The Marian Park
RG-KA-26296 · RERA PRM/KA/RERA/1257/334/PR/180905/001999
Source: official RERA Karnataka filing
Red flags
- Completion date moved by 21 months
- 2 extensions taken
Clear
- No complaints on record
- Separate project account declared
Saved.
The Marian Park is a Mixed Development project by Marian Projects Pvt Ltd in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/334/PR/180905/001999 on 5 Sep 2018. Possession is promised by 30 Sep 2024. The completion date has moved by 21 months from the original filing.
At a glance
Project
- NameThe Marian Park
- TypeMixed Development
- Location
- Mangalore
- Dakshina Kannada
- PincodeNot stated
- RERA no.PRM/KA/RERA/1257/334/PR/180905/001999
- ReraGenie IDRG-KA-26296
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on5 Sep 2018
- Promised completion30 Sep 2024
- Revised completionRevised to 30 Sep 2024 (originally 31 Dec 2022)
- Buildings1 building record
- Documents filed65 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| THE MARIAN PARK | - | - | - | 293 | 0 | 293 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | - |
| Plinth level Beam | Not applicable |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | - |
| Weather Proof work(tile,concrete) | - |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | - |
Progress on shared amenities41
Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | Yes | - |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | Yes | - |
| Street Lighting | No | Not applicable |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | Yes | - |
| Water conservation | Yes | - |
| Energy management | Yes | - |
| Fire protection and fire safety requirements | No | Not applicable |
| Education/Health/Other public amenities | Yes | - |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | Yes | - |
| Storm water drains | Yes | - |
| Use of renewable energy | No | Not applicable |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | - |
| Club House | Yes | - |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | Yes | - |
| Swimming Pool | Yes | - |
| Gym | Yes | - |
| Parks | Yes | - |
| Power Backup | Yes | - |
| Gas | Yes | - |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | Yes | - |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | Yes | - |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | Yes | - |
| Provision for lodging of management staff and security staff | Yes | - |
| Water conservation and renewable energy | Yes | - |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Saldanha & Associates |
| Engineer | NIKHIL SHANGHVI |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
No reason recorded in the filing
Reason as filed by the promoterShortage of Labour; others
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed65
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/334/PR/180905/001999 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CertificateFile: Project Incorporation.jpg | - |
| Architect Certificate for Work Completion Schedule till DateFile: EX-1 Arc certificate - work completed.pdf | - |
| Engineer Certificate for Work Completion Schedule till DateFile: EX-5 Eng certificate - work completed.pdf | - |
| CA Certificate for Funds UtilizationFile: EX3-CA certificate fund utilization.pdf | - |
| Architect Certificate for Pending Work Completion Schedule.File: EX-2 Arc certificate - work pending.pdf | - |
| Engineer Certificate for Pending Work Completion Schedule.File: EX-6 Eng certificate - work pending.pdf | - |
| CA Certificate for Funds required for Project CompletionFile: EX4-CA certificate fund required.pdf | - |
| AffidavitFile: affidavit for seeking extension.pdf | - |
| Latest Encumbrance CertificateFile: EC- 01-04-2011 TO 14-06-2023_compressed.pdf | - |
| Details Of Sold/ Un-sold UnitsFile: Sold Unsold list.xlsx | - |
| Document 1File: covid certificate-RERA.pdf | - |
| Document 2File: Notarised Affidavit for 3(1) violation.pdf | - |
| Document 3File: RERA FORM B.pdf | - |
| Document 4File: proforma AOS.pdf | - |
| Document 5File: Building licence.pdf | - |
