Red flags

  • 6 complaints at RERA Karnataka
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Separate project account declared
Aug 2020Possession promisedmoved 12 months from the original
6Complaints at RERA Karnatakaon this registration
Jump to the 66 documents Report an error

JAL VAYU TOWERS is a Residential/Group Housing project by AIR FORCE NAVAL HOUSING BOARD in Mysore, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1268/378/PR/171214/001637 on 14 Dec 2017. Possession is promised by 31 Aug 2020. The completion date has moved by 12 months from the original filing. 6 complaints are on record with the regulator.

At a glance

Project

  • NameJAL VAYU TOWERS
  • TypeResidential/Group Housing
  • Location
    • MYSORE
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1268/378/PR/171214/001637
  • ReraGenie IDRG-KA-71432

Builder

  • NameAIR FORCE NAVAL HOUSING BOARD
  • Entity typeOther
  • Authorized SignatoryBS NIROLA
  • OthersBS NIROLA

Key dates

this monthRegisteredDec 2017First promiseAug 2019Revised toAug 2020

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on14 Dec 2017
  • Promised completion31 Aug 2020
  • Revised completionRevised to 31 Aug 2020 (originally 31 Aug 2019)
  • Buildings12 building records
  • Documents filed66 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BLOCK1A (3.5BHK DUPLEX)---24024
TOWER 1B (3.5 BHK DUPLEX)---24024
BLOCK 1C (3.5 BHK DUPLEX)---24024
BLOCK 1D (3.5 BHK DUPLEX)---24024
BLOCK1E (3.5 BHK DUPLEX)---24024
BLOCK 1F (3.5BHK DUPLEX)---24024
BLOCK 2A (3.5BHK SIMPLEX)---48048
BLOCK 2B (3.5BHK SIMPLEX)---48048
BLOCK 2C (3.5BHK SIMPLEX)---48048
BLOCK 3 (CLUB HOUSE)---000
BLOCK 4 (3 BHK)---60060
BLOCK 5 (2 BHK)---40040

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)Not applicable
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingNoNot applicable
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalNoNot applicable
Water conservationNoNot applicable
Energy managementYes-
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes-
Emergency Evacuation servicesYes-
Storm water drainsYes-
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseYes-
Community HallYes-
Outdoor Sports facilityYes-
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffYes-
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area53,119 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 171.08 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMr Ramesh
EngineerMr GVB Nandeeswara Rao

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EX/PRM/KA/RERA/1268/378/PR/220620/001637Aug 2019 → Aug 2020

Reason as filed by the promoterFinancial crunch

Complaints filed with RERA Karnataka6

Case no.ComplainantRespondentFiled
CMP/190405/0002577-AIR FORCE NAVAL HOUSING BOARD05/04/2019
CMP/190416/0002587-AIR FORCE NAVAL HOUSING BOARD16/04/2019
CMP/190702/0003427-AIR FORCE NAVAL HOUSING BOARD02/07/2019
CMP/191219/0005023-AIR FORCE NAVAL HOUSING BOARD19/12/2019
CMP/201127/0007033-AIR FORCE NAVAL HOUSING BOARD27/11/2020
CMP/201127/0007034-AIR FORCE NAVAL HOUSING BOARD27/11/2020

