Registration approved Residential/Group Housing project

NORTHERNSKY CITY TOWER C

By NORTHERNSKY PROPERTIES PVT LTD

RG-KA-34605 · RERA PRM/KA/RERA/1257/334/PR/180601/001834

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 21 months
  • 2 extensions taken

Clear

  • No complaints on record
  • Separate project account declared
Sep 2024Possession promisedmoved 21 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 89 documents Report an error

NORTHERNSKY CITY TOWER C is a Residential/Group Housing project by NORTHERNSKY PROPERTIES PVT LTD in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/334/PR/180601/001834 on 1 Jun 2018. Possession is promised by 30 Sep 2024. The completion date has moved by 21 months from the original filing.

At a glance

Project

  • NameNORTHERNSKY CITY TOWER C
  • TypeResidential/Group Housing
  • Location
    • Mangalore
    • Dakshina Kannada
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1257/334/PR/180601/001834
  • ReraGenie IDRG-KA-34605

Builder

  • NameNORTHERNSKY PROPERTIES PVT LTD
  • Entity typeCompany
  • CINU45202KA2011PTC058044
  • Authorized SignatoryDheeraj Amin
  • Other registrations3 more →

Key dates

this monthRegisteredJun 2018First promiseDec 2022Revised toSep 2024

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on1 Jun 2018
  • Promised completion30 Sep 2024
  • Revised completionRevised to 30 Sep 2024 (originally 31 Dec 2022)
  • Buildings1 building record
  • Documents filed89 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
NORTHERNSKY TOWER C---2240224

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)Not applicable
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalYes-
Water conservationYes-
Energy managementYes-
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesYes-
Storm water drainsYes-
Use of renewable energyYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseYes-
Community HallYes-
Outdoor Sports facilityYes-
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksNoNot applicable
Power BackupYes-
GasYes-
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceNoNot applicable
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,837 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 70.72 cr

