MAHARASHTRA HOUSING AND AREA DEVELOPMENT AUTHORITY: RERA track record

Public Authority ยท attribution by exact filing name, entity resolution in progress

MAHARASHTRA HOUSING AND AREA DEVELOPMENT AUTHORITY has 12 registrations in this build, including PLOT NO 3 CHARKOP SECTOR 8 and Planning, Designing, Constuction and Obtaining Necessary Approvals for 72 HIG t/s on lumpsum Turnkey. Its filings disclose 9 earlier MahaRERA projects: 0 of 6 past projects completed on time.

12Registrations in this build
9Past projects disclosed
+63 monthsMedian delivery slip
0Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
PLOT NO 3 CHARKOP SECTOR 8Mumbai Suburban, Maharashtra--Completed
Planning, Designing, Constuction and Obtaining Necessary Approvals for 72 HIG t/s on lumpsum TurnkeyMumbai Suburban, Maharashtra--Registration lapsed
PLOT NO.2Mumbai Suburban, Maharashtra--Completed
Constn of 219 Ts and 172 MIG Ts on CTS No 128 A 12 Pt at Mahaveer nagar Kandivali W MumbaiMumbai Suburban, Maharashtra--Completed
Construction of 86 Tenements out of 430 MIG tenements of old Magathane village BorivaliMumbai Suburban, Maharashtra--Completed
CONST OF 586 EWS 234 MIG TENAMENTS ON LAND BEARING CTS NO 1 C 1 1 BORIVALI WEST MUMBAI 67Mumbai Suburban, Maharashtra--Completed
Planning, designing and construction of 196 MIG T/s and 2 Amenties at Mira RoadMumbai Suburban, Maharashtra--Registration lapsed
64 LIG, 80 MIG, 16HIG and 20 Shops at Sr. No. 491, Res. No. 23 Part, Vengurla, Dist. SindhudurgMumbai Suburban, Maharashtra--Completed
Plotted Development Scheme at Sindhudurhnagari, Oras, Tal- Kudal, Dist- SindhudurgMumbai Suburban, Maharashtra28868%Completed
Constructing EWS and LIG Tenements under PMAY on S No 86 95 and 133 at Shirdhon Tal Kalyan DistThaneThane, Maharashtra--Registered
SURVEY NO 162 VILLAGE KHONI TAL KALYANThane, Maharashtra--Registered
Proposed Redevelopment of existing Transit Camp at Sion, Construction of 91 EWS T/s. 285 Transit T/s +19 shops, 31 LIG T/s, 56 MIG T/s, on land bearing CS. No. 4(Pt.) salt pan Dn. F/N ward at Sion PH -V, MumbaiMumbai City, Maharashtra3520%Registered

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
BLDNG NO 3 SHAILENDRA NAGAR DAHISAR EAST
30 Mar 200711 Jun 2014+87 months
BLDNG NO 1, SHAILENDRA NAGAR,DAHISAR EAST
30 Mar 200718 Dec 2015+105 months
BLDNG NO 1,PLOT B,VILLAGE BORIVALI WEST AT GORAI
14 Aug 20085 Feb 2014+66 months
PLOT C BLDNG NO 7, VILLAGE BORIVALI WEST AT GORAI
28 Jan 201010 Feb 2015+60 months
Survey 41 Plot No 1, Charkop sector 8
18 Jul 20136 May 2014+10 months
Construction of 51 MIG T/s
1 Mar 201415 Jun 2017+40 months
Const of 1041 TR Ts 69 shops 1950 EWS 224 MIG at Kannamwar nagar vikhroli east
P51800000058
31 Mar 2026Not completed yetOngoing
Constructing EWS and LIG Tenements under PMAY on S No 86 95 and 133 at Shirdhon Tal Kalyan DistThane
P51700016820
24 Mar 2027Not completed yetOngoing
SHirdhone
7 Oct 2028Not completed yetOngoing

Frequently asked questions

How do I verify MAHARASHTRA HOUSING AND AREA DEVELOPMENT AUTHORITY as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with MAHARASHTRA HOUSING AND AREA DEVELOPMENT AUTHORITY?

Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.