Documents filed66

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1268/378/PR/171214/001637 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: AFNHB_Incorporation.pdf-
Architect Certificate for Work Completion Schedule till DateFile: Arc certificate work completed.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: engg comp.pdf-
CA Certificate for Funds UtilizationFile: CA Certificate(Fund Utilisation).pdf-
Architect Certificate for Pending Work Completion Schedule.File: Arc certificate - work pending.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: engg pending.pdf-
CA Certificate for Funds required for Project CompletionFile: CA Certificate (Funds Required).pdf-
AffidavitFile: AFFIDAVIT.pdf-
Latest Encumbrance CertificateFile: ENCUMBRANCE CERTIFICATE.pdf-
Details Of Sold/ Un-sold UnitsFile: Details of Sold-Unsold flats.pdf-
NOC DetailsFile: AAI.pdf-
Document 1File: ACCOUNT STATEMENT MYSORE.pdf-
Document 2File: Letter to RERA 24.1.20.pdf-
Document 3File: AFFIDAVIT CUM DECLARATION.pdf-
Document 4File: AFFIDAVIT FOR EXTN..pdf-
Document 5File: AFFIDAVIT FOR CHANGE OF BANK.pdf-
Document 6File: Authoriity letter 24.1.20.pdf-
Document 7File: ACCOUNT STATEMENT 1.pdf-
Document 8File: ACCOUNT STATEMENT 2.pdf-
Document 9File: CA cert n mysore.pdf-
Document 10File: Revised Affidavit 28.2.20.pdf-
Document 11File: CA cert n mysore.pdf-
Document 12File: ACCOUNT STATEMENT 1.pdf-
Document 13File: ACCOUNT STATEMENT 2.pdf-
Document 14File: AFFIDAVIT (TEMPLATE-6).pdf-
Document 15File: Rera 2.pdf-
Document 16File: Rera 2a.pdf-
Document 17File: Rera 1.pdf-
Document 18File: Rera 3.pdf-
commencement certificate mysore_001-
Approved building plan-
Layout approval mysore-
Agreement for Sale-
Agreement for Sale-
Land Agreement Deed Mysore-
Proposed Site Plan with area statement-
Area Diagram Tower A,B,C &D-
Format of Allotment letter-
mysore_technical_brochure-
NOC electricity Mysore-
mysore_project_specification_opt-
Encumbrance Certificate_archive-
Mutation Mysore-
Mysore_Contract_document_opt-
Land Convervsion Mysore-
Balance Sheet 2015 - 2016File: 16_BalanceSheet_opt.pdf-
Balance Sheet 2014 - 2015File: 15_BalanceSheet_opt.pdf-
Balance Sheet 2013 - 2014File: 14_BalanceSheet_opt.pdf-
Audited Profit and Loss Statement 2015 - 2016File: 16_BalanceSheet_opt.pdf-
Audited Profit and Loss Statement 2014 - 2015File: 15_BalanceSheet_opt.pdf-
Audited Profit and Loss Statement 2013 - 2014File: 14_BalanceSheet_opt.pdf-
Director's Report 2015 - 2016File: 16_Notes_opt.pdf-
Director's Report 2014 - 2015File: 15_Notes_opt.pdf-
Director's Report 2013 - 2014File: 14_Notes_opt.pdf-
Cash Flow Statement 2015 - 2016File: 16_BalanceSheet_opt.pdf-
Cash Flow Statement 2014 - 2015File: 15_BalanceSheet_opt.pdf-
Auditor's Report 2015 - 2016File: 16_Audit_Report_opt.pdf-
Auditor's Report 2014 - 2015File: 15_Audit_Report_opt.pdf-
Auditor's Report 2013 - 2014File: 14_Audit_Report_opt.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: IT Exemption Certificate.pdf-
Income Tax Return Acknowledgement 2014 - 2015File: IT Exemption Certificate.pdf-
Income Tax Return Acknowledgement 2013 - 2014File: IT Exemption Certificate.pdf-
form-A mysore-
Prospectus/BrochureFile: Technical Brochure.pdf-
Advertisement Copy 1File: Advertisement.pdf-
Tower Excel SheetFile: PRM_KA_RERA_1268_378_PR_171214_001637.xlsx-

How this compares with Mysore

28%of Mysore projects moved their completion datethis one moved by 12 months
0%of Mysore registrations are shown as withdrawn or revokedthis one is not

Computed across the 700+ Mysore projects on ReraGenie, from their own filings.

Keep JAL VAYU TOWERS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Mysore700+ in Mysore

2 kmJAL VAYU TOWERSOther 5Dot size: filed unitsN

Filed coordinates, straight-line distance. 5 registered projects within 2 km.

Builder: AIR FORCE NAVAL HOUSING BOARD

AIR FORCE NAVAL HOUSING BOARD has 1 registration on RERA Karnataka, including JAL VAYU TOWERS. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Mysore district page.

Frequently asked questions

What are my rights if JAL VAYU TOWERS is delayed beyond 31 Aug 2020?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of JAL VAYU TOWERS?

The registered promoter entity is AIR FORCE NAVAL HOUSING BOARD. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in JAL VAYU TOWERS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against JAL VAYU TOWERS?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at JAL VAYU TOWERS?

The professionals named in the filing: Architect: Mr Ramesh; Engineer: Mr GVB Nandeeswara Rao. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in JAL VAYU TOWERS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About JAL VAYU TOWERS. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save JAL VAYU TOWERS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.