Red flags

  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • No complaints on record
  • Separate project account declared
Jul 2024Possession promisedmoved 9 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 56 documents Report an error

SUKRITHI is a Mixed Development project by CITADEL DEVELOPERS in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/334/PR/190326/002493 on 26 Mar 2019. Possession is promised by 31 Jul 2024. The completion date has moved by 9 months from the original filing.

At a glance

Project

  • NameSUKRITHI
  • TypeMixed Development
  • Location
    • Mangalore
    • Dakshina Kannada
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1257/334/PR/190326/002493
  • ReraGenie IDRG-KA-87718

Builder

  • NameCITADEL DEVELOPERS
  • Entity typePartnership Firm
  • Authorized SignatorySANDEEP
  • Other registrations7 more →
  • Declared earlier projects9 →

Key dates

this monthRegisteredMar 2019First promiseOct 2023Revised toJul 2024

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on26 Mar 2019
  • Promised completion31 Jul 2024
  • Revised completionRevised to 31 Jul 2024 (originally 31 Oct 2023)
  • Buildings2 building records
  • Documents filed56 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Sukrithi Residential---1020102
Sukrithi Commercial---01919

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemYes-
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservationYes-
Energy managementYes-
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymYes-
ParksNoNot applicable
Power BackupYes-
GasYes-
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffYes-
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,978 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 40.00 cr

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionOct 2023 → Jul 2024

No reason recorded in the filing

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed56

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/334/PR/190326/002493 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: img225.jpg-
LICENSE20181128_16434255-
SITE PLAN-
Approved typical plan-
PERFORMA SALE DEED-
PERFORMA AGREEMENT-
SALE DEED20181127_14340350-
SECTION ELEVETION-
DEVELOPMENT PLAN-
ALLOTMENT LETTER-
TEMPLATE--
SPECIFICATION-
EC20181206_17214635-
affidavit 2 rera20190117_17275692-
KHATHA-
mou-
CONVERSION20181127_14470394-
Relinquishment deed20181128_17140877-
FIRE NOC20181127_12100066-
POLLUTION CONTROL20181124_17534704-
Unnamed document-
structural report-
SECTION ELEVETION-
Approved typical plan-
SECTION ELEVETION-
Legal Opinion Final20181127_19322940-
Balance Sheet 2017 - 2018File: bal sheet 2017.pdf-
Balance Sheet 2016 - 2017File: BAL SHEET 2016.jpg-
Balance Sheet 2015 - 2016File: BS 2015.jpg-
Audited Profit and Loss Statement 2017 - 2018File: P&L 2017.pdf-
Audited Profit and Loss Statement 2016 - 2017File: PL 2016.jpg-
Audited Profit and Loss Statement 2015 - 2016File: P L 2015.jpg-
Cash Flow Statement 2017 - 2018File: 2016-17.pdf-
Cash Flow Statement 2016 - 2017File: 2015-16.pdf-
Auditor's Report 2017 - 2018File: Auditors 2017.pdf-
Auditor's Report 2016 - 2017File: AU REP 2016.jpg-
Auditor's Report 2015 - 2016File: AU REP 2015.jpg-
Income Tax Return Acknowledgement 2017 - 2018File: IT 2017.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: IT returns 2016.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: 2015.jpg-
AFFIDAVIT20181124_17474002-
Prospectus/BrochureFile: Sukrithi Broucher.pdf-
Advertisement Copy 1File: Daiji Advt 2.jpg-
Tower Excel SheetFile: PRM_KA_RERA_1257_334_PR_190326_002493 Res Com.xlsx-
Loan raised documentFile: LOAN DETAILS.xlsx-
Stability CertificateFile: STABILITY SUKRITHI.pdf-
NOC issued by the Fire Force department after completion of workFile: Sukrithi FIRE OrderCertificate.pdf-
Occupancy CertificateFile: COMPLETION AND OCCUPANCY CERTIFICATE20240726_10444617.pdf-
Certificate of operation for lifts issued by the Chief of Department of Electrical inspectorate Government of File: LIFT Permission.pdf-
Sanctioned Letter issued by concerned ESCOM of Power sanction and details of transformer installed and whetherFile: MESCOM SUKRITHI COMPLETION.pdf-
Sanctioned letter issued by concerned water supply and sanitary board for the projectFile: WATER CONNECTION.jpeg-
Details of external infrastructure work such as drive way, play area, park, STP and water treatment plant, WheFile: EXTERNAL INFRASRTUCTURE.jpg-
Common Area and other amenities facilities are completed or not and details of handling over of the same to asFile: AMENITIES.jpg-
Architect certificate for having completed the work(in format no 5)File: Arch Form 5.pdf-
Chartered Accountant certificate for having completed the work(in format no 4)File: SUKRITHI FORM 4 CA.pdf-
Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: AFFIDAVIT COMPLETION.pdf-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date
ProjectLocationStatusPromisedDelivered
MAGNUM-OngoingMar 2019Not delivered

How this compares with Dakshina Kannada

30%of Dakshina Kannada projects moved their completion datethis one moved by 9 months
0%of Dakshina Kannada registrations are shown as withdrawn or revokedthis one is not

Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.

Keep SUKRITHI on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dakshina Kannada620+ in Dakshina Kannada

2 kmSUKRITHIOther 22Dot size: filed unitsN

Filed coordinates, straight-line distance. 22 registered projects within 2 km.

Builder: CITADEL DEVELOPERS

CITADEL DEVELOPERS has 8 registrations on RERA Karnataka, including MAGNUM and AURUM. Its filings declare 9 earlier projects, 6 of them declared completed. Read the full track record. See more projects on the Dakshina Kannada district page.

Frequently asked questions

What are my rights if SUKRITHI is delayed beyond 31 Jul 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SUKRITHI?

The registered promoter entity is CITADEL DEVELOPERS, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SUKRITHI?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

What should I check before booking in SUKRITHI?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SUKRITHI. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SUKRITHI to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.