Home / Browse projects / Dakshina Kannada, Karnataka / Sai Matha Garden
Sai Matha Garden
RG-KA-15828 · RERA PRM/KA/RERA/1257/334/PR/180208/001011
Source: official RERA Karnataka filing
Red flags
- Completion date moved by 12 months
- 2 extensions taken
Clear
- No complaints on record
- Separate project account declared
Saved.
Sai Matha Garden is a Residential/Group Housing project by Matha Developers Pvt Ltd in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/334/PR/180208/001011 on 8 Feb 2018. Possession is promised by 31 May 2020. The completion date has moved by 12 months from the original filing.
At a glance
Project
- NameSai Matha Garden
- TypeResidential/Group Housing
- Location
- Mangalore
- Dakshina Kannada
- PincodeNot stated
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1257/334/PR/180208/001011
- ReraGenie IDRG-KA-15828
Builder
- NameMatha Developers Pvt Ltd
- Entity typeCompany
- CINU45205KA2011PTC061006
- Authorized SignatorySanthosh Kumar Shetty N
- Other registrations6 more →
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on8 Feb 2018
- Promised completion31 May 2020
- Revised completionRevised to 31 May 2020 (originally 31 May 2019)
- Buildings8 building records
- Documents filed61 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| MATHA EMERALD | - | - | - | 36 | 0 | 36 |
| MATHA OPAL | - | - | - | 48 | 0 | 48 |
| MATHA DIAMOND | - | - | - | 36 | 0 | 36 |
| MATHA RUBY | - | - | - | 36 | 0 | 36 |
| MATHA PEARL | - | - | - | 36 | 0 | 36 |
| MATHA CRYSTAL | - | - | - | 48 | 0 | 48 |
| MATHA SHAPPIRE | - | - | - | 40 | 0 | 40 |
| SAIMATHA COMPLEX | - | - | - | 3 | 0 | 3 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | - |
| Plinth level Beam | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | - |
| Weather Proof work(tile,concrete) | - |
| Painting | - |
| Elevation work | Not applicable |
| Internal and External work including landscapes as per santioned drawings | - |
Progress on shared amenities41
Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | Yes | - |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | Yes | - |
| Street Lighting | Yes | - |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes | - |
| Solid waste management and disposal | Yes | - |
| Water conservation | Yes | - |
| Energy management | Yes | - |
| Fire protection and fire safety requirements | Yes | - |
| Education/Health/Other public amenities | Yes | - |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | Yes | - |
| Storm water drains | No | Not applicable |
| Use of renewable energy | Yes | - |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | No | Not applicable |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | Yes | - |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | Yes | - |
| Gym | No | Not applicable |
| Parks | Yes | - |
| Power Backup | Yes | - |
| Gas | No | Not applicable |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | Yes | - |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | Yes | - |
| Provision for lodging of management staff and security staff | Yes | - |
| Water conservation and renewable energy | Yes | - |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
No reason recorded in the filing
Reason as filed by the promoterShortage of Building Materials, Concrete, Jalli etc
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed61
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/334/PR/180208/001011 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CertificateFile: Comapany reg certificate.pdf | - |
| Architect Certificate for Work Completion Schedule till DateFile: Architect Certificate.pdf | - |
| Engineer Certificate for Work Completion Schedule till DateFile: Engineer Certificate.pdf | - |
| CA Certificate for Funds UtilizationFile: CA Certificate - Funds Utilized.pdf | - |
| Architect Certificate for Pending Work Completion Schedule.File: Architect Certificate.pdf | - |
| Engineer Certificate for Pending Work Completion Schedule.File: Engineer Certificate.pdf | - |
| CA Certificate for Funds required for Project CompletionFile: CA Certificate - Funds Required.pdf | - |
| AffidavitFile: Resolution & Affidavit_.pdf | - |
| Latest Encumbrance CertificateFile: up to October 2019_.pdf | - |
| Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails.xlsx | - |
| Document 1File: Paper cuttings.PDF | - |
| Document 2File: affidavit under under sec 18(1).pdf | - |
| Document 3File: Explanation.pdf | - |
| Document 4File: PDF.pdf | - |
| Document 5File: RERA - 819.pdf | - |
| Document 6File: CA Certificate - Funds Utilized.pdf | - |
| Document 7File: CA Certificate - Funds Required.pdf | - |
| Document 8File: Clarification on Account Change.pdf | - |
| Document 9File: Account Change Request.PDF | - |
| Document 10File: affidavit under under sec 18(1).pdf | - |
| Document 11File: Old account statement.pdf | - |
| Document 12File: New Account.PDF | - |
| Document 13File: Saimatha Garden Collection Account.pdf | - |
| Document 14File: CA Certificate - Funds Utilized.pdf | - |
| Commencement cert 1 | - |
| 8 | - |
| Sai matha Approved plan | - |
| Sale Deed Draft - Copy | - |
| sale Agreement sai matha | - |
| sai matha khata | - |
| Approve Plan | - |
| 9 | - |
| allotement Sai matha | - |
| Brochure Sai matha | - |
| Noc All 1 | - |
| specifiation sai matha | - |
| sai matha EC | - |
| sai matha khata | - |
| Sai Matha Garden JDA | - |
| Title Deed & sale Deed | - |
| Conversion | - |
| Fire Noc Sai matha (2) | - |
| Balance Sheet 2015 - 2016File: Balance sheet 2016.pdf | - |
| Balance Sheet 2014 - 2015File: Balance sheet 2015.pdf | - |
| Balance Sheet 2013 - 2014File: Balance sheet 2014.pdf | - |
| Audited Profit and Loss Statement 2015 - 2016File: P&L 2016.pdf | - |
| Audited Profit and Loss Statement 2014 - 2015File: P&L 2015.pdf | - |
| Audited Profit and Loss Statement 2013 - 2014File: P&L 2014.pdf | - |
| Director's Report 2015 - 2016File: Directors report.pdf | - |
| Director's Report 2014 - 2015File: Directors report.pdf | - |
| Director's Report 2013 - 2014File: Directors report.pdf | - |
| Cash Flow Statement 2015 - 2016File: Cash flow.pdf | - |
| Cash Flow Statement 2014 - 2015File: Cash flow.pdf | - |
| Auditor's Report 2015 - 2016File: Audit report LOW.pdf | - |
| Auditor's Report 2014 - 2015File: Audit report LOW.pdf | - |
| Auditor's Report 2013 - 2014File: Audit report LOW.pdf | - |
| Income Tax Return Acknowledgement 2015 - 2016File: ITR.pdf | - |
| Income Tax Return Acknowledgement 2014 - 2015File: ITR.pdf | - |
| Income Tax Return Acknowledgement 2013 - 2014File: ITR.pdf | - |
| Affidavit Sai matha | - |
| Tower Excel SheetFile: PRM_KA_RERA_1257_334_PR_180208_001011.xlsx | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Dakshina Kannada
Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.
Keep Sai Matha Garden on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Dakshina Kannada620+ in Dakshina Kannada
Filed coordinates, straight-line distance. 16 registered projects within 2 km.
ROHAN CITY
ROHAN CORPORATION INDIA PRIVATE LIMITED
Bearys Turning Point
Bearys Properties and Developments Private
YAMUNA SKY CITY
YAMUNA HOMES AND DESIGN PRIVATE LIMITED
The Marian Park
Marian Projects Pvt Ltd
ROHAN MARINA ONE
ROHAN PLAZA PRIVATE LIMITED
PRESTIGE VALLEY CREST PHASE I
PRESTIGE ESTATES PROJECTS LIMTED
See every Dakshina Kannada project, with the district possession charts
Builder: Matha Developers Pvt Ltd
Matha Developers Pvt Ltd has 7 registrations on RERA Karnataka, including Matha Shushiganga Residency and Matha Residency. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Dakshina Kannada district page.
Frequently asked questions
What are my rights if Sai Matha Garden is delayed beyond 31 May 2020?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Sai Matha Garden?
The registered promoter entity is Matha Developers Pvt Ltd, a company as per the filing. Its CIN U45205KA2011PTC061006 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Sai Matha Garden?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
What should I check before booking in Sai Matha Garden?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.