Home / Browse projects / Pune, Maharashtra / Mahindra Citadel Phase 1

Registered No litigation declared Residential / Group Housing project

Mahindra Citadel Phase 1

By Mahindra Lifespace Developers limited

RG-MH-64560 · RERA P52100047656 · Last updated on MahaRERA portal: 19 Oct 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • No extension sought by the promoter; the date moved only under MahaRERA's automatic 4-month extension
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 66 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Oct 2028Possession promisedmoved 4 months by MahaRERA order
12 of 44Construction stages doneacross 4 buildings; furthest along: Slabs of Super Structure, 75%
2 of 448Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 99 documents Report an error

Mahindra Citadel Phase 1 is a Residential / Group Housing project by Mahindra Lifespace Developers limited in Pune, Maharashtra, registered with MahaRERA as P52100047656 on 17 Nov 2022. Possession is promised by 30 Oct 2028. The completion date has moved by 4 months under MahaRERA's automatic 4-month extension for the West Asia conflict, which the promoter did not apply for. 446 of the 448 units on this registration are recorded sold or booked, and 12 of 44 construction stages are filed complete.

At a glance

Project

  • NameMahindra Citadel Phase 1
  • TypeResidential / Group Housing
  • Location
    • Old Pune-Mumbai Highway
    • Pimpri
    • Pimpri Chinchawad (M Corp.)
    • Haveli
    • Pune
    • 411018
  • Pincode411018
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100047656
  • ReraGenie IDRG-MH-64560

Builder

  • NameMahindra Lifespace Developers limited
  • Entity typeCompany
  • CINL45200MH1999PLC118949
  • GSTIN27AAACG8904C1ZV
  • CIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • ChairpersonArun Kumar Tilak Raj Nanda
  • Managing DirectorArvind Subramanian
  • Other registrations66 more →
  • Completed25 of 67
  • No longer live19 lapsed, de-registered or revoked
  • Declared earlier projects66 →

Key dates

this monthRegisteredNov 2022First promiseJun 2028Revised toOct 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on17 Nov 2022
  • Promised completion30 Oct 2028
  • Revised completionRevised to 30 Oct 2028 (originally 30 Jun 2028)
  • Buildings4 building records
  • Documents filed99 files

Current status

100%446 of 448 units booked
21.9%Work done, per cost certificate

Figures as on 19 Oct 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower ANA30231370137
Tower BNA30088088
Tower CNA30088088
Tower DNA3001350135

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 19 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

12 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Slabs of Super Structure, at 75%.

Tower A34%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure58%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises4%
Sanitary Fittings within the flats / premises3%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks14%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Tower B33%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure42%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises2%
Sanitary Fittings within the flats / premises2%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks13%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Tower C40%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure75%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises23%
Sanitary Fittings within the flats / premises26%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks16%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Tower D38%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure67%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises12%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks15%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 19 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed4

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots4
Closed/Covered4
BuildingClosed/CoveredTotal
Tower A11
Tower B11
Tower C11
Tower D11

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area6,950 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on18 Aug 2026

Approvals and building plan

Sanctioning authorityPimpri Chinchwad Municipal Corporation
Permissible FSI53000.93
Proposed, not sanctioned2,722 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch167B Ground Floor Ready Money Terrace Dr A B Road Worli Naka Mumbai 400 018
Estimated costRs 237.35 cr
Cost incurredRs 51.90 cr
Work done21.87%
BuildingWingEstimatedIncurred
-NARs 82.59 crRs 12.40 cr
Tower ANARs 45.10 crRs 9.63 cr
Tower DNARs 44.46 crRs 12.72 cr
Tower BNARs 32.72 crRs 5.82 cr
Tower CNARs 32.49 crRs 11.33 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSANKALP DESIGNERS
EngineerSachin Khot
EngineerK C Shah Designs LLP
Chartered AccountantP G BHAGWAT LLP
Chartered AccountantNilesh Vasantlal Shah
Chartered AccountantDELOITTE HASKINS & SELLS LLP
PartnerRole in project
Mahindra Lifespace Developers limited-

Extensions1

A revised date filed with the regulator does not change the possession date in your agreement for sale. Commentary on the order notes that a buyer's right to interest for delay under section 18 of RERA may still stand; that question has not been tested.

