Home / Browse projects / Mysore, Karnataka / Vaishnaoi Eternis
Vaishnaoi Eternis
By GAYATRI VAISHNAOI CONSTRUCTIONS PRIVATE LIMITED
RG-KA-93216 · RERA PRM/KA/RERA/1268/378/PR/180420/001535
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
Vaishnaoi Eternis is a Residential/Group Housing project by GAYATRI VAISHNAOI CONSTRUCTIONS PRIVATE LIMITED in Mysore, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1268/378/PR/180420/001535 on 20 Apr 2018. Possession is promised by 8 Jan 2019.
At a glance
Project
- NameVaishnaoi Eternis
- TypeResidential/Group Housing
- Location
- MYSORE
- PincodeNot stated
- RERA no.PRM/KA/RERA/1268/378/PR/180420/001535
- ReraGenie IDRG-KA-93216
Builder
- NameGAYATRI VAISHNAOI CONSTRUCTIONS PRIVATE LIMITED
- Entity typeCompany
- CINU45200TG2015PTC098274
- Authorized SignatoryChakilam Sesha Giri Rao
- DirectorsAEDLA KRISHNA REDDY, Y SHARATH CHANDRA, Y HEMA CHANDRA
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on20 Apr 2018
- Promised completion8 Jan 2019
- Revised completionNone
- Buildings2 building records
- Documents filed47 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Vaishnaoi Eternis B | - | - | - | 34 | 0 | 34 |
| Vaishnaoi Eternis A | - | - | - | 26 | 0 | 26 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | - |
| Plinth level Beam | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | Not applicable |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | - |
Progress on shared amenities41
Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | No | Not applicable |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes | - |
| Solid waste management and disposal | No | Not applicable |
| Water conservation | No | Not applicable |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Education/Health/Other public amenities | Yes | - |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | Yes | - |
| Storm water drains | Yes | - |
| Use of renewable energy | No | Not applicable |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | - |
| Club House | Yes | - |
| Community Hall | Yes | - |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | Yes | - |
| Swimming Pool | Yes | - |
| Gym | Yes | - |
| Parks | No | Not applicable |
| Power Backup | Yes | - |
| Gas | No | Not applicable |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | Yes | - |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | No | Not applicable |
| Provision for lodging of management staff and security staff | Yes | - |
| Water conservation and renewable energy | Yes | - |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed47
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1268/378/PR/180420/001535 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CertificateFile: certificate(1).pdf | - |
| Mis 31 | - |
| Approval and Plan | - |
| Plan | - |
| Agreement Draft | - |
| Agreement Draft | - |
| Sales deed | - |
| Approval and Plan | - |
| Allotment | - |
| Brochure | - |
| EC Copys | - |
| Khatha present owners | - |
| JDA | - |
| Conversion Copy | - |
| Approval and Plan | - |
| Approval and Plan | - |
| land Conversion | - |
| 13 x 18 cm | - |
| Balance Sheet 2016 - 2017File: Company Financial 171.jpg | - |
| Balance Sheet 2015 - 2016File: Document1.pdf | - |
| Balance Sheet 2014 - 2015File: Document1.pdf | - |
| Audited Profit and Loss Statement 2016 - 2017File: Company Financial 172.jpg | - |
| Audited Profit and Loss Statement 2015 - 2016File: Document1.pdf | - |
| Audited Profit and Loss Statement 2014 - 2015File: Document1.pdf | - |
| Director's Report 2015 - 2016File: Document1.pdf | - |
| Director's Report 2014 - 2015File: Document1.pdf | - |
| Cash Flow Statement 2016 - 2017File: Document1.pdf | - |
| Cash Flow Statement 2015 - 2016File: Document1.pdf | - |
| Auditor's Report 2016 - 2017File: AR.pdf | - |
| Auditor's Report 2015 - 2016File: Document1.pdf | - |
| Auditor's Report 2014 - 2015File: Document1.pdf | - |
| Income Tax Return Acknowledgement 2016 - 2017File: ITR 2017-18.pdf | - |
| Income Tax Return Acknowledgement 2015 - 2016File: Document1.pdf | - |
| Income Tax Return Acknowledgement 2014 - 2015File: Document1.pdf | - |
| Dec | - |
| Prospectus/BrochureFile: Brochure.pdf.pdf | - |
| Advertisement Copy 1File: Brochure.pdf.pdf | - |
| Tower Excel SheetFile: PRMKARERA1268378PR180420001535.xlsx | - |
| Loan raised documentFile: Loan SBI.pdf | - |
| Occupancy CertificateFile: OC.PDF | - |
| Consent for operation issued by KSPCBFile: PCB.pdf | - |
| Certificate of operation for lifts issued by the Chief of Department of Electrical inspectorate Government of File: Electrical Inspectorate.pdf | - |
| Sanctioned Letter issued by concerned ESCOM of Power sanction and details of transformer installed and whetherFile: Electricity permission.pdf | - |
| Sanctioned letter issued by concerned water supply and sanitary board for the projectFile: Water connection.pdf | - |
| Architect certificate for having completed the work(in format no 5)File: Form5 Completion.PDF | - |
| Chartered Accountant certificate for having completed the work(in format no 4)File: FORM4.pdf | - |
| Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: Affidavit.pdf | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mysore
Computed across the 700+ Mysore projects on ReraGenie, from their own filings.
Keep Vaishnaoi Eternis on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Mysore700+ in Mysore
Construction of 2446 Dus at Mandakalli Mysore
MCC
Construction of 1440 houses at lalithadripura
City Corporation Myuru
Construction of 843 G+2 Houses
Chief Officer
JAL VAYU TOWERS
AIR FORCE NAVAL HOUSING BOARD
Sanaklp Temple Tree
Sankalp Constructions private limited
SANKALP CROWN PHASE 1
SANKALP CONSTRUCTIONS PRIVATE LIMITED
See every Mysore project, with the district possession charts
Builder: GAYATRI VAISHNAOI CONSTRUCTIONS PRIVATE LIMITED
GAYATRI VAISHNAOI CONSTRUCTIONS PRIVATE LIMITED has 1 registration on RERA Karnataka, including Vaishnaoi Eternis. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Mysore district page.
Frequently asked questions
What are my rights if Vaishnaoi Eternis is delayed beyond 8 Jan 2019?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Vaishnaoi Eternis?
The registered promoter entity is GAYATRI VAISHNAOI CONSTRUCTIONS PRIVATE LIMITED, a company as per the filing. Its CIN U45200TG2015PTC098274 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Vaishnaoi Eternis?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
What should I check before booking in Vaishnaoi Eternis?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback