Home / Browse projects / Mysore, Karnataka / AAKARACROPOLIS
AAKARACROPOLIS
RG-KA-57476 · RERA PRM/KA/RERA/1268/378/PR/180808/001978
Source: official RERA Karnataka filing
Red flags
- Completion date moved by 9 months
- 1 extension taken
Clear
- No complaints on record
- Separate project account declared
Saved.
AAKARACROPOLIS is a Residential/Group Housing project by AAKAR PROPERTIES in Mysore, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1268/378/PR/180808/001978 on 8 Aug 2018. Possession is promised by 30 Jun 2021. The completion date has moved by 9 months from the original filing.
At a glance
Project
- NameAAKARACROPOLIS
- TypeResidential/Group Housing
- Location
- MYSORE
- PincodeNot stated
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1268/378/PR/180808/001978
- ReraGenie IDRG-KA-57476
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on8 Aug 2018
- Promised completion30 Jun 2021
- Revised completionRevised to 30 Jun 2021 (originally 30 Sep 2020)
- Buildings1 building record
- Documents filed49 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BLOCK A | - | - | - | 42 | 0 | 42 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | Not applicable |
| Retaining wall (All types) | Not applicable |
| Plinth level Beam | Not applicable |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Not applicable |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | Not applicable |
| Plastering inside , outside & Ceiling | Not applicable |
| Joinery: Doors, Windows, Ventilators etc | Not applicable |
| Basic work of Water supply, Sanitary and Electrification | Not applicable |
| Dadoing, Skirting, Flooring, Tiles work (All types) | Not applicable |
| Railing and Grill fixing | Not applicable |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | - |
| Weather Proof work(tile,concrete) | - |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | - |
Progress on shared amenities41
Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | Yes | - |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | Yes | - |
| Street Lighting | Yes | - |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes | - |
| Solid waste management and disposal | Yes | - |
| Water conservation | No | Not applicable |
| Energy management | Yes | - |
| Fire protection and fire safety requirements | No | Not applicable |
| Education/Health/Other public amenities | Yes | - |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | No | Not applicable |
| Storm water drains | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Water conservation/rain water harvesting/recharge of ground water | No | Not applicable |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | - |
| Club House | Yes | - |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | Yes | - |
| Swimming Pool | Yes | - |
| Gym | Yes | - |
| Parks | Yes | - |
| Power Backup | Yes | - |
| Gas | No | Not applicable |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | Yes | - |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | No | Not applicable |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | Yes | - |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | Yes | - |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | CHANDAN C |
| Engineer | H S DEEPAK |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
No reason recorded in the filing
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed49
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1268/378/PR/180808/001978 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CertificateFile: Firm Registration Certificate new.pdf | - |
| Commencement certificate | - |
| Approved building plan | - |
| Approved Layout plan | - |
| Proforma of Sale deed | - |
| Proforma of Sale Agreement | - |
| sale deed and RTC | - |
| Approved Section of building | - |
| ADP | - |
| allotment_letter_of_akar | - |
| aakar-arcopolis-v10-rera | - |
| Projects Specifications | - |
| new encumberance certificates | - |
| Khatha | - |
| JDA | - |
| Relinquishment Deed | - |
| Fire Force Department NOC | - |
| Airport Authority NOC | - |
| CHESCOM NOC | - |
| MWSSB NOC | - |
| KSPCB NOC (2) | - |
| Approved Layout plan | - |
| sectandspec | - |
| Conversion certificate | - |
| Balance Sheet 2016 - 2017File: Balance Sheet 16-17.PDF | - |
| Balance Sheet 2015 - 2016File: Balance sheet 15-16.pdf | - |
| Balance Sheet 2014 - 2015File: Balance sheet 14-15.PDF | - |
| Audited Profit and Loss Statement 2016 - 2017File: P & L Statement 16-17.PDF | - |
| Audited Profit and Loss Statement 2015 - 2016File: P & L Statement 15-16.pdf | - |
| Audited Profit and Loss Statement 2014 - 2015File: P & L Statement 14-15.PDF | - |
| Director's Report 2016 - 2017File: DIRECRORS REPORT.pdf | - |
| Director's Report 2015 - 2016File: DIRECRORS REPORT.pdf | - |
| Director's Report 2014 - 2015File: DIRECRORS REPORT.pdf | - |
| Cash Flow Statement 2016 - 2017File: CASH FLOW STATEMENT.pdf | - |
| Cash Flow Statement 2015 - 2016File: CASH FLOW STATEMENT.pdf | - |
| Auditor's Report 2016 - 2017File: Auditor Report 16-17.pdf | - |
| Auditor's Report 2015 - 2016File: Auditor Report 15-16.pdf | - |
| Auditor's Report 2014 - 2015File: Auditor Report 14-15.pdf | - |
| Income Tax Return Acknowledgement 2016 - 2017File: ITR Acknowledgernent 16-17.pdf | - |
| Income Tax Return Acknowledgement 2015 - 2016File: ITR Acknowledgement 15-16.pdf | - |
| Income Tax Return Acknowledgement 2014 - 2015File: ITR acknowledgement 14-15.pdf | - |
| DECLARATION FORM B | - |
| Prospectus/BrochureFile: ACROPOLIS BROCHURE.pdf | - |
| Advertisement Copy 1File: Ad. image.jpg | - |
| Tower Excel SheetFile: PRM_KA_RERA_1268_378_PR_180808_001978.xlsx | - |
| Occupancy CertificateFile: Applied.pdf | - |
| Completion certificate issued by the competent authorityFile: Completion report - Block A.pdf | - |
| Registered Agreement of SaleFile: Not yet done.pdf | - |
| Registered conveyance deed for an individual unitFile: Not yet done.pdf | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mysore
Computed across the 700+ Mysore projects on ReraGenie, from their own filings.
Keep AAKARACROPOLIS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Mysore700+ in Mysore
Construction of 2446 Dus at Mandakalli Mysore
MCC
Construction of 1440 houses at lalithadripura
City Corporation Myuru
Construction of 843 G+2 Houses
Chief Officer
JAL VAYU TOWERS
AIR FORCE NAVAL HOUSING BOARD
Sanaklp Temple Tree
Sankalp Constructions private limited
SANKALP CROWN PHASE 1
SANKALP CONSTRUCTIONS PRIVATE LIMITED
See every Mysore project, with the district possession charts
Builder: AAKAR PROPERTIES
AAKAR PROPERTIES has 3 registrations on RERA Karnataka, including AAKARACROPOLIS and Aakar Acropolis D & B. Its filings declare 1 earlier project, none of them declared completed. Read the full track record. See more projects on the Mysore district page.
Frequently asked questions
What are my rights if AAKARACROPOLIS is delayed beyond 30 Jun 2021?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of AAKARACROPOLIS?
The registered promoter entity is AAKAR PROPERTIES, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in AAKARACROPOLIS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at AAKARACROPOLIS?
The professionals named in the filing: Architect: CHANDAN C; Engineer: H S DEEPAK. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in AAKARACROPOLIS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback