Home / Browse projects / Dakshina Kannada, Karnataka / Bhandary Parkinn
Bhandary Parkinn
RG-KA-30515 · RERA PRM/KA/RERA/1257/333/PR/180319/001244 · Last updated on RERA Karnataka portal: 10 Nov 2020
Source: official RERA Karnataka filing
Red flags
- Completion date moved by 6 months
- 2 extensions taken
Clear
- No complaints on record
- Separate project account declared
Saved.
Bhandary Parkinn is a Residential/Group Housing project by LAKSHMISH BHANDARY in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/333/PR/180319/001244 on 19 Mar 2018. Possession is promised by 30 Jun 2020. The completion date has moved by 6 months from the original filing.
At a glance
Project
- NameBhandary Parkinn
- TypeResidential/Group Housing
- Location
- Dakshina Kannada
- PincodeNot stated
- RERA no.PRM/KA/RERA/1257/333/PR/180319/001244
- ReraGenie IDRG-KA-30515
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on19 Mar 2018
- Promised completion30 Jun 2020
- Revised completionRevised to 30 Jun 2020 (originally 5 Dec 2019)
- Buildings2 building records
- Documents filed57 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BLOCK A | - | - | - | - | - | 93 |
| BLOCK B | - | - | - | 23 | 0 | 23 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 10 Nov 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | - |
| Plinth level Beam | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | - |
| Fire prevention and fire fighting fitting and fixture with network | - |
| Weather Proof work(tile,concrete) | - |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | - |
Progress on shared amenities41
As on 10 Nov 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | Yes | - |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | Yes | - |
| Street Lighting | Yes | - |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes | - |
| Solid waste management and disposal | Yes | - |
| Water conservation | Yes | - |
| Energy management | Yes | - |
| Fire protection and fire safety requirements | Yes | - |
| Education/Health/Other public amenities | Yes | - |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | Yes | - |
| Storm water drains | Yes | - |
| Use of renewable energy | Yes | - |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | - |
| Club House | Yes | - |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | Yes | - |
| Gym | Yes | - |
| Parks | Yes | - |
| Power Backup | Yes | - |
| Gas | Yes | - |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | Yes | - |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | Yes | - |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | Yes | - |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Gokulraj Associates |
| Engineer | K Anil Hegde |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
No reason recorded in the filing
Reason as filed by the promoterShortage of Building Materials, Concrete, Jalli etc
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed57
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/333/PR/180319/001244 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| AFFIDAVIT UNDER SEC 18(1) IN PRESCRIBED PROFORMAFile: rera parkinn affidavit-converted.pdf | 10 Nov 2020 |
| Extension supporting documentsFile: Extension Supporting Docs.jpg | 10 Nov 2020 |
| Extension supporting documentsFile: Extension Supporting Docs1.jpg | 10 Nov 2020 |
| Extension supporting documentsFile: Extension supporting documents2.jpg | 10 Nov 2020 |
| Bank Statement till date for A/c No: 005312100001650File: BHANDARY BUILDERS-07-10-2020.pdf | 7 Oct 2020 |
| Affidavit under sec 18(1)File: affidavit rera.pdf | 7 Oct 2020 |
| Architect Certificate for Work Completion Schedule till DateFile: ARC-WORK DONE.pdf | - |
| Engineer Certificate for Work Completion Schedule till DateFile: ENGINEERS CETIFICATE-STATUS.pdf | - |
| CA Certificate for Funds UtilizationFile: CA FUND UTILISATION WITH UDIN.pdf | - |
| Architect Certificate for Pending Work Completion Schedule.File: ARC-PENDING.pdf | - |
| Engineer Certificate for Pending Work Completion Schedule.File: ENGINEER-PENDING.pdf | - |
| CA Certificate for Funds required for Project CompletionFile: CA CERTIFICATE FR WITH UDIN.pdf | - |
| AffidavitFile: AFFIDAVIT FOR SEEKING EXTENTION OF REGISTERED PROJECT20200215_11005677.pdf | - |