MahaRERA order of 7 Aug 2026Jun 2028 → Oct 2028

Granted by MahaRERA, not applied for by the promoterMahaRERA's order of 7 August 2026 extended the completion date of eligible registered projects by four months, treating the West Asia conflict as force majeure. Promoters did not have to apply for it.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Oct 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Oct 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Feb 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 31 Oct 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Oct 2028

Documents filed99

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 99 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Mahindra Citadel Phase I - Architect Certificate Sep26.pdf19 Oct 2026
Withdrawal Update Form 2File: Mahindra Citadel Phase I - Engineering Certificate Sep26.pdf19 Oct 2026
Withdrawal Update Form 3File: MAHINDRA CITADEL PHASE 1 Form 3.pdf19 Oct 2026
Form 5 (FY 2025-2026)File: CITADEL-Tower-ABCD_Signed Form 5 FY26.pdf12 Aug 2026
Form 1File: Architect - Phase 1 Tower A B C and D.pdf16 Jul 2026
Form 2File: Mahindra Citadel Phase I - Engineering Certificate_Jul26.pdf16 Jul 2026
Form 3File: Citadel - Phase 1 - Q1 - FY 2026-27 - Certificate.pdf16 Jul 2026
Disclosure of Sold and Booked InventoryFile: Disclosure Of Sold or Booked Inventory_Citadel (Horizon) all Phases.pdf16 Jul 2026
Form 1File: Mahindra Citadel Phase I - Architect Certificate Mar-26 Final.pdf20 Apr 2026
Form 2File: Mahindra Citadel Phase I - Engineering Certificate_Mar-26 Final.pdf20 Apr 2026
Form 3File: CA Citadel - Phase 1 - Q4 - FY 2025-26 Final.pdf20 Apr 2026
Disclosure of Sold and Booked InventoryFile: Disclosure Of Sold or Booked Inventory_Citadel Phase 1234 Final.pdf20 Apr 2026
Form 2A (FY 2025-2026)File: Quality assurance certificate FY 25-26 Tower ABCDIJK Final.pdf20 Apr 2026
Form 1File: Mahindra Citadel Phase I - Architect Certificate Dec-25 Final.pdf19 Jan 2026
Form 2File: Mahindra Citadel Phase I - Engineering Certificate-Dec-25 Final.pdf19 Jan 2026
Form 3File: Citadel - Phase 1 - Q3 - FY 2025-26 - CA Certificate Final.pdf19 Jan 2026
Disclosure of Sold and Booked InventoryFile: Disclosure Citadel Ph I.pdf19 Jan 2026
Form 1File: Mahindra Citadel Phase I - Architect Certificate Sep'25 Final.pdf14 Oct 2025
Form 2File: Mahindra Citadel Phase I - Engineering Certificate_Sep'25 Final.pdf14 Oct 2025
Form 3File: Citadel - Phase 1 - Q2 - FY 2025-26 - Certificate Final.pdf14 Oct 2025
Disclosure of Sold and Booked InventoryFile: Disclosure Citadel_Ph I.pdf14 Oct 2025
Form 5 (FY 2024-2025)File: 15_Form 5 Report - Mahindra Citadel Phase 1.pdf22 Sep 2025
Form 1File: Mahindra Citadel Phase I - Architect Certificate Jun'25 signed.pdf17 Jul 2025
Form 2File: Mahindra Citadel Phase I - Engineering Certificate_Jun'25 signed.pdf17 Jul 2025
Form 3File: Citadel - Phase 1 - Q1 - FY 2025-26 signed.pdf17 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure Citadel Ph I.pdf17 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Mahindra Citadel Phase I - Architect Certificate Mar'25_Signed comp.pdf17 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Citadel - Phase 1 - Q4 - FY 2024-25 - Certificate.pdf17 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Mahindra Citadel Phase I - Engineering Certificate_Mar'25_Signed Stamped.pdf17 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Quality assurance certificate FY 23-24 signed Final reduced.pdf17 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Mahindra Citadel Phase 1 signed compressed.pdf14 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Citadel_-_Phase_1_-_Q3_-_FY_2024-25_-_Certificate signed.pdf14 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Mahindra Citadel Phase I - Engineering Certificate_Dec'24 signed.pdf14 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Citadel_Phase_1_sept24__.pdf15 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Mahindra Citadel Phase I - Architect Certificate Sep'24 signed_compressed 1.pdf9 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Mahindra Citadel Phase I - Engineering Certificate_Sep'24 signed.pdf9 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Citadel Phase 1- Form 5- FY24.pdf8 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Mahindra Citadel Phase I - Architect Certificate Jun'24 Signd stamp_compressed.pdf17 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Mahindra Citadel Phase I - Engineering Certificate_Jun'24 r-signed.pdf17 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Citadel_-_Phase_1_-_Q1_-_FY_2024-25_Certificate.pdf17 Jul 2024
Other - LegalFile: MLDL - Letter for updation of Authorized Signatories.pdf15 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Mahindra Citadel Phase I - Architect Certificate Mar'24 Signed Form 1 stamped Reduced.pdf17 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Mahindra Citadel Phase I - Engineering Certificate_Mar'24 Signed c.pdf17 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality assurance certificate FY 23-24 signed Final reduced.pdf17 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality assurance certificate FY 23-24 signed Final reduced.pdf17 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Citadel Phase 1 CA Q4_R.pdf17 Apr 2024
Building plan approvalFile: Rev Plan Tower A 14122023.pdf28 Feb 2024
Building Plan Approval / NA Order for plotted developmentFile: Rev Plan Tower A 14122023.pdf28 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Citadel Ph1_arch cert Signed D.pdf17 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Mahindra Citadel Phase I - Engineering Certificate_Dec'23_signed D.pdf17 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Citadel - Phase 1 - Q3 - RERA Certificate_.pdf16 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: MLDL - Citadel - Phase I - Q2 - Certificate_signed_.pdf16 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Mahindra Citadel Phase I - Architect Certificate Sep'23_signed_11zon.pdf11 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Mahindra Citadel Phase I - Engineering Certificate_Sep'23_signed.pdf11 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Citadel Ph 1 Form 5 v1 FY 22-23.pdf28 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final_CA Certificate_Citadel_June_2023_signed.pdf14 Jul 2023
Other - FinanceFile: PGB_MLDL RERA letter.pdf14 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Mahindra Citadel Phase I - Architect Certificate_Compressed.pdf7 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Mahindra Citadel Phase I - Engineering Certificate_Mar'23_signed.pdf6 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Mahindra Citadel Phase I - Engineering Certificate_Jun'23_signed.pdf6 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Mahindra Citadel - PHASE I Quality Certificate FY 23_signed_compressed.pdf17 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Citadel CA Certificate March 23_signed_11zon.pdf15 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Mahindra Citadel Phase I - Engineering Certificate_Mar'23_signed.pdf11 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Mahindra Citadel Phase I - Architect Certificate March'23-compressed.pdf8 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Mahindra Citadel Phase I - Architect Certificate Dec'22_signed_compressed.pdf18 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Mahindra Citadel Phase I - Engineering Certificate_Dec'22_Compressed.pdf18 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Citadel December 22_signed.pdf18 Jan 2023
Building plan approvalFile: Sanctioned Layout.pdf15 Nov 2022
Building plan approvalFile: Tower A Typical Floor Plan.pdf15 Nov 2022
Building plan approvalFile: Tower B Typical Floor Plan.pdf15 Nov 2022
Building plan approvalFile: Tower C Typical Floor Plan.pdf15 Nov 2022
Building plan approvalFile: Tower D Typical Floor Plan.pdf15 Nov 2022
Building Plan Approval / NA Order for plotted developmentFile: Sanctioned Layout.pdf15 Nov 2022
Building Plan Approval / NA Order for plotted developmentFile: Tower A Typical Floor Plan.pdf15 Nov 2022
Building Plan Approval / NA Order for plotted developmentFile: Tower B Typical Floor Plan.pdf15 Nov 2022
Building Plan Approval / NA Order for plotted developmentFile: Tower C Typical Floor Plan.pdf15 Nov 2022
Building Plan Approval / NA Order for plotted developmentFile: Tower D Typical Floor Plan.pdf15 Nov 2022
Details of encumbrances concerned to FinanceFile: Letter of Encumbrances with respect to Finance.pdf11 Nov 2022
Details of encumbrances concerned to LegalFile: Letter of Encumbrances with respect to Finance.pdf11 Nov 2022
Layout approvalFile: Layout Approval.pdf31 Oct 2022

Promoter's earlier projects40

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

25 delivered on promise5 not delivered by the promised date19 under way, not due yet
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Mahindra BeaconHillPM1170002600357Byculla, Mumbai City199May 2026OngoingApr 2032Registered original: Dec 2031Not due yet
Mahindra Citadel - Phase 5PM1264042600425Pimpri Chinchawad (M Corp.), Pune670May 2026OngoingDec 2031Registered original: Aug 2031Not due yet
Mahindra Vista Phase 2P51800079147Kandivali East, Mumbai Suburban667Feb 2025OngoingApr 2031Registered original: Dec 2030Not due yet
Mahindra Citadel - Tower LPR1260002500154Pune, Pune211Jun 2025OngoingApr 2031Registered original: Dec 2030Not due yet
Mahindra IvyLush Tower C and Tower DP52100078592Wagholi, Pune497Dec 2024OngoingDec 2030Registered original: Aug 2030Not due yet
Mahindra Marina64 - Phase 3PR1182022502265Malad, Mumbai Suburban348Feb 2026OngoingOct 2030Registered original: Jun 2030Not due yet
Mahindra Codename Crown Tower EP52100055162Wagholi, Pune125Mar 2024OngoingJul 2030Registered original: Dec 2029Not due yet
Mahindra Codename Crown Tower A and Tower BP52100055161Wagholi, Pune453Mar 2024OngoingJul 2030Registered original: Dec 2029Not due yet
Mahindra Citadel - Bastion IP52100053012Near ICC Tech Park, Pune123Oct 2023OngoingJul 2030Registered original: Mar 2030Not due yet
Mahindra Vista Phase 1P51800054671Kandivali East, Mumbai Suburban600Feb 2024OngoingApr 2030Registered original: Dec 2029Not due yet
Mahindra Marina64 - Phase 2PR1181012500523Malad, Mumbai Suburban70Aug 2025OngoingApr 2030Registered original: Dec 2029Not due yet
Mahindra Marina64 - Phase 1PR1181012500087Malad, Mumbai Suburban62Jun 2025OngoingDec 2029Not due yet
Mahindra Citadel - Bastion J , KP52100053150Near ICC Tech Park, Pune272Oct 2023OngoingOct 2029Registered original: Jun 2029Not due yet
Mahindra Happinest Kalyan - 2 Project BP51700076963Ranjnoli, Thane501Jul 2024OngoingApr 2029Registered original: Dec 2028Not due yet
Mahindra Happinest Kalyan-2 Project AP51700032925Ranjnoli, Thane899Feb 2022OngoingDec 2028Registered original: Apr 2026Not due yet
Mahindra Happinest Tathawade Phase 3P52100052559Tathawade, Pune502Sep 2023OngoingApr 2028Registered original: Dec 2027Not due yet
Mahindra Happinest Tathawade Phase 2P52100045388Tathawade, Pune314May 2022OngoingSep 2027Registered original: May 2027Not due yet
Nest EWSP52100045279Tathawade, Pune89May 2022OngoingMay 2027Registered original: Jan 2027Not due yet
Happinest Tathawade Phase-1P52100028049Tathawade, Pune692Jan 2021OngoingMay 2027Registered original: Jan 2027Not due yet
MAHINDRA ALCOVE WING A AND CP51800033573CHANDIVALI, Mumbai Suburban122Feb 2022OngoingOct 2026Registered original: Jun 2026Not delivered
MAHINDRA ALCOVE WING D AND EP51800028352CHANDIVALI, Mumbai Suburban-Feb 2021OngoingJun 2026Not delivered
MAHINDRA ALCOVE WING BP51800031699CHANDIVALI, Mumbai Suburban62Nov 2021OngoingDec 2025Not delivered
VICINO A5A6P51800033415ANDHERI, Mumbai Suburban-Feb 2022CompletedJul 2025Jul 2025
VICINO A3A4P51800022067Andheri, Mumbai Suburban-Aug 2019CompletedMar 2025Mar 2025
VICINO A1A2P51800022126Andheri, Mumbai Suburban-Aug 2019CompletedMar 2025Mar 2025
Mahindra Meridian PlotsP52000048049Nagaon, Raigarh26Dec 2022OngoingMar 2025Registered original: Mar 2024Not delivered
RootsP51800016833Vickers Compound, Mumbai Suburban-Jun 2018CompletedSep 2023Sep 2023
Centralis Tower 2P52100019393Pimpri, Pune-Jan 2019CompletedAug 2023Aug 2023
Centralis Tower 1P52100019406Pimpri, Pune-Jan 2019CompletedAug 2023Aug 2023
Centralis Tower 4P52100019375Pimpri, Pune-Jan 2019CompletedMar 2023Mar 2023
Centralis Tower 3P52100019407Pimpri, Pune-Jan 2019CompletedMar 2023Mar 2023
Antheia C3P52100016619Pimpri, Pune-May 2018CompletedMar 2023Mar 2023
Centro MHADAP52100030814Pimpri, Pune-Sep 2021CompletedFeb 2023Feb 2023
The Serenes Villa No 14P52000012548nagaon, Raigarh1Sep 2017OngoingDec 2022Not delivered
The Serenes Villa No 13P52000012781nagaon, Raigarh-Sep 2017CompletedDec 2022Dec 2022
VIVANTEP51800000242., