New projects and RERA data in Mumbai City district, Maharashtra
793 projects are registered in Mumbai City district: 39,215 units across them, 113 registered in the last 12 months. Sales and inventory trends accumulate from each future quarterly update; this page shows the first one.
Of the 793 covered registrations, 286 have revised their promised completion date and 95 declare litigation. The median project here is 17% booked as of the current data. Every figure comes from the projects' own MahaRERA filings.
Mumbai monthly RERA report
What registered month by month, this city against its own twelve-month run and against the other six, with the possession pipeline, the taluka split and the busiest pincodes. Built from the same filings as this page. It covers Mumbai City and Mumbai Suburban together, which is what MahaRERA files as this market.
October 2026: 88 new registrations, 5,277 homes and units, 4 complaints filed.
When Mumbai City projects promise possession
Promised possession year as filed by the builder with MahaRERA, split by what the registration says today. Of 793 projects with a promised date, 215 are recorded delivered, 388 are still on the register and 190 have a registration that has lapsed or been cancelled.
DeliveredOn the registerRegistration lapsed or cancelled
435 projects promise possession in 2026 or later. Years outside 2017 to 2035 hold 2 further projects and are not shown. Facts as per filings on RERA website.
35,960 flats are promised in 2026 or later, across the 84% of those projects that file a flat count. Hatched years are ones where most builders never filed a count, so the bar understates real supply and cannot be compared with the years beside it. Years outside 2017 to 2035 hold 2 further projects and are not shown. Facts as per filings on RERA website.
How far Mumbai City possession dates have moved
Builders may revise the possession date they filed at registration. Each bar is the year a project first promised, split by how far that date has since moved. 285 of 793 projects (36%) have moved at least once; the median move is 24 months and the longest is 132 months.
Kept the original dateMoved by under 2 yearsMoved by 2 years or more
Read down a bar to see how much of that year's cohort held its promise. Facts as per filings on RERA website.
Hatched years are ones where most builders never filed a flat count, so the bar understates the real total. Read down a bar to see how much of that year's cohort held its promise. Facts as per filings on RERA website.
Redevelopment in Mumbai City
307 of the 793 registrations on this page (39%) show a redevelopment on their own filing. Over the last 12 months it is 85 of 113 new registrations (75%). See all 307 in the project list.
MahaRERA has no redevelopment field, so this is ReraGenie's reading of the filings. A registration counts only when its own filing shows it: flats filed as rehab units (MahaRERA's column for homes returned to existing occupants or owners), a sanction from a slum rehabilitation authority, a MHADA layout in Mumbai, a redevelopment, tenant or alternate accommodation agreement among its documents, or a project name that says so. A redevelopment whose filing shows none of these is not counted, so the true number is higher.
| Kind | Registrations | Flats filed | Of which rehab |
|---|---|---|---|
| Housing societies and other buildings | 234 | 15,345 | 7,852 |
| Slum rehabilitation | 60 | 11,199 | 720 |
| MHADA layouts | 13 | 1,236 | 168 |
Redevelopment registrations by year
| Year | Redevelopment | All | Filed the unit table | Share among those |
|---|---|---|---|---|
| 2018* | 9 | 49 | 18% | 78% |
| 2019* | 10 | 34 | 41% | 64% |
| 2020* | 5 | 29 | 41% | 42% |
| 2021 | 15 | 37 | 57% | 67% |
| 2022 | 34 | 78 | 65% | 65% |
| 2023 | 31 | 56 | 77% | 67% |
| 2024 | 22 | 38 | 84% | 69% |
| 2025 | 57 | 72 | 90% | 86% |
| 2026 (so far) | 72 | 98 | 93% | 79% |
Rehab units, the commonest sign of a redevelopment, are filed in the building unit table, and most registrations before 2023 did not file that table. So the count in older years is lower than the truth by more, and a rise down the second column is partly filing. The last column holds the filing still: it is the share among registrations that did file the table, and it is the one to read as a trend. Starred years are ones where fewer than half filed it.
52 more registered in 2017, the year registration began, alongside every project already under way at the time, so that year is a backlog and not a launch year and is left out of the table.
When they promise possession
Each row is the year a redevelopment promised possession, split by what its registration says today. Completed is the only completion signal MahaRERA publishes, and it sits on the year the project promised, not the year it finished. Completed and lapsed registrations are mostly older ones, which filed the unit table less often, so those two columns understate more than the middle one.
| Promised for | Completed | On the register | Lapsed or cancelled |
|---|---|---|---|
| 2022 | 0 | 0 | 2 |
| 2023 | 1 | 0 | 1 |
| 2024 | 2 | 0 | 3 |
| 2025 | 3 | 0 | 16 |
| 2026 | 9 | 42 | 9 |
| 2027 | 2 | 53 | 0 |
| 2028 | 0 | 37 | 0 |
| 2029 | 0 | 42 | 0 |
| 2030 | 0 | 29 | 0 |
| 2031 | 0 | 29 | 0 |
The largest redevelopments on the register
AARADHYA AVAAN (545 flats filed), SATTVA SUMERA (528 flats filed), Island Cove (523 flats filed), North Tower - Tower 3 (496 flats filed), Avhad Millate (385 flats filed), MINERVA (372 flats filed), Siddha Sky Phase 2 (369 flats filed), Siddha Sky Phase 4 (365 flats filed).
Permissions and land in Mumbai City
Who sanctions building in Mumbai City
447 of the 793 registrations on this page name the body that sanctioned their building plan. The rest leave that box empty, which is a gap in the filing and not a project without permission: the commencement certificate is filed as a separate document and is on the file for most projects. The body named here is where a commencement or occupancy certificate is verified.
| Sanctioning authority | Projects |
|---|---|
| MCGM | 363 |
| Slum Rehabilitation Authority | 46 |
| 17 other bodies | 38 |
One body is often filed under several spellings, and those are counted together. Acronyms that could mean two different bodies are not: PMC is Pune or Pimpri Chinchwad depending who typed it, so it is counted as filed.
Whose name the land is in
Every one of the 793 registrations on this page answers this: on 477 the promoter is the only owner named; on 224 the promoter is an owner with other names on the file, which is what a joint development looks like on paper; on 92 the promoter is not an owner. Where other names are on the file, ask which of them signs your agreement for sale. A landowner who is not a party to it is a question for your lawyer before you pay, not a defect in the project.
Where in Mumbai City: projects by taluka
793 of the 793 registrations on this page name their taluka.
| Taluka | Projects | Share |
|---|---|---|
| Mumbai City | 565 | 71% |
| Ward GNorth | 118 | 15% |
| Ward FNorth | 47 | 6% |
| Ward ABCD | 27 | 3% |
| 3 other talukas | 36 | 5% |
Projects in Mumbai City
Showing 1 to 60 of 793 projects.
Largest first, by the unit count in the filing.
| Project | Developer | Units | Booked | Registered | Status |
|---|---|---|---|---|---|
| NATHANI HEIGHTS SALEmumbai central, 400011 | Nathani Parekh Constructions Private Limited | 815 | 82% | 31 Aug 2017 | Registered |
| AARADHYA AVAANNANA CHOWK, 400007Redevelopment | SHREEPATI SKIES (R R CHATURVEDI) | 545 | 30% | 12 Jan 2023 | Registered |
| SATTVA SUMERADADAR-NAIGAON, 400012Slum rehabilitation | ALPERTON DEVELOPERS AND CONTRACTORS PRIVATE LIMITED | 528 | 4% | 2 Mar 2026 | Registered |
| Island CoveMahim, 400016Slum rehabilitation | LH Residential Housing Private Limited | 523 | 85% | 22 Jun 2022 | Registered |
| North Tower - Tower 3saatraasta, 400011Slum rehabilitation | Glider Buildcon Realtors | 496 | 95% | 31 May 2019 | Registered |
| Piramal Aranya - Wing BByculla East, 400010 | Glider Buildcon Realtors Private Limited | 480 | 69% | 10 Oct 2018 | Registration lapsed |
| Godrej Horizon Phase IWadala, 400031 | Godrej Projects Development Ltd | 400 | 94% | 28 Apr 2022 | Registered |
| Avhad MillateMahim West, 400016Slum rehabilitation | HRUB INFRA PROJECTS PRIVATE LIMITED | 385 | 0% | 6 Nov 2026 | Registered |
| DOSTI EASTERN BAY - PHASE 3WADALA EAST, 400037 | DOSTI REALTY LTD | 377 | 97% | 3 Dec 2021 | Registered |
| South TowerSaatraasta, 400011Slum rehabilitation | Glider Buildcon Realtors | 376 | 82% | 28 Mar 2018 | Registration lapsed |
| MINERVALOWER PAREL, 400011Slum rehabilitation | Lokhandwala Kataria Construction Private Limited | 372 | 82% | 18 Aug 2017 | Registered |
| Siddha Sky Phase 2Raoli Camp, Kokari Agar, Sadar Nagar No. 4, Near GTB Monorail Station, Sion Koliwada., 400037Slum rehabilitation | M/s Sejal Shakti Realtors LLP | 369 | 89% | 31 May 2019 | Registered |
| 7 Mahalaxmi - Tower 3Lower Parel, 400013 | Runwal Real Estates Private Limited | 368 | 0% | 15 May 2026 | Registered |
| Siddha Sky Phase 4Raoli Camp, Kokari Agar, Sadar Nagar 4, Sion Koliwada, Besides GTB Nagar Monorail Station, 400037Slum rehabilitation | Sejal Shakti Realtors LLP | 365 | 16% | 27 May 2019 | Registered |
| Lodha BellevueByculla, 400011 | Lodha Developers Limited | 360 | 60% | 13 Aug 2022 | Registered |
| Siddha Sky Phase 1Raoli Camp, Kokari Agar, Sadar Nagar No 4, GTB Monorail station, Sion Koliwada, 400037Slum rehabilitation | Sejal Shakti Realtors LLP | 357 | 89% | 27 May 2019 | Registration lapsed |
| Siddha Sky Phase 3Raoli Camp Kokri Nagar, Sardar Nagar No. 4, GTB Monorail Station, 400037Slum rehabilitation | M/s. Sejal Shakti Realtors LLP | 357 | 85% | 31 May 2019 | Registered |
| Lodha Sewri ProjectSewree, 400015Slum rehabilitation | Lodha Developers Limited | 354 | 0% | 16 Mar 2026 | Registered |
| Proposed Redevelopment of existing Transit Camp at Sion, Construction of 91 EWS T/s. 285 Transit T/s +19 shops, 31 LIG T/s, 56 MIG T/s, on land bearing CS. No. 4(Pt.) salt pan Dn. F/N ward at Sion PH -V, MumbaiSion, 400022Redevelopment | Maharashtra Housing and Area Development Authority | 352 | 0% | 18 Apr 2026 | Registered |
| Piramal Aranya - Wing CByculla East, 400010 | Glider Buildcon Realtors Private Limited | 337 | 75% | 5 Apr 2019 | Registered |
| Daffodil HeightsMumbai CIty, 400078Slum rehabilitation | Shree Krishna Constructions | 326 | 40% | 26 Sep 2017 | Registered |
| One MarinaChira Bazar Chandanwadi, 400002 | VALENCIA AND MISHAL VENTURES PVT LTD | 318 | 58% | 14 Feb 2019 | Registered |
| EMBASSY CITADELLOWER PAREL, 400018 | EQUINOX INDIA INFRAESTATE LIMITED, SPERO PROPERTIES AND SERVICES PRIVATE LIMITED | 316 | 12% | 29 Dec 2025 | Registered |
| SOBHA InizioParel Sewree Division, 400015Slum rehabilitation | SOBHA LIMITED | 312 | 7% | 21 Nov 2025 | Registered |
| SERENE CITYMumbai City, 400086 | SANGHVI BUILDTECH LLP | 308 | 5% | 29 Jul 2017 | Registration lapsed |
| Midtown BayMahim, 400016Slum rehabilitation | Rising Sun Impex Private Limited | 298 | 121% | 17 Aug 2021 | Completed |
| Piramal Aranya - Ahan 2Byculla East, 400010 | Glider Buildcon Realtors Private Limited | 292 | 45% | 27 Jun 2023 | Registered |
| Simana - Wing B - Phase 1Parel, 400033 | Bhoomi Properties | 292 | 55% | 16 Feb 2022 | Registered |
| 7 Mahalaxmi - Tower 1Lower Parel, 400013 | Runwal Real Estates Private Limited | 271 | 49% | 25 Sep 2024 | Registered |
| Labdhi SeabreezeF-NORTH WARD, WADALA, 400037Slum rehabilitation | Labdhi Siddhivinayak Realtors LLP | 268 | 98% | 2 Jan 2020 | Registered |
| Island Cove Tower 4Mumbai City, 400016Slum rehabilitation | LH Residential Housing Private Limited, Shree Nidhi Concept Realtors Private Limited and Bhoomi Habitat | 256 | 0% | 15 Sep 2025 | Registered |
| La BellezaBhuleshwar Division, 400002Redevelopment | Qaswa Enterprises | 256 | 3% | 5 Apr 2023 | Registered |
| AL AMIR APARTMENTDongri, 400009Redevelopment | JANZEB AMIRKAMAL KHAN | 255 | 35% | 17 Aug 2017 | Registered |
| 10 HARBOUR ESTATESMAZGAON, 400010Slum rehabilitation | NAN ENTERPRISES | 250 | 20% | 29 May 2021 | Registered |
| Bayline ResidencesMahim Taluka, Mahim City at Lady Jamshetji Road, Mahim (W), G N Ward, 400016Slum rehabilitation | HRUB Infra Projects Pvt Ltd | 241 | 4% | 11 Feb 2026 | Registered |
| BKC EDGEDharavi, 400017Slum rehabilitation | Labdhi Bliss Private Limited | 241 | 14% | 27 Oct 2017 | Registered |
| Ruparel MillenniaSewree, 400012Slum rehabilitation | Renuka Realtors | 237 | 72% | 8 Nov 2021 | Registration lapsed |
| Simana - Wing A - Phase 1Parel, 400033 | Bhoomi Properties | 237 | 62% | 16 Feb 2022 | Registration lapsed |
| The Address by GS Tower 2Shashtri Nagar Sion East, 400022Slum rehabilitation | TEN X Realty East Limited , Messrs Renaissance Spaces | 236 | 41% | 29 Dec 2025 | Registered |
| The Address by GS Tower 3Shashtri Nagar sion east, 400022Slum rehabilitation | TEN X Realty East Limited , Messrs Renaissance Spaces | 233 | 36% | 26 Dec 2025 | Registered |
| Bellevue Tower - 3Byculla, 400011 | Lodha Developers Limited | 231 | 86% | 19 Aug 2022 | Registered |
| Piramal Aranya - Wing AByculla East, 400010 | Glider Buildcon Realtors Private Limited | 229 | 65% | 5 Aug 2017 | Completed |
| RUNWAL RAAYA - TOWER 2Lower Parel, 400013 | AETHON DEVELOPERS PRIVATE LIMITED | 226 | 7% | 7 May 2025 | Registered |
| FUEGOMumbai City, 400008 | HILTON INFRASTRUCTURE | 220 | 56% | 22 Aug 2017 | Registered |
| Presidence EterniaMazgaon, 400010Redevelopment | ABU ENTERPRISES | 219 | 0% | 23 Sep 2026 | Registered |
| One India TowerOthers, 400010Redevelopment | One India Constructions Private Limited | 217 | 28% | 19 Aug 2017 | Registered |
| The Address by GS Tower 4Shashtri Nagar Sion East, 400022Slum rehabilitation | TEN X Realty East Limited, Messrs Renaissance Spaces | 217 | 0% | 26 Dec 2025 | Registered |
| Imperial T3 Wing CTardeo, 400034Slum rehabilitation | S. D. Corporation Private Limited | 215 | 0% | 20 Feb 2026 | Registered |
| Imperial T3 Wing C1Tardeo, 400034Slum rehabilitation | S D CORPORATION PRIVATE LIMITED | 212 | 0% | 27 Jul 2026 | Registered |
| SHIVSOLITAIREJogeshwari, 400060Slum rehabilitation | SO LUCKY BUILDERS | 212 | 87% | 16 Aug 2017 | Completed |
| SKY 27OFF LBS MARG, NEAR MANGATRAM PETROL PUMP, 400078Slum rehabilitation | Space Developers | 212 | 53% | 31 Jan 2024 | Registered |
| AJMAL-235Nagpada, 400008Redevelopment | AWFI REAL ESTATE PRIVATE LIMITED | 210 | 0% | 21 Apr 2025 | Registered |
| CODENAME MATUNGA ORIGINSDADAR MATUNGA DIVISION, MATUNGA (C.R), 400019Redevelopment | J. P. INFRA (MUMBAI) PRIVATE LIMITED | 208 | 0% | 16 Oct 2025 | Registered |
| Kohinoor Square Phase 1Dadar West, 400028 | Kohinoor CTNL Infrastructure Company Private Limited | 199 | 100% | 9 Aug 2017 | Registration lapsed |
| Mahindra BeaconHillByculla, 400011 | Mahindra Lifespace Developers limited | 199 | 0% | 6 May 2026 | Registered |
| Lodha Worli Residential ProjectWorli, 400025Slum rehabilitation | Lodha Developers Limited | 195 | 0% | 23 Jan 2026 | Registered |