| Latest Encumbrance CertificateFile: PARK INN EC (4 files merged)_compressed.pdf | - |
| Consent letter from 2/3rd of AllotteesFile: ALL NOCS (1).pdf | - |
| Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails (1).xlsx | - |
| Document 1File: AFFIDAVIT CUM DECLARATION20200215_11024554.pdf | - |
| comence | - |
| Typical Plan | - |
| Layout | - |
| perfoma aggrement-ilovepdf-compressed | - |
| mou-ilovepdf-compressed (2) | - |
| Developement Plan | - |
| Park-Inn Brochure 11-08 | - |
| fire noc-ilovepdf-compressed | - |
| Specification & Amenities-Parkinn | - |
| EC - 27 cents | - |
| khatha | - |
| NA (1) | - |
| NA (1) | - |
| Unnamed document | - |
| Typical Plan | - |
| Balance Sheet 2015 - 2016File: Bal-15-16.pdf | - |
| Balance Sheet 2014 - 2015File: Bal-14-15.pdf | - |
| Balance Sheet 2013 - 2014File: Balance sheet-AY13-14.pdf | - |
| Audited Profit and Loss Statement 2015 - 2016File: PL-15-16.pdf | - |
| Audited Profit and Loss Statement 2014 - 2015File: PL-14-15.pdf | - |
| Audited Profit and Loss Statement 2013 - 2014File: P&L-13-14.pdf | - |
| Auditor's Report 2015 - 2016File: 3cb 15-16.pdf | - |
| Auditor's Report 2014 - 2015File: 3cb 14-15.pdf | - |
| Auditor's Report 2013 - 2014File: 3cb 13-14.pdf | - |
| Income Tax Return Acknowledgement 2015 - 2016File: ITR ACKNOWELGMENT AY-15-16.jpeg | - |
| Income Tax Return Acknowledgement 2014 - 2015File: ITR ACKNOWLEDGEMENT.jpeg | - |
| Income Tax Return Acknowledgement 2013 - 2014File: ITR ACKNOWLEDGEMENT.jpeg | - |
| Form b | - |
| Prospectus/BrochureFile: brocher.pdf | - |
| Advertisement Copy 1File: brocher.pdf | - |
| Tower Excel SheetFile: PRM_KA_RERA_1257_333_PR_180319_001244.xlsx | - |
| NOC issued by the Fire Force department after completion of workFile: Fire Noc.jpg | - |
| Occupancy CertificateFile: Completion Certificate.pdf | - |
| Consent for operation issued by KSPCBFile: POLLUTION NOC.jpeg | - |
| Certificate of operation for lifts issued by the Chief of Department of Electrical inspectorate Government of File: lift Certificate.jpg | - |
| Sanctioned Letter issued by concerned ESCOM of Power sanction and details of transformer installed and whetherFile: MESCOM NOC.jpg | - |
| Sanctioned letter issued by concerned water supply and sanitary board for the projectFile: WATER NOC.jpg | - |
| Architect certificate for having completed the work(in format no 5)File: form 6.pdf | - |
| Chartered Accountant certificate for having completed the work(in format no 4)File: PARK INN FORM4.pdf | - |
| Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: Affidavit.jpg | - |
Promoter's earlier projects2
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Status | Promised | Delivered |
|---|---|---|---|---|
| BHANDARY PACIFIC | - | Completed | Aug 2017 | No date filed |
| BHANDARY MERIDIAN | - | Completed | Aug 2017 | No date filed |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Dakshina Kannada
Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.
Keep Bhandary Parkinn on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Dakshina Kannada620+ in Dakshina Kannada
ROHAN CITY
ROHAN CORPORATION INDIA PRIVATE LIMITED
Bearys Turning Point
Bearys Properties and Developments Private
YAMUNA SKY CITY
YAMUNA HOMES AND DESIGN PRIVATE LIMITED
The Marian Park
Marian Projects Pvt Ltd
Sai Matha Garden
Matha Developers Pvt Ltd
ROHAN MARINA ONE
ROHAN PLAZA PRIVATE LIMITED
See every Dakshina Kannada project, with the district possession charts
Builder: LAKSHMISH BHANDARY
LAKSHMISH BHANDARY has 2 registrations on RERA Karnataka, including Bhandary Parkinn and bhandary heights. Its filings declare 3 earlier projects, 3 of them declared completed. Read the full track record. See more projects on the Dakshina Kannada district page.
Frequently asked questions
What are my rights if Bhandary Parkinn is delayed beyond 30 Jun 2020?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Bhandary Parkinn?
The registered promoter entity is LAKSHMISH BHANDARY. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Bhandary Parkinn?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at Bhandary Parkinn?
The professionals named in the filing: Architect: Gokulraj Associates; Engineer: K Anil Hegde. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Bhandary Parkinn?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback