Home / Browse projects / Mysore, Karnataka / SERENE SAGARA

Registration approved No litigation declared Residential/Group Housing project

SERENE SAGARA

By TORAS DEVELOPERS LLP

RG-KA-60422 · RERA PRM/KA/RERA/1268/378/PR/020726/008781 · Last updated on RERA Karnataka portal: 13 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Jun 2031Possession promisedno revision filed
1 of 18Construction stages donefurthest along: Foundation footing work, 70%
87 of 113Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 106 documents Report an error

SERENE SAGARA is a Residential/Group Housing project by TORAS DEVELOPERS LLP in Mysore, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1268/378/PR/020726/008781 on 2 Jul 2026. Possession is promised by 1 Jun 2031. 26 of the 113 units on this registration are recorded sold or booked, and 1 of 18 construction stages are filed complete.

At a glance

Project

  • NameSERENE SAGARA
  • TypeResidential/Group Housing
  • Location
    • MYSORE
    • 570003
  • Pincode570003
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1268/378/PR/020726/008781
  • ReraGenie IDRG-KA-60422

Builder

  • NameTORAS DEVELOPERS LLP
  • Entity typePartnership Firm
  • LLPINACM-7219
  • GSTIN29AAXFT7193C1ZE
  • Authorized SignatoryAbhinav Sriprakash

Key dates

this monthRegisteredJul 2026PromisedJun 2031

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on2 Jul 2026
  • Promised completion1 Jun 2031
  • Revised completionNone
  • Buildings1 building record
  • Documents filed106 files

Current status

23%26 of 113 units booked
8.0%Of the estimated cost spent so far

Figures as on 13 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SERENE SAGARA---1130113

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 13 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 18 construction stages are filed complete. The stage furthest along is Foundation footing work, at 70%.

Building: 13% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work70%
Upto Plinth Level70%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)0%
Retaining wall (All types)0%
RCC or MS Framed structure0%
Masonry Construction0%
Plastering inside , outside & Ceiling0%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with network0%
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities41

As on 13 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementYes0%
Fire protection and fire safety requirementsYes0%
Solid waste management and disposalYes0%
Emergency Evacuation servicesYes0%
Internal Roads & FootpathsYes0%
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyYes0%
Sewage Treatment Plant (STP)Yes5%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseYes0%
Community HallYes0%
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityYes0%
Swimming PoolNoNot applicable
GymYes0%
ParksYes0%
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes0%
LiftsYes0%
Corridor/LobbiesYes0%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes0%
BasementYes70%
TerraceYes0%
Outer WallYes0%
Open parking areasYes0%
Provision for lodging of management staff and security staffYes0%
Water conservation and renewable energyYes0%
Common storage spacesNoNot applicable
Transformer YardYes0%

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area8,094 sq m
Named landowners2
LandownerVillageDistrict
TORAS DEVELOPERS LLP--
TORAS DEVELOPERS LLP--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 67.75 cr
Cost incurredRs 5.40 cr
Spent of the estimate7.97%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 54.00 crRs 3.81 cr
Administrative CostsRs 8.75 cr-
On-site expenditure-Consultants FeesRs 1.75 crRs 1.28 cr
Principal sum and interest payable to financial institutions-Scheduled BanksRs 1.75 cr-
Taxes, Cess or levyRs 1.50 crRs 30.80 lakh

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMohan B R
EngineerSahana. G
Chartered AccountantPerumal Madhavan

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed106

As listed on the registration, under the names the promoter filed them with; the newest 80 of 106 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1268/378/PR/020726/008781 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Certificate yafa zinnia.pdf13 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 Architect Certificate.pdf13 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer Certificate.pdf13 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)13 Oct 2026
Q2 2026-27 Fire and Safety13 Oct 2026
Building LicenceFile: 1 Building Licence.pdf29 Jun 2026
Site PlanFile: 2 Site Plan.pdf29 Jun 2026
Basement PlanFile: 2 Basement Plan.pdf29 Jun 2026
GF PlanFile: 2 GF Plan.pdf29 Jun 2026
1st 2nd 3rd Floor PlanFile: 2 1st 2nd 3rd Floor Plan.pdf29 Jun 2026
4th 5th 6th 7th 8th Floor PlanFile: 2 4th 5th 6th 7th 8th Floor Plan.pdf29 Jun 2026
Section and Elevation PlanFile: 2 Section and Elevation Plan.pdf29 Jun 2026
Commencement Certificat DeclarationFile: 3 Commencement Certificat Declaration.pdf29 Jun 2026
Amenities DetailsFile: 5 Amenities Details.pdf29 Jun 2026
Engineer License copyFile: 6 Engineer License copy.pdf29 Jun 2026
Form 3 Engineer CertificateFile: 7 Form 3 Engineer Certificate.pdf29 Jun 2026
Abstract EstimationFile: 7 Abstract Estimation.pdf29 Jun 2026
Structural Stability Certificate and LicenseFile: 8 Structural Stability Certificate and License.pdf29 Jun 2026
Structural engineer DeclarationFile: 8 Structural engineer Declaration.pdf29 Jun 2026
Structural Engineer CertificateFile: 8 Structural Engineer Certificate.pdf29 Jun 2026
Agreement for SaleFile: 9 Agreement for Sale.pdf29 Jun 2026
Allotment LetterFile: Allotment Letter.pdf29 Jun 2026
STP DrawingFile: 10 STP Drawing.pdf29 Jun 2026
Query Answer Document 29-06-2026File: Query Answer Document 29-06-2026.pdf29 Jun 2026
RTC, survey 5/1-
Mutation, survey 5/1-
Encumbrance Certificate, survey 5/1-
Conversion/Alienation Order, survey 5/1-
Sale/Title/Gift Deed, survey 5/1-
Khatha, survey 5/1-
RTC, survey 5/6-
Mutation, survey 5/6-
Encumbrance Certificate, survey 5/6-
Conversion/Alienation Order, survey 5/6-
Sale/Title/Gift Deed, survey 5/6-
Khatha, survey 5/6-
Registration CertificateFile: Toras Developers LLP Incorporation Certificate.pdf-
GST CertificateFile: Toras Developers LLP GST.pdf-
Partnership DeedFile: Toras Developers LLP Partnership Deed.pdf-
Partner Details-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: Toras Developers LLP Form 1 CA Certificate.pdf-
Certificate issued by Architect Form 2File: Toras Developers LLP Form 2 Architect Certificate.pdf-
Certificate issued by Engineer Form 3File: Toras Developers LLP Form 3 Engineer Certificate.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Toras Developers LLP Affidavit - No litigation.pdf-
Balance Sheet 2024 - 2025File: Toras Developers LLP Balance Sheet FY 2024-25.pdf-
Balance Sheet 2023 - 2024File: Toras Developers LLP Financial declaration.pdf-
Balance Sheet 2022 - 2023File: Toras Developers LLP Financial declaration.pdf-
Audited Profit and Loss Statement 2024 - 2025File: Toras Developers LLP Profit and Loss FY 2024-25.pdf-
Audited Profit and Loss Statement 2023 - 2024File: Toras Developers LLP Financial declaration.pdf-
Audited Profit and Loss Statement 2022 - 2023File: Toras Developers LLP Financial declaration.pdf-
Income Tax Return Acknowledgement 2024 - 2025File: Toras Developers LLP ITR FY 2024-25.pdf-
Income Tax Return Acknowledgement 2023 - 2024File: Toras Developers LLP Financial declaration.pdf-
Income Tax Return Acknowledgement 2022 - 2023File: Toras Developers LLP Financial declaration.pdf-
Toras Developers LLP Sanction Letter-
Toras Developers LLP Site Plan-
Toras Developers LLP Section and Elevation-
Toras Developers LLP Structural Stability Certificate and License-
Toras Developers LLP Project Specifications-
Toras Developers LLP Relinquishment Deed-
Toras Developers LLP Agreement for Sale-
Toras Developers LLP Allotment Letter-
Toras Developers LLP Affidavit- Form B-
Toras Developers LLP Affidavit- Sec 3(1) Non Violation-
Toras Developers LLP Legal Report-
Toras Developers LLP Affidavit - CESCOM and Temporary ELC Supply receipt-
Toras Developers LLP Affidavit- Water NOC-
Toras Developers LLP KSPCB NOC-
Unnamed document-
Toras Developers LLP Fire NOC-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-

How this compares with Mysore

23%of this project is bookeddistrict median 34%
28%of Mysore projects moved their completion datethis one has not
0%of Mysore registrations are shown as withdrawn or revokedthis one is not

Computed across the 700+ Mysore projects on ReraGenie, from their own filings.

Keep SERENE SAGARA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Mysore700+ in Mysore

2 kmSERENE SAGARAOther 5Dot size: filed unitsN

Filed coordinates, straight-line distance. 5 registered projects within 2 km.

Builder: TORAS DEVELOPERS LLP

TORAS DEVELOPERS LLP has 1 registration on RERA Karnataka, including SERENE SAGARA. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Mysore district page.

Frequently asked questions

What are my rights if SERENE SAGARA is delayed beyond 1 Jun 2031?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SERENE SAGARA?

The registered promoter entity is TORAS DEVELOPERS LLP, a partnership firm as per the filing. Its LLPIN ACM-7219 and GSTIN 29AAXFT7193C1ZE can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SERENE SAGARA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SERENE SAGARA?

The professionals named in the filing: Architect: Mohan B R; Engineer: Sahana. G; Chartered Accountant: Perumal Madhavan. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SERENE SAGARA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SERENE SAGARA. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SERENE SAGARA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.