CIN U70109MH1998PTC116091 · Company · attribution by exact filing name, entity resolution in progress

S D Corporation Private Limited has 14 registrations in this build, including SIENNAA WING A and SIENNAA WING B. Its filings disclose 1 earlier MahaRERA project: 1 of 1 past projects completed on time. Litigation is declared on 9 of its registrations.

14Registrations in this build
1Past projects disclosed
on timeMedian delivery slip
9Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
SIENNAA WING AMumbai Suburban, Maharashtra--Registration lapsed
SIENNAA WING BMumbai Suburban, Maharashtra--Registration lapsed
SIENNAA WING CMumbai Suburban, Maharashtra--Registration lapsed
SIENNAA WING EMumbai Suburban, Maharashtra33100%Registered
SIENNAA WING FMumbai Suburban, Maharashtra33100%Registered
SIENNAA WING DMumbai Suburban, Maharashtra399100%Registered
AUBBURN WING AMumbai Suburban, Maharashtra6673%Registered
AUBBURN WING BMumbai Suburban, Maharashtra1100%Registered
AUBBURN WING CMumbai Suburban, Maharashtra9798%Registered
Triton Building No 3 Wing CMumbai Suburban, Maharashtra--De-registered
Building no 3 Wing C AquilaMumbai Suburban, Maharashtra--Registered
Imperial T3 Wing CMumbai City, Maharashtra2150%Registered
NP 1.2 AMumbai Suburban, Maharashtra290%Registered
NP 1.2 BMumbai Suburban, Maharashtra850%Registered

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
Building No. 2 Wings A and B Alpine
P51800000879
30 Dec 20208 Feb 2019On time

Frequently asked questions

How do I verify S D Corporation Private Limited as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its CIN U70109MH1998PTC116091 on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with S D Corporation Private Limited?

Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

Does the declared litigation make S D Corporation Private Limited unsafe to buy from?

Not by itself. Litigation on a registration ranges from a boundary dispute to an allottee case about delay; what matters is the case type, which court or forum, and whether it touches the land title of the project you are buying. The case list is in each project's filed documents. Treat litigation as a question to resolve in writing before booking, not as a verdict either way.