Home / Browse projects / Mysore, Karnataka / Brigade Topaz
Brigade Topaz
RG-KA-17446 · RERA PRM/KA/RERA/1268/378/PR/181122/002190
Source: official RERA Karnataka filing
Red flags
- Completion date moved by 9 months
- 1 extension taken
Clear
- No complaints on record
- Separate project account declared
Saved.
Brigade Topaz is a Residential/Group Housing project by Brigade Enterprises Ltd in Mysore, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1268/378/PR/181122/002190 on 22 Nov 2018. Possession is promised by 31 Dec 2021. The completion date has moved by 9 months from the original filing.
At a glance
Project
- NameBrigade Topaz
- TypeResidential/Group Housing
- Location
- MYSORE
- PincodeNot stated
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1268/378/PR/181122/002190
- ReraGenie IDRG-KA-17446
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on22 Nov 2018
- Promised completion31 Dec 2021
- Revised completionRevised to 31 Dec 2021 (originally 31 Mar 2021)
- Buildings2 building records
- Documents filed40 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A | - | - | - | 40 | 0 | 40 |
| B | - | - | - | 40 | 0 | 40 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | - |
| Plinth level Beam | Not applicable |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | - |
| Weather Proof work(tile,concrete) | - |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | - |
Progress on shared amenities41
Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | Yes | - |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | Yes | - |
| Street Lighting | Yes | - |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | Yes | - |
| Water conservation | No | Not applicable |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | Yes | - |
| Education/Health/Other public amenities | No | Not applicable |
| Electricity supply transformer and substation | No | Not applicable |
| Emergency Evacuation services | No | Not applicable |
| Storm water drains | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Water conservation/rain water harvesting/recharge of ground water | No | Not applicable |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | - |
| Club House | Yes | - |
| Community Hall | Yes | - |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | Yes | - |
| Swimming Pool | Yes | - |
| Gym | Yes | - |
| Parks | Yes | - |
| Power Backup | Yes | - |
| Gas | No | Not applicable |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | Yes | - |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | No | Not applicable |
| Open parking areas and common storage spaces | No | Not applicable |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | Yes | - |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
No reason recorded in the filing
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed40
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1268/378/PR/181122/002190 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CertificateFile: Certificate of Incorporation - BEL copy.pdf | - |
| plan sanction letter Topaz | - |
| Site Plan | - |
| Site Plan and Floor plans - Topaz | - |
| Awaiting Sale Deed Draft | - |
| Agreement to Sell RERA Brigade topaz with specs | - |
| Vendor Sale Deed & RTC | - |
| Section and elevation Topaz | - |
| Brigade Topaz - Approved Developement Plan Dt 24th July 17 | - |
| Allotment Letter- Topaz - Mysore | - |
| Topaz_RERA Brochure_14Nov18 | - |
| Specification Brigade TOPAZ | - |
| Brigade Topaz - EC from 01-04-2004 to 20-08-2018 | - |
| Brigade Topaz Katha Dt 11-1-18 | - |
| JDA and GPA Topaz | - |
| Death Certificate - Bharath Gowda | - |
| Conversion Order | - |
| Site Plan | - |
| section elevation specification | - |
| Balance Sheet 2017 - 2018File: Balance Sheet - 31-03-2017.pdf | - |
| Balance Sheet 2016 - 2017File: Balance Sheet - 31-03-2016.pdf | - |
| Balance Sheet 2015 - 2016File: Balance Sheet - 31-03-2015.pdf | - |
| Audited Profit and Loss Statement 2017 - 2018File: P&L Account - 31-03-2017.pdf | - |
| Audited Profit and Loss Statement 2016 - 2017File: P&L Account - 31-03-2016.pdf | - |
| Audited Profit and Loss Statement 2015 - 2016File: P&L Account - 31-03-2015.pdf | - |
| Director's Report 2017 - 2018File: Director's Report 2016-17.pdf | - |
| Director's Report 2016 - 2017File: Director's Report 2015-16.pdf | - |
| Director's Report 2015 - 2016File: Director's Report 2014-15.pdf | - |
| Cash Flow Statement 2017 - 2018File: Cash Flow Statement - 31-03-2017.pdf | - |
| Cash Flow Statement 2016 - 2017File: Cash Flow Statement - 31-03-2016.pdf | - |
| Auditor's Report 2017 - 2018File: Auditor's Report - 31-03-2017.pdf | - |
| Auditor's Report 2016 - 2017File: Auditor's Report - 31-03-2016.pdf | - |
| Auditor's Report 2015 - 2016File: Auditor's Report - 31-03-2015.pdf | - |
| Income Tax Return Acknowledgement 2017 - 2018File: ITR 2017.pdf | - |
| Income Tax Return Acknowledgement 2016 - 2017File: ITR 2016.pdf | - |
| Income Tax Return Acknowledgement 2015 - 2016File: ITR 2015.pdf | - |
| Topaz- Form B | - |
| Prospectus/BrochureFile: Topaz_RERA Brochure_11Jan19.pdf | - |
| Advertisement Copy 1File: Marketing - No Ad.pdf | - |
| Tower Excel SheetFile: PRM_KA_RERA_1268_378_PR_181122_002190.xlsx | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mysore
Computed across the 700+ Mysore projects on ReraGenie, from their own filings.
Keep Brigade Topaz on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Mysore700+ in Mysore
Filed coordinates, straight-line distance. 7 registered projects within 2 km.
Construction of 2446 Dus at Mandakalli Mysore
MCC
Construction of 1440 houses at lalithadripura
City Corporation Myuru
Construction of 843 G+2 Houses
Chief Officer
JAL VAYU TOWERS
AIR FORCE NAVAL HOUSING BOARD
Sanaklp Temple Tree
Sankalp Constructions private limited
SANKALP CROWN PHASE 1
SANKALP CONSTRUCTIONS PRIVATE LIMITED
See every Mysore project, with the district possession charts
Builder: Brigade Enterprises Ltd
Brigade Enterprises Ltd has 5 registrations on RERA Karnataka, including Brigade Misty Greens and Brigade Oak Tree Place. Its filings declare 37 earlier projects, 22 of them declared completed. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Mysore district page.
Frequently asked questions
What are my rights if Brigade Topaz is delayed beyond 31 Dec 2021?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Brigade Topaz?
The registered promoter entity is Brigade Enterprises Ltd, a company as per the filing. Its CIN L85110KA1995PLC019126 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Brigade Topaz?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
What should I check before booking in Brigade Topaz?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback