Westline Signature
RG-KA-63427 · RERA PRM/KA/RERA/1257/334/PR/171021/000845 · Last updated on RERA Karnataka portal: 15 Oct 2026
Source: official RERA Karnataka filing
Red flags
- Completion date moved by 45 months
- 3 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
Saved.
Westline Signature is a Residential/Group Housing project by Westline Builders Pvt Ltd in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/334/PR/171021/000845 on 21 Oct 2017. Possession is promised by 30 Sep 2027. The completion date has moved by 45 months from the original filing. 66 of the 137 units on this registration are recorded sold or booked, and 1 of 17 construction stages are filed complete.
At a glance
Project
- NameWestline Signature
- TypeResidential/Group Housing
- Location
- Mangalore
- Dakshina Kannada
- PincodeNot stated
- RERA no.PRM/KA/RERA/1257/334/PR/171021/000845
- ReraGenie IDRG-KA-63427
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on21 Oct 2017
- Promised completion30 Sep 2027
- Revised completionRevised to 30 Sep 2027 (originally 31 Dec 2023)
- Buildings1 building record
- Documents filed122 files
Current status
Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Westline Signature | - | - | - | 137 | 0 | 137 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
1 of 17 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 98%.
Building: 62% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 98% |
| Foundation footing work | 100% |
| Retaining wall (All types) | 85% |
| Plinth level Beam | Not applicable |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 85% |
| RCC or MS Framed structure | 90% |
| Masonry construction: Bricks, Concrete blocks etc | 88% |
| Plastering inside , outside & Ceiling | 85% |
| Joinery: Doors, Windows, Ventilators etc | 20% |
| Basic work of Water supply, Sanitary and Electrification | 85% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 70% |
| Railing and Grill fixing | 65% |
| Electrification, Water supply and Sanitary Finishing | 15% |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | 30% |
| Weather Proof work(tile,concrete) | 30% |
| Painting | 35% |
| Elevation work | 35% |
| Internal and External work including landscapes as per santioned drawings | 35% |
Progress on shared amenities37
As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 40% |
| Internal Roads & Footpaths | No | Not applicable |
| Sewage and Drainage System | Yes | 20% |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | Yes | 0% |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes | 0% |
| Solid waste management and disposal | Yes | 30% |
| Water conservation | No | Not applicable |
| Energy management | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 30% |
| Education/Health/Other public amenities | Yes | 0% |
| Electricity supply transformer and substation | Yes | 20% |
| Emergency Evacuation services | No | Not applicable |
| Storm water drains | Yes | 0% |
| Use of renewable energy | No | Not applicable |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 30% |
| Electricity | Yes | 20% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | 0% |
| Club House | Yes | 40% |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | Yes | 40% |
| Swimming Pool | Yes | 0% |
| Gym | Yes | 0% |
| Parks | No | Not applicable |
| Power Backup | Yes | 0% |
| Gas | Yes | 0% |
| Water and Sanitation | Yes | 30% |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | 65% |
| Lifts | Yes | 8% |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | 10% |
| Fire escapes | Yes | 30% |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | 0% |
| Basement | Yes | 75% |
| Terrace | Yes | 28% |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 153.70 cr | Rs 130.62 cr |
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Guulshan Roy |
| Engineer | Nikhil Shanghavi |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
No reason recorded in the filing
Reason as filed by the promoterShortage of Labour
No reason recorded in the filing
