Completed No litigation declared Residential / Group Housing project

Midtown Bay

By Rising Sun Impex Private Limited

RG-MH-30041 · RERA P51900030390 · Last updated on MahaRERA portal: 22 Jun 2026

Source: official MahaRERA filing

Red flags

  • 4 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai City registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedregistration recorded completed
11 of 11Construction stages doneevery applicable stage filed complete
0 of 298Units unsoldnot recorded sold or booked
4Complaints at MahaRERAon this registration
Jump to the 163 documents Report an error

Midtown Bay is a Residential / Group Housing project by Rising Sun Impex Private Limited in Mumbai City, Maharashtra, registered with MahaRERA as P51900030390 on 17 Aug 2021. The registration is recorded completed; possession was promised by 31 Dec 2027. 361 of the 298 units on this registration are recorded sold or booked, and 11 of 11 construction stages are filed complete. 4 complaints are on record with the regulator.

At a glance

Project

  • NameMidtown Bay
  • TypeResidential / Group Housing
  • Location
    • Sitladevi mandir Road
    • Mahim
    • Mumbai City
    • 400016
  • Pincode400016
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900030390
  • ReraGenie IDRG-MH-30041

Builder

  • NameRising Sun Impex Private Limited
  • Entity typeCompany
  • CINU52396TG2009PTC066022
  • DirectorsVinay Surendra Kedia, Vedanshu Nitin Kedia, Vijay Kumar Puranmal Khowala, Rajkumar Mohanlal Mawatwal

Key dates

this monthRegisteredAug 2021PromisedDec 2027Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on17 Aug 2021
  • Promised completion31 Dec 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed163 files

Current status

121%361 of 298 units booked
100.0%Work done, per cost certificate

Figures as on 22 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Midtown BayNA49352980298

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 22 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

Midtown Bay: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 22 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable

Parking filed430

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots430
Closed/Covered430

Land and ownership2

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,784 sq m
Land owned byNot the promoter
Named landowners2
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on10 Jul 2025
LandownerVillageDistrict
HRUB Infra Projects Private LimitedMumbai CityMumbai City
MCGMAndheriMumbai Suburban

Approvals and building plan

Sanctioning authoritySLUM REHABILITATION AUTHORITY
Permissible FSI23376.82
Proposed, not sanctioned21,422 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMadhuban CHS Ltd, Service Road, Panchpakhadi, Thane West
Estimated costRs 214.07 cr
Cost incurredRs 214.07 cr
Work done100.0%
BuildingWingEstimatedIncurred
Midtown BayNARs 211.33 crRs 211.33 cr
-NARs 2.74 crRs 2.74 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSKYLINE INFRAMART CONSULTANTS LLP
EngineerSajid Idrisi
Chartered AccountantSANDEEP RATHI & ASSOCIATES
Chartered Accountantmayank tibrewala
PartnerRole in project
Rising Sun Impex Private Limited-

Litigation declared2

CaseCourtStatus
Stamp No 16616/2021High Court BombayDisposed Off vide order dated Twelfth August Two Thousand and Twenty One
Stamp No 16645/2021High Court BombayDisposed Off vide order dated Twelfth August Two Thousand and Twenty One

Complaints filed with MahaRERA4

Case no.ComplainantRespondentFiled
CC12400969Sunil SharmaManoj Sadanand Mantri02/12/2024
CC12500578Abhijit Vishwanath MoreRising Sun Impex Private Limited19/02/2025
CC12601223Bina Shashak KolwalkarRising Sun Impex Private Limited06/03/2026
CC12601232Bina Shashak KolwalkarRising Sun Impex Private Limited06/03/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 11 Aug 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 11 Mar 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 5 Aug 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 17 Mar 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed163

