Home / Browse projects / Mumbai City, Maharashtra / One Marina

Registered No litigation declared Residential / Group Housing project

One Marina

By VALENCIA AND MISHAL VENTURES PVT LTD

RG-MH-53596 · RERA P51900019619 · Last updated on MahaRERA portal: 12 May 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Rs 570.00 crore secured on the land, in favour of Asia Pragati Strategic Investment Fund

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai City registration emailed to you, free during the pilot beta.
Dec 2028Possession promisedno revision filed
5 of 11Construction stages donefurthest along: Slabs of Super Structure, 3%
131 of 318Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 115 documents Report an error

One Marina is a Residential / Group Housing project by VALENCIA AND MISHAL VENTURES PVT LTD in Mumbai City, Maharashtra, registered with MahaRERA as P51900019619 on 14 Feb 2019. Possession is promised by 30 Dec 2028. 187 of the 318 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameOne Marina
  • TypeResidential / Group Housing
  • Location
    • Shamaldas Gandhi Marg
    • Chira Bazar Chandanwadi
    • Mumbai City
    • 400002
  • Pincode400002
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900019619
  • ReraGenie IDRG-MH-53596

Builder

  • NameVALENCIA AND MISHAL VENTURES PVT LTD
  • Entity typeCompany
  • DirectorsAshwin Sheth, AATIF YAKUB, SUHAIL YAKUB

Key dates

this monthRegisteredFeb 2019PromisedDec 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on14 Feb 2019
  • Promised completion30 Dec 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed115 files

Current status

59%187 of 318 units booked
22.3%Work done, per cost certificate

Figures as on 12 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
One MarinaNA76643180318

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 12 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 3%.

One Marina: 46% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure3%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 12 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed638

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots638
Closed/Covered638

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area1,042 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofAsia Pragati Strategic Investment Fund
Secured amountRs 570.00 crore
CERSAI search filedYes
Declared on18 Dec 2025

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI39918.55
Proposed, not sanctioned29,496 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchUnit No 2 Hallmark Business Plaza Bandra East
Estimated costRs 612.48 cr
Cost incurredRs 136.77 cr
Work done22.33%
BuildingWingEstimatedIncurred
One MarinaNARs 597.48 crRs 131.17 cr
-NARs 15.00 crRs 5.60 cr

Certifying professionals and partners10

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAparna consultant
ArchitectSHARIF H SAULEH
ArchitectSaachi Associates
ArchitectReza Kabul Architect Pvt Ltd
EngineerZahir Khair
EngineerGovind G Navale
Chartered AccountantNihar Atul Mehta
Chartered AccountantHarshal Chhadva
Chartered AccountantM B AGRAWAL & CO.
Chartered AccountantRAJESH KUMAR CHOTIA
PartnerRole in project
VALENCIA AND MISHAL VENTURES PVT LTD-

Litigation declared7

CaseCourtStatus
3387/2018MUMBAI HIGH COURTPENDING
3388/2018MUMBAI HIGH COURTPENDING
3389/2018MUMBAI HIGH COURTPENDING
3392/2018MUMBAI HIGH COURTPENDING
3393/2018MUMBAI HIGH COURTPENDING
3394/2018MUMBAI HIGH COURTPENDING
355/2018SMALL CAUSES COURTPENDING

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000591160propertycloud Realty specifier Pvt Ltd.Valencia and Mishal Ventures Pvt Ltd13/07/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 2 Feb 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 23 Apr 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 7 Feb 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 4 Feb 2026Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Dec 2028

Documents filed115

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 115 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: 1Marina form 1.pdf12 May 2026
Withdrawal Update Form 2File: Form 2 One Marina.pdf12 May 2026
Withdrawal Update Form 3File: Form - 3_One Marina_Mar 26 R.pdf12 May 2026
Building plan approvalFile: iod_bp_74forUpload.pdf7 Feb 2026
Commencement certificateFile: FurtherCC_signed One Marina Sale Bldg dtd-13032025.pdf4 Feb 2026
Withdrawal Update Form 1File: Form -1 One Marina.pdf4 Feb 2026
Withdrawal Update Form 2File: ONE MARINA.pdf4 Feb 2026
Withdrawal Update Form 3File: Form-3_One Marina_Dec 25_Signed.pdf4 Feb 2026
Withdrawal Update Form 1File: Form 1- One Marina-30-9-25.pdf9 Dec 2025
Withdrawal Update Form 2File: Form 2 One Marina-Sep.pdf9 Dec 2025
Withdrawal Update Form 3File: FORM-3 - VALENCIA.pdf9 Dec 2025
Form 5 (FY 2023-2024)File: onemarina 23-24.pdf8 Dec 2025
Withdrawal Update Form 1File: Form 1- One Marina - 30-6-25.pdf29 Nov 2025
Withdrawal Update Form 2File: Form 2 One Marina-July.pdf29 Nov 2025
Withdrawal Update Form 3File: Signed Form - 3_One Marina June 2025.pdf29 Nov 2025
Form 5 (FY 2024-2025)File: Onemarina 24-25.pdf25 Nov 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE 31-MARCH-2024.pdf23 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE 30-JUNE-2024.pdf23 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE 30-SEP-2024.pdf23 Apr 2025
Commencement Certificates / NA Order for plotted developmentFile: FCC.pdf19 Apr 2025
Commencement Certificates / NA Order for plotted developmentFile: FurtherCC.pdf19 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1_ONE MARINA MARCH 24.pdf2 Apr 2025
Certificates of CA (Form 3)File: 23 Final One Marina CA Certificate - Mar-24.pdf2 Apr 2025
Certificates of CA (Form 3)File: 24 Final One Marina CA Certificate - June-24.pdf2 Apr 2025
Certificates of CA (Form 3)File: 25 Final One Marina CA Certificate - Sep-24.pdf2 Apr 2025
Certificates of CA (Form 3)File: 26 Final One Marina CA Certificate - Dec-24.pdf2 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 02 ONE MARINA.pdf2 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 02 ONE MARINA 31 12 2024.pdf2 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 02 JUNE 2024.pdf2 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FROM-2 ENGG CERTIFICATE ONE MARINA SEP-24.pdf2 Apr 2025
Building plan approvalFile: Concession Drawing 2023.pdf23 Apr 2024
Building plan approvalFile: Sheet No 1 Amended Drawing Layout 07 03 2024.pdf23 Apr 2024
Layout approvalFile: 2417978Amendletter_signed.pdf23 Apr 2024
Building plan approvalFile: Sheet No 01-07_11zon.pdf23 Apr 2024
Building plan approvalFile: Sheet No 08 -14_11zon.pdf23 Apr 2024
Building plan approvalFile: Sheet No 15-21_11zon.pdf23 Apr 2024
Building plan approvalFile: Sheet No 22-24_11zon.pdf23 Apr 2024
Copy of Layout Approval (in case of layout)File: 2417978Amendletter_signed.pdf23 Apr 2024
Building Plan Approval (IOD)File: Concession Drawing 2023.pdf23 Apr 2024
Building Plan Approval (IOD)File: Sheet No 1 Amended Drawing Layout 07 03 2024.pdf23 Apr 2024
Building Plan Approval (IOD)File: Sheet No 01-07_11zon.pdf23 Apr 2024
Building Plan Approval (IOD)File: Sheet No 08 -14_11zon.pdf23 Apr 2024
Building Plan Approval (IOD)File: Sheet No 15-21_11zon.pdf23 Apr 2024
Building Plan Approval (IOD)File: Sheet No 22-24_11zon.pdf23 Apr 2024
Commencement Certificates / NA Order for plotted developmentFile: 2417209_FurtherCC_signed.pdf23 Apr 2024
OtherFile: REGISTARED SALE AGRREMENT_compressed (1)_compressed (2).pdf23 Apr 2024
Other - TechnicalFile: Reply for Consent comment.pdf22 Apr 2024
Commencement Certificates / NA Order for plotted developmentFile: 2417209_FurtherCC_signed.pdf10 Apr 2024
Building plan approvalFile: Amendletter_signed.pdf1 Apr 2024
Building plan approvalFile: Drawing (2)_11zon.pdf1 Apr 2024
Building plan approvalFile: DWG8_11zon (1).pdf1 Apr 2024
Building plan approvalFile: DWG15_11zon (1).pdf1 Apr 2024
Building plan approvalFile: DWG22_11zon.pdf1 Apr 2024
Details of encumbrances concerned to FinanceFile: Encumbrance Certificate Final (Details of Encumbrance).pdf1 Apr 2024
Details of encumbrances concerned to LegalFile: Encumbrance Certificate Final (Details of Encumbrance).pdf1 Apr 2024
Building Plan Approval (IOD)File: Amendletter_signed.pdf1 Apr 2024
Building Plan Approval (IOD)File: Drawing (2)_11zon.pdf1 Apr 2024
Building Plan Approval (IOD)File: DWG8_11zon (1).pdf1 Apr 2024
Building Plan Approval (IOD)File: DWG15_11zon (1).pdf1 Apr 2024
Building Plan Approval (IOD)File: DWG22_11zon.pdf1 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM _01 DEC 2024_ ONE MARINA.pdf1 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 02_ ONE MARINA DEC-23.pdf1 Apr 2024
CERSAI detailsFile: CERSAI_Search_Report_Asset_Id_Based_Search_29_02_2024_16_01_27_721.pdf1 Apr 2024
Certificates of CA (Form 3)File: FORM03_ CA Certificate - Dec-23.pdf1 Apr 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A VNS Disclosure of Interest in O R O.pdf1 Apr 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A JNS Disclosure of Interest in O R O.pdf1 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM-05 Mar-2022.pdf1 Apr 2024
Proforma of Agreement for saleFile: Agreement for Sale One Marina.pdf1 Apr 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration of Separate Bank Account.pdf1 Apr 2024
Deviation Report with respect to Allotment letterFile: Deviation report for allotment letter.pdf1 Apr 2024
Deviation Report with respect to model copy of AgreementFile: Deviation report for agreement for sale.pdf1 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect Certificate.pdf6 Nov 2023
Commencement Certificates / NA Order for plotted developmentFile: FurtherCC Sale building.pdf1 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ONE MARINA JUNE 2023.pdf18 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ONE MARINA JUNE 2023.pdf18 Sep 2023
Certificates of CA (Form 3)File: FORM 3 ONE MARINA JUNE 2023.pdf18 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Work Complication One Marina June 2023.pdf7 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Valencia 31-Dec-2022.pdf2 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Valencia 30-Sept-2022.pdf2 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Valencia 30-March-2023.pdf2 May 2023

How this compares with Mumbai City

59%of this project is bookeddistrict median 17%
33%of Mumbai City projects moved their completion datethis one has not
25%of Mumbai City registrations have lapsed or been cancelledthis one is on the register

Computed across the 780+ Mumbai City projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep One Marina on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Chira Bazar Chandanwadi780+ in Mumbai City

2 kmOne MarinaCompleted 15Lapsed / revoked 24Other 43Dot size: filed unitsN

Filed coordinates, straight-line distance. 82 registered projects within 2 km.

Builder: VALENCIA AND MISHAL VENTURES PVT LTD

VALENCIA AND MISHAL VENTURES PVT LTD has 1 registration on MahaRERA, including One Marina. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai City district page.

Frequently asked questions

What are my rights if One Marina is delayed beyond 30 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of One Marina?

The registered promoter entity is VALENCIA AND MISHAL VENTURES PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in One Marina?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against One Marina?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for One Marina?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at One Marina?

The professionals named in the filing: Architect: Aparna consultant; Architect: SHARIF H SAULEH; Architect: Saachi Associates; Architect: Reza Kabul Architect Pvt Ltd; Engineer: Zahir Khair; Engineer: Govind G Navale. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in One Marina?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About One Marina. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save One Marina to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.