| Document 6File: FIRE NOC 2017 - MARIAN PARK.PDF | - |
| Document 7File: Reason for Delay.pdf | - |
| Document 8File: affidavit for seeking extension.pdf | - |
| Document 9File: Affidavit paying Compensation.pdf | - |
| Document 10File: EC- 01-04-2011 TO 14-06-2023.pdf | - |
| Document 11File: KSPCB CFE-2013.pdf | - |
| Document 12File: approved plan.pdf | - |
| Document 13File: MP-Park-Form 4(WIth Annexure) (1) Q1 23-24.pdf | - |
| Document 14File: Engineer Certificate Park - Q1 23-24.pdf | - |
| Document 15File: Architect Certificate Park - Q1 23-24.pdf | - |
| Document 17File: allotment letter.pdf | - |
| Document 18File: list of allottees.pdf | - |
| Document 19File: inventory details.pdf | - |
| Document 20File: water NOC.PDF | - |
| Marian Park_Revised Licence (2) | - |
| Site Plan | - |
| Approval Plan | - |
| Amalgamation Order & Explanation Letter | - |
| Sale Agreement_Marian Park | - |
| Sale Deed | - |
| Section AA | - |
| 1st to 14th residential | - |
| Marian Park_Allottment Letter | - |
| Marian park_brochure | - |
| Explanation Letter | - |
| PROJECT SPECIFICATION | - |
| EC | - |
| Khatha | - |
| JDA | - |
| Conversion Order | - |
| Site Plan | - |
| G and 1st floor section CC | - |
| Balance Sheet 2016 - 2017File: BS_2016-2017.pdf | - |
| Balance Sheet 2015 - 2016File: BS_15-16.pdf | - |
| Balance Sheet 2014 - 2015File: P & L 2014-15.pdf | - |
| Audited Profit and Loss Statement 2016 - 2017File: P & L AY 16-17.PDF | - |
| Audited Profit and Loss Statement 2015 - 2016File: P&L 15-16.pdf | - |
| Audited Profit and Loss Statement 2014 - 2015File: Audit Report AY 14-15.pdf | - |
| Director's Report 2016 - 2017File: Directors report FY 15-16.pdf | - |
| Director's Report 2015 - 2016File: Directors report FY 14-15.pdf | - |
| Director's Report 2014 - 2015File: Director report FY 13-14.pdf | - |
| Auditor's Report 2016 - 2017File: AUDITED REPORT_2016-17.pdf | - |
| Auditor's Report 2015 - 2016File: AUDITED REPORT_2015-16.pdf | - |
| Auditor's Report 2014 - 2015File: Audit Report AY 14-15.pdf | - |
| Income Tax Return Acknowledgement 2016 - 2017File: ITR AY 16-17.pdf | - |
| Income Tax Return Acknowledgement 2015 - 2016File: ITR AY 15-16.pdf | - |
| Income Tax Return Acknowledgement 2014 - 2015File: ITR AY 14-15.pdf | - |
| Prospectus/BrochureFile: MARIAN PARK_BROUCHER.pdf | - |
| Advertisement Copy 1File: MARIAN PARK_BROUCHER.pdf | - |
| Tower Excel SheetFile: RERA CARPET AREA_NEW 13.12.18.xlsx | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Dakshina Kannada
Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.
Keep The Marian Park on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Dakshina Kannada620+ in Dakshina Kannada
ROHAN CITY
ROHAN CORPORATION INDIA PRIVATE LIMITED
Bearys Turning Point
Bearys Properties and Developments Private
YAMUNA SKY CITY
YAMUNA HOMES AND DESIGN PRIVATE LIMITED
Sai Matha Garden
Matha Developers Pvt Ltd
ROHAN MARINA ONE
ROHAN PLAZA PRIVATE LIMITED
PRESTIGE VALLEY CREST PHASE I
PRESTIGE ESTATES PROJECTS LIMTED
See every Dakshina Kannada project, with the district possession charts
Builder: Marian Projects Pvt Ltd
Marian Projects Pvt. Ltd. has 5 registrations on RERA Karnataka, including Marian Sentinel and Marian Aspire. Its filings declare 3 earlier projects, 2 of them declared completed. Read the full track record. See more projects on the Dakshina Kannada district page.
Frequently asked questions
What are my rights if The Marian Park is delayed beyond 30 Sep 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of The Marian Park?
The registered promoter entity is Marian Projects Pvt Ltd, a partnership firm as per the filing. Its CIN U45200KA2011PTC057746 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in The Marian Park?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at The Marian Park?
The professionals named in the filing: Architect: Saldanha & Associates; Engineer: NIKHIL SHANGHVI. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in The Marian Park?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.