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 163 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupational CertificateFile: Full OC midtownbay.pdf22 Jun 2026
Occupational CertificateFile: MYSCAN_20260227_0001.PDF22 Jun 2026
Occupational CertificateFile: MYSCAN_20260227_0002.PDF22 Jun 2026
Occupational CertificateFile: MYSCAN_20260227_0003.PDF22 Jun 2026
Occupational CertificateFile: MYSCAN_20260227_0004.PDF22 Jun 2026
Occupational CertificateFile: MYSCAN_20260227_0005.PDF22 Jun 2026
Occupational CertificateFile: MYSCAN_20260227_0006.PDF22 Jun 2026
Occupational CertificateFile: MYSCAN_20260227_0007.PDF22 Jun 2026
Occupational CertificateFile: MYSCAN_20260227_0008.PDF22 Jun 2026
Occupational CertificateFile: MYSCAN_20260227_0009.PDF22 Jun 2026
Occupational CertificateFile: MYSCAN_20260227_0010.PDF22 Jun 2026
Occupational CertificateFile: MYSCAN_20260227_0011.PDF22 Jun 2026
Occupational CertificateFile: MYSCAN_20260227_0012.PDF22 Jun 2026
Occupational CertificateFile: MYSCAN_20260227_0013.PDF22 Jun 2026
Occupational CertificateFile: MYSCAN_20260227_0014.PDF22 Jun 2026
Occupational CertificateFile: MYSCAN_20260227_0015.PDF22 Jun 2026
Occupational CertificateFile: MYSCAN_20260227_0016.PDF22 Jun 2026
Occupational CertificateFile: MYSCAN_20260227_0017.PDF22 Jun 2026
Occupational CertificateFile: MYSCAN_20260227_0018.PDF22 Jun 2026
Occupational CertificateFile: MYSCAN_20260227_0019.PDF22 Jun 2026
Occupational CertificateFile: MYSCAN_20260227_0020.PDF22 Jun 2026
Occupational CertificateFile: MYSCAN_20260227_0021.PDF22 Jun 2026
Occupational CertificateFile: MYSCAN_20260227_0022.PDF22 Jun 2026
Occupational CertificateFile: MYSCAN_20260227_0023.PDF22 Jun 2026
Occupational CertificateFile: MYSCAN_20260227_0024.PDF22 Jun 2026
Occupational CertificateFile: MYSCAN_20260227_0025.PDF22 Jun 2026
Occupational CertificateFile: MYSCAN_20260227_0026.PDF22 Jun 2026
Occupational CertificateFile: MYSCAN_20260227_0027.PDF22 Jun 2026
Occupational CertificateFile: MYSCAN_20260227_0028.PDF22 Jun 2026
Occupational CertificateFile: MYSCAN_20260227_0029.PDF22 Jun 2026
Occupational CertificateFile: MYSCAN_20260227_0030.PDF22 Jun 2026
Occupational CertificateFile: MYSCAN_20260227_0031.PDF22 Jun 2026
Occupational CertificateFile: MYSCAN_20260227_0032.PDF22 Jun 2026
Occupational CertificateFile: MYSCAN_20260227_0033.PDF22 Jun 2026
Occupational CertificateFile: MYSCAN_20260227_0034.PDF22 Jun 2026
Occupational CertificateFile: MYSCAN_20260227_0035.PDF22 Jun 2026
Occupational CertificateFile: MYSCAN_20260227_0036.PDF22 Jun 2026
Occupational CertificateFile: MYSCAN_20260227_0037.PDF22 Jun 2026
Occupational CertificateFile: MYSCAN_20260227_0038.PDF22 Jun 2026
Occupational CertificateFile: MYSCAN_20260227_0039.PDF22 Jun 2026
Occupational CertificateFile: MYSCAN_20260227_0040.PDF22 Jun 2026
Occupational CertificateFile: MYSCAN_20260227_0041.PDF22 Jun 2026
Occupational CertificateFile: MYSCAN_20260227_0042.PDF22 Jun 2026
Occupational CertificateFile: MYSCAN_20260227_0043.PDF22 Jun 2026
Withdrawal Update Form 1File: Form 1 Signed.pdf20 May 2026
Withdrawal Update Form 2File: Form 2 Sale Signed.pdf20 May 2026
Withdrawal Update Form 3File: Form 3 RSIPL Signed.pdf20 May 2026
Withdrawal Update Form 1File: Form 1 Signed.pdf16 May 2026
Withdrawal Update Form 2File: Form 2 Sale Signed.pdf16 May 2026
Withdrawal Update Form 3File: Form 3 RSIPL Signed.pdf16 May 2026
Layout approvalFile: Plans 1 to 25-1-3.pdf11 Mar 2026
Layout approvalFile: Plans 1 to 25-4-6.pdf11 Mar 2026
Layout approvalFile: Plans 1 to 25-7-8.pdf11 Mar 2026
Layout approvalFile: Plans 1 to 25-9-10.pdf11 Mar 2026
Layout approvalFile: Plans 1 to 25-11-13.pdf11 Mar 2026
Layout approvalFile: Plans 1 to 25-14-16.pdf11 Mar 2026
Layout approvalFile: Plans 1 to 25-17-19.pdf11 Mar 2026
Layout approvalFile: Plans 1 to 25-20-22.pdf11 Mar 2026
Layout approvalFile: Plans 1 to 25-22-25.pdf11 Mar 2026
Layout approvalFile: Plans 26 to 43-1.pdf11 Mar 2026
Layout approvalFile: Plans 26 to 43-2.pdf11 Mar 2026
Layout approvalFile: Plans 26 to 43-3.pdf11 Mar 2026
Layout approvalFile: Plans 26 to 43-4.pdf11 Mar 2026
Layout approvalFile: Plans 26 to 43-5.pdf11 Mar 2026
Layout approvalFile: Plans 26 to 43-6.pdf11 Mar 2026
Withdrawal Update Form 1File: Form 1_Dec 25.pdf31 Jan 2026
Withdrawal Update Form 2File: Form 2_Sep 25 Sale.pdf31 Jan 2026
Withdrawal Update Form 3File: Form 3_Dec 25 RSIPL REVISED.pdf31 Jan 2026
Withdrawal Update Form 1File: Form 1_Sep 25.pdf12 Nov 2025
Withdrawal Update Form 2File: Form 2_Sep 25 Sale.pdf12 Nov 2025
Withdrawal Update Form 3File: midtown bay june 25 final 2025.pdf12 Nov 2025
Withdrawal Update Form 1File: Form 1 Architect Certificate 300625.pdf8 Nov 2025
Withdrawal Update Form 2File: Form 2 Engineer Certificate Sale Rehab 300625.pdf8 Nov 2025
Withdrawal Update Form 3File: midtown bay june 25 final 2025.pdf8 Nov 2025
Form 5 (FY 2024-2025)File: midtown bay form 5.pdf29 Sep 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate 310325.pdf19 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate 310325.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate 310325.pdf19 Apr 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Inventory 310325.pdf19 Apr 2025
Commencement Certificates / NA Order for plotted developmentFile: Full CC for Sale Building dtd 12032025.pdf17 Mar 2025

How this compares with Mumbai City

121%of this project is bookeddistrict median 17%
33%of Mumbai City projects moved their completion datethis one has not
25%of Mumbai City registrations have lapsed or been cancelledthis one is completed

Computed across the 780+ Mumbai City projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Midtown Bay on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Mahim780+ in Mumbai City

2 kmMidtown BayCompleted 73Lapsed / revoked 59Other 85Dot size: filed unitsN

Filed coordinates, straight-line distance. 217 registered projects within 2 km.

Builder: Rising Sun Impex Private Limited

Rising Sun Impex Private Limited has 1 registration on MahaRERA, including Midtown Bay. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai City district page.

Frequently asked questions

What are my rights if Midtown Bay is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Midtown Bay?

The registered promoter entity is Rising Sun Impex Private Limited, a company as per the filing. Its CIN U52396TG2009PTC066022 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Midtown Bay?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Midtown Bay?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Midtown Bay?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Midtown Bay?

The professionals named in the filing: Architect: SKYLINE INFRAMART CONSULTANTS LLP; Engineer: Sajid Idrisi; Chartered Accountant: SANDEEP RATHI & ASSOCIATES; Chartered Accountant: mayank tibrewala. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Midtown Bay?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Midtown Bay. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Midtown Bay to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.