| Rustomjee Vista BaySCHEME 57 OF SEWRI WADALA ESTATE, 400031MHADA redevelopment | Xcellent Realty Private Limited | 195 | 6% | 1 Jan 2026 | Registered |
| RUNWAL RAAYA - TOWER 1LOWER PAREL, 400013 | AETHON DEVELOPERS PRIVATE LIMITED | 193 | 31% | 15 May 2025 | Registered |
| AR HorizonNagpada, 400008Redevelopment | Tattva & Mittal Realty Private Limited | 192 | 0% | 20 Nov 2026 | Registered |
| Prestige Ocean Towers - SouthCharni Road, 400002 | Prestige Projects Private Limited | 192 | 24% | 11 Jun 2024 | Registered |
Developers active in Mumbai City
SURAJ ESTATE DEVELOPERS LTD (13), Lodha Developers Limited (10), TWENTY FIVE DOWNTOWN REALTY LIMITED (6), GURUKRUPA REALCON LIFESPACES LLP (5), Ten X Realty Limited (5), National Happy Homes (5). Each link opens the promoter's track record built from their own filings.
Frequently asked questions
How do I shortlist among the Mumbai City projects listed above?
Compare each project against its neighbours, not against the brochure. The median project on this page is 17% booked, which is the benchmark to hold any single project against. A project selling much slower than the district may have a pricing or credibility problem; one selling much faster deserves a look at whether construction is keeping pace with collections. Then open the developer link to check their delivery record on other projects, and compare filed carpet areas rather than super built-up marketing areas.
What does a revised completion date on a Mumbai City project actually mean?
The promoter has moved their deadline with the regulator, usually under section 6, which allows an extension of up to one year for reasons beyond their control. It does not move the date in your agreement for sale: your section 18 claim for delay interest or refund runs from the possession date you signed for. Before booking a project with a revision on record, ask which approvals or works the new date depends on.
What stamp duty will I pay on a flat in Mumbai City district?
The whole district falls inside BMC limits: 6 percent of the property value for men and joint buyers, 5 percent for a woman buying in her sole name, metro cess included. The registration fee is 1 percent of value, capped at Rs 30,000. Duty is charged on the higher of your agreement value and the ready reckoner value. ReraGenie has a free Maharashtra stamp duty calculator under Tools.
What does it mean that some Mumbai City registrations have lapsed?
A RERA registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then, the registration lapses and the project stops being a registered project: the promoter may not legally market or sell in it, and the Authority can act under section 7 against a defaulting promoter. It does not cancel your agreement for sale or your section 18 rights if you have already booked, and it does not mean construction has stopped. Ask the promoter for the current registration position in writing, and verify it on the MahaRERA portal before you pay any further instalment.
What if a Mumbai City project shows strong sales but slow construction?
That shape means the promoter is collecting money faster than they are building, which is fine under a disciplined promoter and dangerous under a stretched one. The law helps: withdrawals from the project account need architect, engineer and CA certificates in proportion to progress. Check the promoter's delivery record, and watch the next quarterly filing (due within 20 days of each quarter end) to see whether the construction line moves.