New projects and RERA data in Mysore district, Karnataka
708 projects are registered in Mysore district: 10,929 units across the 97 that file a count, 53 registered in the last 12 months. Sales and inventory trends accumulate from each future quarterly update; this page shows the first one.
708Projects covered
53Registered, last 12 months
10,929Units declared
204Completion dates revised
20With declared litigation
Of the 708 covered registrations, 204 have revised their promised completion date and 20 declare litigation. Of the 28 that file a booking figure, the median is 34% booked as of the current data. Every figure comes from the projects' own RERA Karnataka filings.
How far Mysore possession dates have moved
Builders may revise the possession date they filed at registration. Each bar is the year a project first promised, split by how far that date has since moved. 204 of 708 projects (29%) have moved at least once; the median move is 9 months and the longest is 48 months.
Kept the original dateMoved by under 2 yearsMoved by 2 years or more
Read down a bar to see how much of that year's cohort held its promise. Facts as per filings on RERA website.
Hatched years are ones where most builders never filed a flat count, so the bar understates the real total. Read down a bar to see how much of that year's cohort held its promise. Facts as per filings on RERA website.
Where in Mysore: projects by taluka
708 of the 708 registrations on this page name their taluka.
How do I shortlist among the Mysore projects listed above?
Compare each project against its neighbours, not against the brochure. Of the 28 projects on this page that file a booking figure, the median is 34% booked, which is the benchmark to hold any single project against. A project selling much slower than the district may have a pricing or credibility problem; one selling much faster deserves a look at whether construction is keeping pace with collections. Then open the developer link to check their delivery record on other projects, and compare filed carpet areas rather than super built-up marketing areas.
What does a revised completion date on a Mysore project actually mean?
The promoter has moved their deadline with the regulator, usually under section 6, which allows an extension of up to one year for reasons beyond their control. It does not move the date in your agreement for sale: your section 18 claim for delay interest or refund runs from the possession date you signed for. Before booking a project with a revision on record, ask which approvals or works the new date depends on.
What if a Mysore project shows strong sales but slow construction?
That shape means the promoter is collecting money faster than they are building, which is fine under a disciplined promoter and dangerous under a stretched one. The law helps: withdrawals from the project account need architect, engineer and CA certificates in proportion to progress. Check the promoter's delivery record, and watch the next quarterly filing (due within 20 days of each quarter end) to see whether the construction line moves.
Does something here look wrong, or is there a number you expected to find and did not? Every figure on this page is summed from the projects' own RERA Karnataka filings, and we read every report.