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionDec 2022 → Sep 2023

No reason recorded in the filing

EX/PRM/KA/RERA/1257/334/PR/240116/001834Sep 2023 → Sep 2024

Reason as filed by the promoterAwaiting OC

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed89

As listed on the registration, under the names the promoter filed them with; the newest 80 of 89 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/334/PR/180601/001834 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: Company Registration Certificate.pdf-
Architect Certificate for Work Completion Schedule till DateFile: 20 Extension NOV 2023 _TOWER C_.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Engineer Certificate.pdf-
CA Certificate for Funds UtilizationFile: Form-Ex4 CA Certificate For Fund Required_compressed (1).pdf-
Architect Certificate for Pending Work Completion Schedule.File: 21 Pending Work NOV 2023 _TOWER C__compressed.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Engineer certificate - Form 5.jpeg-
CA Certificate for Funds required for Project CompletionFile: Form-Ex4 CA Certificate For Fund Required_compressed (1).pdf-
AffidavitFile: Affidavit.pdf-
Latest Encumbrance CertificateFile: EC-3.pdf-
Consent letter from 2/3rd of AllotteesFile: C 203_C 1406_merged (2).pdf-
Details Of Sold/ Un-sold UnitsFile: Sold & Unsold Inventory.pdf-
Document 1File: ilovepdf_merged.pdf-
Document 2File: C 203C 1406merged 2_merged.pdf-
Commencement_Certificate 1mb-
Approval Building plan plotting plan BW-min 5 mb-
Approved Layout Plan MARKED C TOWER-
sale deed draft (1)-
AGREEMENT - DRAFT-
Sale DEED -city project-
Approved Section Plan-min-
Development plan-
allotmnent letter (1)-
Northern-sky-Brochure-
PROJECT_SPECIFICATION-
EC-
Khatha-
joint development agreement 18042018-
NA for this project-
Conversion Order 1 MB-
NA for this project-
NA for this project-
Relinquish deed-
Fire_NOC-ilovepdf-compressed-ilovepdf-compressed-
NA for this project-
NA for this project-
NA for this project-
kspcb-
MOEF-
NA for this project-
NA for this project-
Unnamed document-
NA for this project-
NA for this project-
NA for this project-
NA for this project-
NA for this project-
NA for this project-
Structure safety report from Engr-
combinepdf-
Approved Layout Plan-
Section plan with specification-
ZONAL-
Legal_opinion_merged-ilovepdf-compressed (1)-min-
Balance Sheet 2016 - 2017File: BS 2017.pdf-
Balance Sheet 2015 - 2016File: Balance sheet FY 2015-16.pdf-
Balance Sheet 2014 - 2015File: Balance sheet FY 2014-15.pdf-
Audited Profit and Loss Statement 2016 - 2017File: P&L 2017.pdf-
Audited Profit and Loss Statement 2015 - 2016File: P&L FY 2015-16.pdf-
Audited Profit and Loss Statement 2014 - 2015File: P&L FY 2014-15.pdf-
Director's Report 2016 - 2017File: Directors Report 2016-17.pdf-
Director's Report 2015 - 2016File: directors report 15-16.pdf-
Director's Report 2014 - 2015File: Director report 2014-15.pdf-
Cash Flow Statement 2016 - 2017File: Cash Flow 2017.pdf-
Cash Flow Statement 2015 - 2016File: Cash flow FY 2015-16.pdf-
Auditor's Report 2016 - 2017File: Auditors_Report_2017.pdf-
Auditor's Report 2015 - 2016File: AUDITORS REPORT.pdf-
Auditor's Report 2014 - 2015File: Auditors report 14 15.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: ITR V.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: ITR FY 2015-16.pdf-
Income Tax Return Acknowledgement 2014 - 2015File: ITR FY 2014-15.pdf-
form B-
Prospectus/BrochureFile: Northern-sky-Brochure.pdf-
Advertisement Copy 1File: Ad with RERA number.pdf-
Tower Excel SheetFile: PRM_KA_RERA_1257_334_PR_180601_001834.xlsx-
Loan raised documentFile: Structural Stability.pdf-
Stability CertificateFile: Structural Stability.pdf-
Road cutting permission letter issued by the planning Authority for laying Water supply line, sanitary line, UFile: NA (1).pdf-
NOC issued by the Fire Force department after completion of workFile: Fire Tower C CC.pdf-
Occupancy CertificateFile: Occupancy Certificate-Tower C.pdf-
Consent for operation issued by KSPCBFile: NSC City KSPCB NOC 1 1 1 1 1 2.pdf-

How this compares with Dakshina Kannada

30%of Dakshina Kannada projects moved their completion datethis one moved by 21 months
0%of Dakshina Kannada registrations are shown as withdrawn or revokedthis one is not

Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.

Keep NORTHERNSKY CITY TOWER C on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dakshina Kannada620+ in Dakshina Kannada

2 kmNORTHERNSKY CITY TOWER COther 29Dot size: filed unitsN

Filed coordinates, straight-line distance. 29 registered projects within 2 km.

Builder: NORTHERNSKY PROPERTIES PVT LTD

NORTHERNSKY PROPERTIES PVT LTD has 4 registrations on RERA Karnataka, including NORTHERNSKY CITY B block and NORTHERNSKY PALMSTREAK. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Dakshina Kannada district page.

Frequently asked questions

What are my rights if NORTHERNSKY CITY TOWER C is delayed beyond 30 Sep 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of NORTHERNSKY CITY TOWER C?

The registered promoter entity is NORTHERNSKY PROPERTIES PVT LTD, a company as per the filing. Its CIN U45202KA2011PTC058044 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in NORTHERNSKY CITY TOWER C?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

What should I check before booking in NORTHERNSKY CITY TOWER C?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About NORTHERNSKY CITY TOWER C. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save NORTHERNSKY CITY TOWER C to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.