Marian SolaceMarian Projects Pvt Ltd163-17 Feb 2018Registration approved
bhandary heightsLakshmish bhandary160-5 Jun 2018Registration approved
Habitat One54Land Trades Builders And Developers Private Limited154-10 Dec 2018Registration approved
GEEKAY SMART CITYMS BAWA BUILDERS144-18 Jul 2022Registration approved
Provident Skyworth Phase 1Provident Housing Limited144-16 Sep 2017Registration approved
SolitaireK Shrinath Hebbar143-14 Oct 2017Registration approved
Vishwas HeritageVishwas Bawa Builders143-19 Dec 2018Registration approved
Gardens of DelightSPAS Infrastructures Private limited141-7 Dec 2017Registration approved
OCEAN VIEWNAMKO BUILDERS AND DEVELOPERS139-16 Jan 2023Registration approved
Milestone-25K. Shrinath Hebbar138-18 Nov 2017Registration approved
ICARE CITY MALLICARE BUILDERS & DEVELOPERS13710%26 May 2023Registration approved
WESTGATE GARDENS 'BLOCK A'SMR GROUP137-3 Oct 2018Registration approved
Westline SignatureWestline Builders Pvt Ltd13748%21 Oct 2017Registration approved
AlexandriaMenorah Realties Pvt Ltd136-13 Mar 2018Registration approved
CLASSIQUE RUBYMAHABALESHWARA PROMOTERS AND BUILDERS PRIVATE LTD136-26 Oct 2017Registration approved
POORVI ESTELLA575004POORVI HOUSING DEVELOPMENT COMPANY PVT. LTD.13612%18 Aug 2023Registration approved
ROHAN CROWN575003PROPERTY REAL ESTATE & DEVELOPERS13631%5 Feb 2025Registration approved
VISTARA SUNSHINEVISTARA INFRA DEVELOPERS1350%23 Jun 2026Registration approved
NORTHERNSKY EXCELSA575003Northern Sky Properties Private Limited13356%16 Feb 2023Registration approved
KailashBhargavi Builders And Developers131-19 Mar 2021Registration approved
LUCENT575006M/s MOHTISHAM COMPLEXES PVT LTD13045%10 Oct 2023Registration approved
NORTHERNSKY PALMSTREAKNORTHERNSKY PROPERTIES PVT LTD130-8 Dec 2017Registration approved
REDBRICKS PALM HILLS BLOCK B AND BLOCK CRedbricks Dwellings and Infraprojects Pvt Ltd12840%19 Feb 2020Registration approved
Rudraksh575006Mukund MGM Realty12825%14 Jan 2026Registration approved
SHETTY’S RAMPRASAD COMPLEXSHETTYS DEVELOPERS128-11 Aug 2023Registration approved
Abish Residency and Business CenterAbish Builders Pvt. Ltd.126-4 May 2018Registration approved
PRISTINE575006Land Trades Builders and Developers12333%29 Apr 2023Registration approved
Vishwas SagarVishwas Bawa Builders123-19 Dec 2018Registration approved
LANDMARK GREEN COUNTYS S REALTY121-15 Oct 2017Registration approved
LOTUS PARADISE PLAZALOTUS AVENUE121-22 Jul 2019Registration approved
SUKRITHICITADEL DEVELOPERS121-26 Mar 2019Registration approved
Palace GardensMAC & VK Associates120-27 Oct 2017Registration approved
AVALON MALL574227BENJA BUILDERS AND DEVELOPERS1180%11 Mar 2025Registration approved
MAK PRIME SQUARE575013MAK INFRAREALTY PRIVATE LIMITED11759%15 Mar 2024Registration approved
Bhandary ParkinnLAKSHMISH BHANDARY116-19 Mar 2018Registration approved
FORTUNE NEETHI HEIGHTSFORTUNE PROMOTERS115-15 Mar 2023Registration approved
VISHWAS Neethi HeightsAbdul Rauf Puthige115-4 Aug 2021Registration transferred
ALTURALand Trades Builders and Developers11473%22 Oct 2021Registration approved

Developers active in Dakshina Kannada

Lotus Properties (13), Land Trades Builders and Developers (12), POONAM BUILDERS (11), CITADEL DEVELOPERS (8), S S REALTY (7), GANESH M P (7). Each link opens the promoter's track record built from their own filings.

Frequently asked questions

How do I shortlist among the Dakshina Kannada projects listed above?

Compare each project against its neighbours, not against the brochure. Of the 163 projects on this page that file a booking figure, the median is 38% booked, which is the benchmark to hold any single project against. A project selling much slower than the district may have a pricing or credibility problem; one selling much faster deserves a look at whether construction is keeping pace with collections. Then open the developer link to check their delivery record on other projects, and compare filed carpet areas rather than super built-up marketing areas.

What does a revised completion date on a Dakshina Kannada project actually mean?

The promoter has moved their deadline with the regulator, usually under section 6, which allows an extension of up to one year for reasons beyond their control. It does not move the date in your agreement for sale: your section 18 claim for delay interest or refund runs from the possession date you signed for. Before booking a project with a revision on record, ask which approvals or works the new date depends on.

What if a Dakshina Kannada project shows strong sales but slow construction?

That shape means the promoter is collecting money faster than they are building, which is fine under a disciplined promoter and dangerous under a stretched one. The law helps: withdrawals from the project account need architect, engineer and CA certificates in proportion to progress. Check the promoter's delivery record, and watch the next quarterly filing (due within 20 days of each quarter end) to see whether the construction line moves.

Does something here look wrong, or is there a number you expected to find and did not? Every figure on this page is summed from the projects' own RERA Karnataka filings, and we read every report.

Report an errorShare feedback

Data from official RERA Karnataka filings.

Report an error or share feedback

About Dakshina Kannada district. Every figure on this page is summed from the projects' own filings, so if a number looks wrong it helps to say which one.