Home / Browse projects / Mumbai City, Maharashtra / AL AMIR APARTMENT

Registered No litigation declared Mixed project

AL AMIR APARTMENT

By JANZEB AMIRKAMAL KHAN

RG-MH-54732 · RERA P51900007426 · Last updated on MahaRERA portal: 24 Sep 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 65 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai City registration emailed to you, free during the pilot beta.
Dec 2028Possession promisedmoved 65 months from the original
1 of 11Construction stages doneacross 2 buildings; furthest along: Podiums (if any), 90%
165 of 255Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 70 documents Report an error

AL AMIR APARTMENT is a Mixed project by JANZEB AMIRKAMAL KHAN in Mumbai City, Maharashtra, registered with MahaRERA as P51900007426 on 17 Aug 2017. Possession is promised by 31 Dec 2028. The completion date has moved by 65 months from the original filing. 90 of the 255 units on this registration are recorded sold or booked, and 1 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameAL AMIR APARTMENT
  • TypeMixed
  • Location
    • 33-37 Jail road South
    • Dongri
    • Mumbai City
    • 400009
  • Pincode400009
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900007426
  • ReraGenie IDRG-MH-54732

Builder

  • NameJANZEB AMIRKAMAL KHAN
  • Entity typeIndividual
  • GSTIN27AEQPK0486C1ZF

Key dates

this monthRegisteredAug 2017First promiseJul 2023Revised toDec 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on17 Aug 2017
  • Promised completion31 Dec 2028
  • Revised completionRevised to 31 Dec 2028 (originally 31 Jul 2023)
  • Buildings1 building record
  • Documents filed70 files

Current status

35%90 of 255 units booked
91.8%Work done, per cost certificate

Figures as on 24 Sep 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
AL AMIR APARTMENTNA272223117248

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 24 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 11 construction stages are filed complete across 2 buildings. The stage furthest along is Podiums (if any), at 90%.

AL AMIR APARTMENT65%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)90%
Plinth0%
Stilt Floor0%
Slabs of Super Structure89%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises89%
Sanitary Fittings within the flats / premises89%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks89%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.89%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.78%
NA Plot Without StructureNot stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 24 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes89%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes89%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes50%
Electrical meter room, sub-station, receiving stationYes89%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area868 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on14 Aug 2026

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI4196.87
Proposed, not sanctioned4,197 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchcarmellos house 414 418 sir j j road opp j j hospital mumbai 400 008
Estimated costRs 27.29 cr
Cost incurredRs 25.04 cr
Work done91.76%
BuildingWingEstimatedIncurred
AL AMIR APARTMENTNARs 27.29 crRs 25.04 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
Architectmujawar zakir husain kasam
EngineerHuzaifa KHAN
Chartered AccountantNITIN RAMNIKLAL MAMTORA
Chartered AccountantEsha Ramesh Bhanushali
PartnerRole in project
JANZEB AMIRKAMAL KHAN-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51900017253Jul 2023 → Jul 2024

Reason as filed by the promoterAmalgamation of adjoining plot bearing C.S. No. 1808 of Mandvi division.

EA19082622234Jul 2023 → Dec 2028

Reason as filed by the promoterExtension is required on the grounds of additional incentive fsi available on the plot. Previously the structure of A wing was to be limited to 22 floors but now due to change in incentive this structure is to be reworked to 25 floors and balance excess fsi unutilised will be transferred to other scheme..

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000181971Mrs Sameera Shahbaz Dalvi and Mr Abdul Raheman Shahebaz DalviJanzeb Amirkamal Khan24/12/2019

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 6 Aug 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 23 Jul 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2028

Documents filed70

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: Form 2A FY 2024-25.pdf24 Sep 2026
Withdrawal Update Form 1File: Annexure A Forn 1.pdf22 Sep 2026
Withdrawal Update Form 1File: Annexure A Forn 1.pdf22 Sep 2026
Withdrawal Update Form 1File: Annexure A Forn 1.pdf22 Sep 2026
Withdrawal Update Form 1File: Annexure A Forn 1.pdf22 Sep 2026
Withdrawal Update Form 1File: Form 1 March 2026.pdf22 Sep 2026
Withdrawal Update Form 1File: Form 1 June 2026.pdf22 Sep 2026
Withdrawal Update Form 2File: Engineer Certificate Pdf.pdf22 Sep 2026
Withdrawal Update Form 2File: Engineer Certificate Pdf.pdf22 Sep 2026
Withdrawal Update Form 2File: Engineer Certificate Pdf.pdf22 Sep 2026
Withdrawal Update Form 2File: Engineer Certificate Pdf.pdf22 Sep 2026
Withdrawal Update Form 2File: Form 2 March 2026_compressed (2).pdf22 Sep 2026
Withdrawal Update Form 2File: Form 2 June 2026_compressed (2).pdf22 Sep 2026
Withdrawal Update Form 3File: Form 3 July to Nov 2025.pdf22 Sep 2026
Withdrawal Update Form 3File: Form 3 July to Nov 2025.pdf22 Sep 2026
Withdrawal Update Form 3File: Form 3 July to Nov 2025.pdf22 Sep 2026
Withdrawal Update Form 3File: Form 3 July to Nov 2025.pdf22 Sep 2026
Withdrawal Update Form 3File: Form 3 March 2026 Final_compressed (1).pdf22 Sep 2026
Withdrawal Update Form 3File: Form 3 March 2026 Final_compressed (1).pdf22 Sep 2026
Form 2A (FY 2024-2025)File: Form 2A FY 2024-25.pdf19 Aug 2026
Commencement Certificates / NA Order for plotted developmentFile: 2486790_FurtherCC_signed.pdf23 Jul 2025
Disclosure of sold/ booked inventoryFile: sold inventory .pdf23 Jul 2025
Disclosure of sold/ booked inventoryFile: sold inventory .pdf23 Jul 2025
Declaration in FORM BFile: ANNEXURE A FORM 1.pdf3 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ANNEXURE A FORM 1.pdf3 Feb 2025
Disclosure of sold/ booked inventoryFile: 3 DISCLOSURE OF SOLD BOOKED INVENTARY.pdf3 Feb 2025
Other - TechnicalFile: Explanatory note.pdf3 Feb 2025
Disclosure of sold/ booked inventoryFile: RERA Flat List 2018 to 2023.pdf6 Sep 2023
Certificates of CA (Form 3)File: Certificate of CA (FORM 3).pdf5 Sep 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Alif - 3CB-3CD Ack.pdf5 Sep 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - Rera ( Alif ).pdf5 Sep 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Annexure A Forn 1.pdf1 Sep 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Pdf.pdf1 Sep 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Pdf.pdf1 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: RERA Quality Assurance Certificate-1.pdf1 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: RERA Quality Assurance Certificate.pdf28 Aug 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Annexure A FORM 1.pdf26 Aug 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate word.pdf26 Aug 2023
Disclosure of sold/ booked inventoryFile: RERA.pdf26 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Acct Statement_XX4119_25082023.PDF26 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Acct Statement_XX4119_25082023(1).PDF26 Aug 2023
Declaration in FORM BFile: NOTARY COPY FOR RERA.pdf22 Aug 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: BANK ESCROW.pdf1 Oct 2022
Declaration about Commencement CertificateFile: format D- declaration about CC.pdf5 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf5 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: form 2A- Engineer's certificate for QA.pdf5 Aug 2021
Disclosure of sold/ booked inventoryFile: Disclosure of sold inventory.pdf5 Aug 2021
Building plan approval or NA orderFile: Approved Amended approval conditions.pdf6 Aug 2019
Building Plan Approval (IOD)File: Approved Amended approval conditions.pdf6 Aug 2019
Commencement Certificates / NA Order for plotted developmentFile: CC Jail Road.pdf6 Aug 2019
Building plan approval or NA orderFile: approval Letter.pdf24 Dec 2018
Building plan approval or NA orderFile: Amended Drawing 6.pdf24 Dec 2018
Building Plan Approval (IOD)File: approval Letter.pdf24 Dec 2018
Building Plan Approval (IOD)File: Amended Drawing 6.pdf24 Dec 2018
Layout approvalFile: plan3.pdf31 Jul 2017
Building plan approval or NA orderFile: iod.pdf31 Jul 2017
Building plan approval or NA orderFile: plan1.pdf31 Jul 2017
PAN CardFile: pan card.pdf31 Jul 2017
Copy of the legal title reportFile: Title certificate.pdf31 Jul 2017
Details of encumbrancesFile: details.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: plan3.pdf31 Jul 2017
Building Plan Approval (IOD)File: plan1.pdf31 Jul 2017
Building Plan Approval (IOD)File: iod.pdf31 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: C C.pdf31 Jul 2017
Declaration in FORM BFile: afidavit.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch cft.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer cft.pdf31 Jul 2017
Certificates of CA (Form 3)File: C A certificate.pdf31 Jul 2017
Certificates of CA (Form 5)File: CA form 5.pdf31 Jul 2017
Proforma of Allotment letterFile: agreement.pdf31 Jul 2017

How this compares with Mumbai City

35%of this project is bookeddistrict median 17%
33%of Mumbai City projects moved their completion datethis one moved by 65 months
25%of Mumbai City registrations have lapsed or been cancelledthis one is on the register

Computed across the 780+ Mumbai City projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep AL AMIR APARTMENT on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Dongri780+ in Mumbai City

Builder: JANZEB AMIRKAMAL KHAN

JANZEB AMIRKAMAL KHAN has 1 registration on MahaRERA, including AL AMIR APARTMENT. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai City district page.

Frequently asked questions

What are my rights if AL AMIR APARTMENT is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of AL AMIR APARTMENT?

The registered promoter entity is JANZEB AMIRKAMAL KHAN, an individual as per the filing. Its GSTIN 27AEQPK0486C1ZF can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in AL AMIR APARTMENT?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against AL AMIR APARTMENT?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for AL AMIR APARTMENT?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at AL AMIR APARTMENT?

The professionals named in the filing: Architect: mujawar zakir husain kasam; Engineer: Huzaifa KHAN; Chartered Accountant: NITIN RAMNIKLAL MAMTORA; Chartered Accountant: Esha Ramesh Bhanushali. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AL AMIR APARTMENT?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AL AMIR APARTMENT. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AL AMIR APARTMENT to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.