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed122
As listed on the registration, under the names the promoter filed them with; the newest 80 of 122 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/334/PR/171021/000845 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: form 4.pdf | 15 Oct 2026 |
| Q2 2026-27 Form-5 Certificate issued by ArchitectFile: ARCHITECTS CERTIFICATE.pdf | 15 Oct 2026 |
| Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: ENGINEERS CERTIFICATE.pdf | 15 Oct 2026 |
| Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: CA CERTIFICATE -Q1_compressed.pdf | 15 Jul 2026 |
| Q1 2026-27 Form-5 Certificate issued by ArchitectFile: WSI-RERA-ARCHITECT CERTIFICATE-SIGNATURE - Q1-2026-27 MODIFIED.pdf | 15 Jul 2026 |
| Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: ENG CERTIFICATE.pdf | 15 Jul 2026 |
| Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: CA CERTIFICATE-Q4.pdf | 15 Apr 2026 |
| Q4 2025-26 Form-5 Certificate issued by ArchitectFile: WSI-RERA-ARCHITECT CERTIFICATE-SIGNATURE - Q4-2025-26 MODIFIED.pdf | 15 Apr 2026 |
| Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: ENGINEERS CERTIFICATE.pdf | 15 Apr 2026 |
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: CA Q3 25-26_merged_compressed.pdf | 31 Mar 2026 |
| Q3 2025-26 Form-5 Certificate issued by ArchitectFile: ARCHI-Q3-25-26.pdf | 31 Mar 2026 |
| Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: ENG-Q325-26.pdf | 31 Mar 2026 |
| clarification on landFile: clarification.pdf | 7 Jan 2026 |
| sources of fundsFile: 1 Sources of Funds.pdf | 18 Dec 2025 |
| FS 2024-25File: 1 Financial 2024-25.pdf | 18 Dec 2025 |
| JDAFile: 2 JDA.pdf | 18 Dec 2025 |
| KATHAFile: 2 WSI - E khata.pdf | 18 Dec 2025 |
| delay reason letter for modificationFile: 3 Reason for modification of the project.pdf | 18 Dec 2025 |
| sold and unsold units detailsFile: 4 List of sold and unsold Units.pdf | 18 Dec 2025 |
| sold unsold units as per new and old licenceFile: 5 SOLD AND UNSOLD UNIT.pdf | 18 Dec 2025 |
| CA CERTIFICATE modificationFile: 5 CA certiifcate.pdf | 18 Dec 2025 |
| CONSENT LETTER 1-19 CONSENTFile: 6 consent letter 1.pdf | 18 Dec 2025 |
| CONSENT LETTER 2 -17 CONSENTFile: 6 consent letter 2.pdf | 18 Dec 2025 |
| MESCOM APPLICATIONFile: 7 mescom application.jpeg | 18 Dec 2025 |
| MESCOM APPLICATION FORWARDEDFile: 7 mescom application-forwarded.pdf | 18 Dec 2025 |
| AFFIDAVIT FOR MESCOM NOCFile: 7 affidavit mescom.pdf | 18 Dec 2025 |
| INVENTORY DETAILS FLOOR WISEFile: Inventory Details Floor Wise.pdf | 18 Dec 2025 |
| CAREPET AREA AS PER OLD PLANFile: Carpet area As per Old Plan.pdf | 18 Dec 2025 |
| CAREPET AREA AS PER MODIFIED PLANFile: Carpet area As per Modified Plan.pdf | 18 Dec 2025 |
| CLARIFICATIONFile: Clarification on the Notice.pdf | 18 Dec 2025 |
| CertificateFile: CERTIFICATE OF INCORPORATION.pdf | - |
| Project Details | - |
| Already registered project ongoing detailsFile: Ongoing Project Details.pdf | - |
| Modified plan details site plan, floor plans, Plan Licence LetterFile: site plan.pdf | - |
| Elevation, Sections, Specifications ( If changes are there )File: section elevation plan.pdf | - |
| List Of AllotteesFile: List of allottees.pdf | - |
| Consent LetterFile: consent letter.pdf | - |
| Chartered Accountant CertificateFile: RERA Modification CA Certificate_compressed.pdf | - |
| Notarized AffidavitFile: Affidavit for Modification.pdf | - |
| Engineer CertificateFile: form 6 modification_compressed.pdf | - |
| Architect CertificateFile: Architect Certificate Form 5.pdf | - |
| Structural Engineer Certificate for stability of structureFile: stability certificate.pdf | - |
| Modification of Plan DetailsFile: Approved Ploting Plan.pdf | - |
| Modification of Plan DetailsFile: approved plan-modification.pdf | - |
| Modification of Plan DetailsFile: building licence-old_compressed.pdf | - |
| Modification of Plan DetailsFile: building licence-modified.pdf | - |
| Modification of Plan DetailsFile: Sold unsold units-old licence.pdf | - |
| Modification of Plan DetailsFile: Sold unsold unit new licence.pdf | - |
| Document 1File: fire noc.pdf | - |
| Document 2File: water noc.pdf | - |
| Document 3File: MESCOM NOC.pdf | - |
| Document 4File: KSPCB.pdf | - |
| Document 5File: SEIAA.pdf | - |
| consent letter 1File: consent letter 1.pdf | - |
| consent letter 2File: consent letter 2.pdf | - |
| affidavit 3(1)File: Affidavit 3(1).pdf | - |
| affidavit for litigation on landFile: Affidavit for Non Litigation on land.pdf | - |
| form bFile: form b.pdf | - |
| PROFORMA AOSFile: proforma AOS.pdf | - |
| PROFORMA ALLOTTMENT LETTERFile: proforma allotment letter.pdf | - |
| ESTIMATION COSTFile: estimated cost.pdf | - |
| approved plan modifiedFile: approved plan-modification_compressed.pdf | - |
| inventory detailsFile: INVENTORY DETAILS.pdf | - |
| Architect Certificate for Work Completion Schedule till DateFile: Form-Ex1 Architect Certificate For Status of Work As On Date.pdf | - |
| Engineer Certificate for Work Completion Schedule till DateFile: Form-Ex5 Engineers Certificate for Status of Work as on date.pdf | - |
| CA Certificate for Funds UtilizationFile: Form-Ex3 Chartered Accountant Certificate For Fund Utilization_compressed.pdf | - |
| Architect Certificate for Pending Work Completion Schedule.File: Form-Ex2 Architect Certificate For Pending Work As On Date.pdf | - |
| Engineer Certificate for Pending Work Completion Schedule.File: Form-Ex6 Engineers Certificate for Pending work as on date.pdf | - |
| CA Certificate for Funds required for Project CompletionFile: Form-Ex4 Chartered Accountant Certificate For Fund Required_compressed.pdf | - |
| AffidavitFile: Form-Ex7 Affidavit for seeking extension of registered project.pdf | - |
| Latest Encumbrance CertificateFile: EC 15 YEARS (IN FORM 15)-2008 TO 2024.pdf | - |
| Details Of Sold/ Un-sold UnitsFile: 3 SOLD AND UNSOLD UNIT-DETAILS_.xlsx | - |
| Document 1File: building licence.pdf | - |
| Document 2File: APPROVED PLAN.pdf | - |
| Document 3File: PRMKARERA1257334PR171021000845.pdf | - |
| Document 4File: PRMKARERA1257334PR171021000845 covid.pdf | - |
| Document 5File: Notarized Affidavit for 3(1) Voliation.pdf | - |
| Document 6File: Litigation Affidavith.pdf | - |
| Document 7File: list of allottees.pdf | - |
| Document 8File: proforma AOS.pdf | - |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Status | Promised | Delivered |
|---|---|---|---|---|
| Westline Skydale | - | Ongoing | Aug 2017 | Not delivered |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Dakshina Kannada
Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.
Keep Westline Signature on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Dakshina Kannada620+ in Dakshina Kannada
ROHAN CITY
ROHAN CORPORATION INDIA PRIVATE LIMITED
Bearys Turning Point
Bearys Properties and Developments Private
YAMUNA SKY CITY
YAMUNA HOMES AND DESIGN PRIVATE LIMITED
The Marian Park
Marian Projects Pvt Ltd
Sai Matha Garden
Matha Developers Pvt Ltd
ROHAN MARINA ONE
ROHAN PLAZA PRIVATE LIMITED
See every Dakshina Kannada project, with the district possession charts
Builder: Westline Builders Pvt Ltd
Westline Builders Pvt Ltd has 3 registrations on RERA Karnataka, including Westline Signature and WESTLINE FAIRMONT. Its filings declare 3 earlier projects, none of them declared completed. Read the full track record. See more projects on the Dakshina Kannada district page.
Frequently asked questions
What are my rights if Westline Signature is delayed beyond 30 Sep 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Westline Signature?
The registered promoter entity is Westline Builders Pvt Ltd, a company as per the filing. Its CIN U45205KA2014PTC075160 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Westline Signature?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at Westline Signature?
The professionals named in the filing: Architect: Guulshan Roy; Engineer: Nikhil Shanghavi. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Westline Signature?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.