Home / Browse projects / Mysore, Karnataka / Sowparnika The Landmark
Sowparnika The Landmark
By SOWPARNIKA PROJECTS AND INFRASTRUCTURE PRIVATE LIMITED
RG-KA-37186 · RERA PRM/KA/RERA/1268/378/PR/180504/001612 · Last updated on RERA Karnataka portal: 23 May 2022
Source: official RERA Karnataka filing
Red flags
- Completion date moved by 48 months
- 3 extensions taken
Clear
- No complaints on record
- Separate project account declared
Saved.
Sowparnika The Landmark is a Residential/Group Housing project by SOWPARNIKA PROJECTS AND INFRASTRUCTURE PRIVATE LIMITED in Mysore, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1268/378/PR/180504/001612 on 4 May 2018. Possession is promised by 30 Sep 2025. The completion date has moved by 48 months from the original filing.
At a glance
Project
- NameSowparnika The Landmark
- TypeResidential/Group Housing
- Location
- MYSORE
- PincodeNot stated
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1268/378/PR/180504/001612
- ReraGenie IDRG-KA-37186
Builder
- NameSOWPARNIKA PROJECTS AND INFRASTRUCTURE PRIVATE LIMITED
- Entity typeCompany
- CINU45201KA2007PTC043166
- Authorized SignatoryMEENAKSHI RAMJI
- OthersMOHAMAD ZEAULLA
- Other registrations1 more →
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on4 May 2018
- Promised completion30 Sep 2025
- Revised completionRevised to 30 Sep 2025 (originally 30 Sep 2021)
- Buildings1 building record
- Documents filed84 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| 1 | - | - | - | 130 | 0 | 130 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 23 May 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | - |
| Plinth level Beam | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | - |
| Weather Proof work(tile,concrete) | - |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | - |
Progress on shared amenities41
As on 23 May 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | Yes | - |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | Yes | - |
| Street Lighting | Yes | - |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes | - |
| Solid waste management and disposal | Yes | - |
| Water conservation | Yes | - |
| Energy management | Yes | - |
| Fire protection and fire safety requirements | Yes | - |
| Education/Health/Other public amenities | Yes | - |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | Yes | - |
| Storm water drains | Yes | - |
| Use of renewable energy | Yes | - |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | - |
| Club House | Yes | - |
| Community Hall | Yes | - |
| Outdoor Sports facility | Yes | - |
| Indoor Sports facility | Yes | - |
| Swimming Pool | Yes | - |
| Gym | Yes | - |
| Parks | Yes | - |
| Power Backup | Yes | - |
| Gas | No | Not applicable |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | Yes | - |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | Yes | - |
| Provision for lodging of management staff and security staff | Yes | - |
| Water conservation and renewable energy | Yes | - |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
No reason recorded in the filing
Reason as filed by the promoterothers
No reason recorded in the filing
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed84
As listed on the registration, under the names the promoter filed them with; the newest 80 of 84 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1268/378/PR/180504/001612 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Bank statement tilld dateFile: AXIS BANK 3598_merged file.pdf | 23 May 2022 |
| RERA Registration CertificateFile: Covid Extension Land Mark RERA Certificate.pdf | 23 May 2022 |
| Affidavit Form B project end dateFile: Affidavit Cum Declaration Form B.pdf | 23 May 2022 |
| Affidavit seeking extension in Form EX 7File: Affidavit Form Ex-7.pdf | 23 May 2022 |
| List of sold and unsold units with list of alloteesFile: Form 4 - Annexure - Landmark.pdf | 23 May 2022 |
| Affidavit as per section 18(1) of RERA actFile: Affidavit Sec 18.pdf | 23 May 2022 |
| Affidavit seeking extension for the Registered projectFile: Affidavit Form Ex-7.pdf | 23 May 2022 |
| Project Cost detailsFile: Statement of total Project cost.pdf | 23 May 2022 |
| Project Architech detailsFile: COUNCIL OF ARCHITECTURE.pdf | 23 May 2022 |
| BHKwise break up of the development detailsFile: Landmark BHKwise developed Area.pdf | 23 May 2022 |
| Certificate of structural safety of the buildingFile: LAND MARK PROJECT STABILITY CERTIFICATE 20-05-2022.pdf | 23 May 2022 |
| water NOCFile: Water NOC.pdf | 23 May 2022 |
| Airport NOCFile: AAI noc comp2.pdf | 23 May 2022 |
| Project Engineer detailsFile: BBMP LICENSE 2023.jpg | 23 May 2022 |
| Proforma of agreement of sale notified by the GOKFile: Agreement Format Landmark.pdf | 23 May 2022 |
| STP demarcation site plan along with STP design drawingFile: RERA_STP LOCATION DRAWING.pdf | 23 May 2022 |
| STP demarcation site plan along with STP design drawingFile: STP PROCESS FLOW DIAGRAM.pdf | 23 May 2022 |
| CertificateFile: SPIPL - COI.jpeg | - |
| Project Details | - |
| Architect Certificate for Work Completion Schedule till DateFile: Form-Ex1Architect Certificate.pdf | - |
| Engineer Certificate for Work Completion Schedule till DateFile: Form-Ex5 Engineers Certificate.pdf | - |
| CA Certificate for Funds UtilizationFile: Form-Ex3 The Landmark.pdf | - |
| Architect Certificate for Pending Work Completion Schedule.File: Form-Ex2 Architect Certificate.pdf | - |
| Engineer Certificate for Pending Work Completion Schedule.File: Form-Ex6 Engineers Certificate.pdf | - |
| CA Certificate for Funds required for Project CompletionFile: Form-Ex4 The Landmark.pdf | - |
| AffidavitFile: Form B Affidavit cum Declaration.pdf | - |
| Latest Encumbrance CertificateFile: The LandMark - ECs.pdf | - |
| Consent letter from 2/3rd of AllotteesFile: Consent letters.pdf | - |
| Details Of Sold/ Un-sold UnitsFile: Form 4 - Annexure for sold and unsold Units.pdf | - |
| The LandMark - Commencement Certificate | - |
| Plan - Page II Compressed | - |
| The LandMark - Single Plot Approval | - |
| The LandMark - RERA Draft Sale Deed | - |
| The LandMark - RERA Draft Agreement of Sale | - |
| The LandMark - Sale Deed & RTC | - |
| Plan - Page III | - |
| Plan - Page I Compressed | - |
| The LandMark - Draft Allotment Letter | - |
| The LandMark - Brochure | - |
| The LandMark - Specs | - |
| The LandMark - ECs Revised | - |
| The LandMark - Khatha | - |
| The LandMark - JDA & POA | - |
| The LandMark - Land Conversion Order | - |
| The LandMark - Relinquishment Deed | - |
| The LandMark - NOC - Fire | - |
| The LandMark - NOC - CHESCOM | - |
| The LandMark - NOC - KSPCB | - |
| Plan - Page IV | - |
| The LandMark - Single Plot Approval | - |
| The LandMark - Plan SanctionS - Combined (4 Sheets) | - |
| The LandMark - Land Conversion Order | - |
| The LandMark - Legal Report | - |
| Balance Sheet 2016 - 2017File: Balance Sheet - 16-17.pdf | - |
| Balance Sheet 2015 - 2016File: Balance Sheet - 15-16.pdf | - |
| Balance Sheet 2014 - 2015File: Balance Sheet - 14-15.pdf | - |
| Audited Profit and Loss Statement 2016 - 2017File: P & L Account - 16-17.pdf | - |
| Audited Profit and Loss Statement 2015 - 2016File: P & L Account - 15-16.pdf | - |
| Audited Profit and Loss Statement 2014 - 2015File: Auditors Report 14-15.pdf | - |
| Director's Report 2016 - 2017File: Directors Report - 16-17.pdf | - |
| Director's Report 2015 - 2016File: Directors Report - 15-16.pdf | - |
| Director's Report 2014 - 2015File: Directors Report 14-15.pdf | - |
| Cash Flow Statement 2016 - 2017File: Cash Flow Statement - 16-17.pdf | - |
| Cash Flow Statement 2015 - 2016File: Cash Flow Statement - 15-16.pdf | - |
| Auditor's Report 2016 - 2017File: Audit Report - 16-17.pdf | - |
| Auditor's Report 2015 - 2016File: Audit Report - 15-16.pdf | - |
| Auditor's Report 2014 - 2015File: Auditors Report 14-15.pdf | - |
| Income Tax Return Acknowledgement 2016 - 2017File: ITR - V - 16-17.pdf | - |
| Income Tax Return Acknowledgement 2015 - 2016File: ITR - V - 15-16.pdf | - |
| Income Tax Return Acknowledgement 2014 - 2015File: ITR V - 14-15.pdf | - |
| The LandMark - Declaration in Form B Under RERA | - |
| Prospectus/BrochureFile: Landmark-Bi-Fold-Final-Print-30-07-18-lowres.pdf | - |
| Advertisement Copy 1File: landmark ad.pptx | - |
| Tower Excel SheetFile: The Land Mark.xlsx | - |
| Delay ReasonFile: Landmark Reason for the delay.pdf | - |
| Stability CertificateFile: LANDMARK STR STABILITY CERT.pdf | - |
| NOC issued by the Fire Force department after completion of workFile: Fire NOC Land Mark.pdf | - |
| Occupancy CertificateFile: Landmark - Occupancy Certificate.pdf | - |
| Consent for operation issued by KSPCBFile: KSPCB NOC Land Mark.pdf | - |
| Sanctioned Letter issued by concerned ESCOM of Power sanction and details of transformer installed and whetherFile: Landmark - Power Sanction letter.pdf | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mysore
Computed across the 700+ Mysore projects on ReraGenie, from their own filings.
Keep Sowparnika The Landmark on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Mysore700+ in Mysore
Filed coordinates, straight-line distance. 15 registered projects within 2 km.
Construction of 2446 Dus at Mandakalli Mysore
MCC
Construction of 1440 houses at lalithadripura
City Corporation Myuru
Construction of 843 G+2 Houses
Chief Officer
JAL VAYU TOWERS
AIR FORCE NAVAL HOUSING BOARD
Sanaklp Temple Tree
Sankalp Constructions private limited
SANKALP CROWN PHASE 1
SANKALP CONSTRUCTIONS PRIVATE LIMITED
See every Mysore project, with the district possession charts
Builder: SOWPARNIKA PROJECTS AND INFRASTRUCTURE PRIVATE LIMITED
SOWPARNIKA PROJECTS AND INFRASTRUCTURE PRIVATE LIMITED has 2 registrations on RERA Karnataka, including SOWPARNIKA BLUE BELLS and Sowparnika The Landmark. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Mysore district page.
Frequently asked questions
What are my rights if Sowparnika The Landmark is delayed beyond 30 Sep 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Sowparnika The Landmark?
The registered promoter entity is SOWPARNIKA PROJECTS AND INFRASTRUCTURE PRIVATE LIMITED, a company as per the filing. Its CIN U45201KA2007PTC043166 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Sowparnika The Landmark?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
What should I check before booking in Sowparnika The Landmark?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.