Registration approved No litigation declared Residential/Group Housing project

PRAMUR VANANTARA

By Pramur Homes and Shelters

RG-KA-27592 · RERA PRM/KA/RERA/1268/378/PR/011026/008988 · Last updated on RERA Karnataka portal: 18 Sep 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Jul 2030Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 72 documents Report an error

PRAMUR VANANTARA is a Residential/Group Housing project by Pramur Homes and Shelters in Mysore, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1268/378/PR/011026/008988 on 1 Oct 2026. Possession is promised by 31 Jul 2030.

At a glance

Project

  • NamePRAMUR VANANTARA
  • TypeResidential/Group Housing
  • Location
    • MYSORE
    • 570026
  • Pincode570026
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1268/378/PR/011026/008988
  • ReraGenie IDRG-KA-27592

Builder

  • NamePramur Homes and Shelters
  • Entity typePartnership Firm
  • GSTIN29AAJFP3045R1ZI
  • Authorized SignatoryNikhil P Koundinya
  • Other registrations2 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredOct 2026PromisedJul 2030

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on1 Oct 2026
  • Promised completion31 Jul 2030
  • Revised completionNone
  • Buildings1 building record
  • Documents filed72 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PRAMUR VANATARA---69069

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 18 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Upto Plinth Level-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
Retaining wall (All types)Not applicable
RCC or MS Framed structure-
Masonry Construction-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Painting-
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work-
Internal and External work including landscapes as per sanctioned drawings-

Progress on shared amenities40

As on 18 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Sewage and Drainage SystemYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesYes-
Internal Roads & FootpathsYes-
Electricity supply transformer and substationYes-
Storm water drainsYes-
Use of renewable energyYes-
Sewage Treatment Plant (STP)Yes-
Parks & Tree plantingYes-
Street LightingNoNot applicable
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallYes-
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
Piped GasNoNot applicable
Water and SanitationYes-
Air ConditioningNoNot applicable
StaircasesYes-
LiftsYes-
Corridor/LobbiesYes-
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes-
BasementNoNot applicable
TerraceYes-
Outer WallNoNot applicable
Open parking areasYes-
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes-
Common storage spacesNoNot applicable

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,395 sq m
Named landowners2
LandownerVillageDistrict
Shubha Sanjay Urs--
Chandrashekar Raje Urs--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 30.90 cr
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 26.50 cr-
Principal sum and interest payable to financial institutions-Scheduled BanksRs 1.65 cr-
On-site expenditure-Salaries of workersRs 1.50 cr-
Payment of taxesRs 75.00 lakh-
On-site expenditure-Consultants FeesRs 50.00 lakh-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectS Prakash
EngineerArjun H R
Chartered AccountantNarayana Swamy T S

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed72

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1268/378/PR/011026/008988 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual audit and Quarterly update of previous projectFile: Annual audit AND Quarterly update of previous project.pdf18 Sep 2026
Source of FundsFile: Source of Fund.pdf18 Sep 2026
Partners ITRFile: Partners ITR.pdf18 Sep 2026
Loan amount deposited to RERA accountFile: Loan amount to be deposited to RERA account.pdf18 Sep 2026
Mutation MRFile: Latest Mutation.pdf18 Sep 2026
Title deedFile: TITLE DEED.pdf18 Sep 2026
Change of Land use order issued from the concerned development authorityFile: Change of Land use order issued from concerned authority.pdf18 Sep 2026
1. Annual audit AND Quarterly update of previous projectFile: Annual Audit Report and Quarterly Update of previous project_ASTER.pdf13 Aug 2026
2. CA KYC and Licence self attestedFile: CA KYC and Certificate Self attested.pdf13 Aug 2026
3. Source of FundsFile: Source of fund.pdf13 Aug 2026
4. MutationFile: Mutation.pdf13 Aug 2026
5. Title deeedFile: TITLE DEED.pdf13 Aug 2026
6. Survey report with Latitude and longitudeFile: Survey report.pdf13 Aug 2026
7. Sanction PlanFile: Approved Buidling Plan.pdf13 Aug 2026
8. Commencement certificateFile: Commencement certificate clarification.pdf13 Aug 2026
9. Clarification on KSPCB No of UnitsFile: Clarification on KSPCB No of Units.pdf13 Aug 2026
10. Approved Master PlanFile: Approved Master Plan.pdf13 Aug 2026
11. Original Village mapFile: Village Map.pdf13 Aug 2026
12. Approval under KTCP act from competent authorityFile: Change of Land Use.pdf13 Aug 2026
14. Amenities and facilitiesFile: Amenities and facilities.pdf13 Aug 2026
15. Project BrochureFile: Pramur Vananatara Brochure.pdf13 Aug 2026
16. Structural Stability CertificateFile: Structural Stability Certificate.pdf13 Aug 2026
17. Project SpecifiationsFile: Project Specifications.pdf13 Aug 2026
18. Proforma of AFS with account detailsFile: Proforma of agreement for sale.pdf13 Aug 2026
19. Structural Engineer Licence and clarificationFile: Structural Engineer Licence and clarification.pdf13 Aug 2026
20. Land cost calculation sheet with guidance valueFile: Land cost calculation sheet with guidance value.pdf13 Aug 2026
21. Source of waterFile: Source of Water.pdf13 Aug 2026
22. STP DrawingFile: STP Drawing.pdf13 Aug 2026
Registration CertificateFile: Registration Certificate.pdf-
GST CertificateFile: GST CERTIFICATE.pdf-
Partnership DeedFile: Partnership Deed.pdf-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: Form 1_CA Certificate.pdf-
Certificate issued by Architect Form 2File: Architect Certificate Form 2.pdf-
Certificate issued by Engineer Form 3File: Engineer Certificate Form 3.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Non Litigation Affidavit.pdf-
Balance Sheet 2024 - 2025File: Balance Sheet_2024-25.pdf-
Balance Sheet 2023 - 2024File: Balance Sheet_2023-24.pdf-
Balance Sheet 2022 - 2023File: Balance Sheet_2022-23.pdf-
Audited Profit and Loss Statement 2024 - 2025File: Audited P&L_2024-25.pdf-
Audited Profit and Loss Statement 2023 - 2024File: Audited P&L_2023-24.pdf-
Audited Profit and Loss Statement 2022 - 2023File: Audited P&L_2022-23.pdf-
Income Tax Return Acknowledgement 2024 - 2025File: ITR_2024-25.pdf-
Income Tax Return Acknowledgement 2023 - 2024File: ITR_2023-24.pdf-
Income Tax Return Acknowledgement 2022 - 2023File: ITR_2022-23.pdf-
Licence-
Approved Buidling Plan-
Approved Section of the building-
Stability certificate-
Project Specifications-
Pramur Vananatara Brochure-
Relinquishment Deed-
Proforma of agreement for sale-
Proforma of Allotment_letter-
Declaration Form B-
Affidavit for 3(1) Voliation-
JD Affidavit cum declaration-
Pramur Vanantara Advocate Search Report-
NOC_ELECTRICITY-
Water_NOC-
KSPCB NOC-
Abstract Estimate-
EKhata_CASite-
EKhata_Park-
EKhata_Road-
ADLR Survey Sketch-
Single Layout Plan-
Structural Engineer (Stability Certificate) Licence-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
Pramur AsterPramur Aster, Site no.576, Dewans Road, Chamaraja Mohalla, MysoreCompleted-No date filed

How this compares with Mysore

28%of Mysore projects moved their completion datethis one has not
0%of Mysore registrations are shown as withdrawn or revokedthis one is not

Computed across the 700+ Mysore projects on ReraGenie, from their own filings.

Keep PRAMUR VANANTARA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Mysore700+ in Mysore

2 kmPRAMUR VANANTARAOther 19Dot size: filed unitsN

Filed coordinates, straight-line distance. 19 registered projects within 2 km.

Builder: Pramur Homes and Shelters

Pramur Homes and Shelters has 3 registrations on RERA Karnataka, including PRAMUR VANANTARA and PRAMUR ASTER. Its filings declare 1 earlier project, 1 of them declared completed. Read the full track record. See more projects on the Mysore district page.

Frequently asked questions

What are my rights if PRAMUR VANANTARA is delayed beyond 31 Jul 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of PRAMUR VANANTARA?

The registered promoter entity is Pramur Homes and Shelters, a partnership firm as per the filing. Its GSTIN 29AAJFP3045R1ZI can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in PRAMUR VANANTARA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at PRAMUR VANANTARA?

The professionals named in the filing: Architect: S Prakash; Engineer: Arjun H R; Chartered Accountant: Narayana Swamy T S. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PRAMUR VANANTARA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PRAMUR VANANTARA. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PRAMUR VANANTARA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.