MAHARASHTRA HOUSING AND AREA DEVELOPMENT AUTHORITY: RERA track record
GSTIN 27AAAJM0344HCZ3 · Public Authority · attribution by exact filing name, entity resolution in progress
MAHARASHTRA HOUSING AND AREA DEVELOPMENT AUTHORITY has 12 registrations on MahaRERA, including PLOT NO 3 CHARKOP SECTOR 8 and Planning, Designing, Constuction and Obtaining Necessary Approvals for 72 HIG t/s on lumpsum Turnkey. Its filings disclose 9 earlier MahaRERA projects: declares 0 of 6 past projects completed on time.
Projects by this developer
Showing all 12 projects.
Largest first, by the unit count in the filing.
What this promoter declares as its own experience
MAHARASHTRA HOUSING AND AREA DEVELOPMENT AUTHORITY declares experience on 9 earlier projects. 2 of them carry a registration number we could match on MahaRERA, of which 1 is registered under a different promoter name.
2 of these declarations can be compared with the dates those projects' own registrations hold. On 2, the date given as the original completion date is the REVISED deadline that project carries after an extension rather than its original one. It changes nothing about whether those projects were delivered on time.
| Declared project | Registered to | Status |
|---|---|---|
| Const of 1041 TR Ts 69 shops 1950 EWS 224 MIG at Kannamwar nagar vikhroli east | MHADA | Registration lapsed |
From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| BLDNG NO 3 SHAILENDRA NAGAR DAHISAR EAST | 30 Mar 2007 | 11 Jun 2014 | +87 months |
| BLDNG NO 1, SHAILENDRA NAGAR,DAHISAR EAST | 30 Mar 2007 | 18 Dec 2015 | +105 months |
| BLDNG NO 1,PLOT B,VILLAGE BORIVALI WEST AT GORAI | 14 Aug 2008 | 5 Feb 2014 | +66 months |
| PLOT C BLDNG NO 7, VILLAGE BORIVALI WEST AT GORAI | 28 Jan 2010 | 10 Feb 2015 | +60 months |
| Survey 41 Plot No 1, Charkop sector 8 | 18 Jul 2013 | 6 May 2014 | +10 months |
| Construction of 51 MIG T/s | 1 Mar 2014 | 15 Jun 2017 | +40 months |
| Const of 1041 TR Ts 69 shops 1950 EWS 224 MIG at Kannamwar nagar vikhroli east P51800000058 | 31 Mar 2026 | Not completed yet | Ongoing |
| Constructing EWS and LIG Tenements under PMAY on S No 86 95 and 133 at Shirdhon Tal Kalyan DistThane P51700016820 | 24 Mar 2027 | Not completed yet | Ongoing |
| SHirdhone | 7 Oct 2028 | Not completed yet | Ongoing |
Frequently asked questions
How do I verify MAHARASHTRA HOUSING AND AREA DEVELOPMENT AUTHORITY as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its GSTIN 27AAAJM0344HCZ3 on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with MAHARASHTRA HOUSING AND AREA DEVELOPMENT AUTHORITY?
Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.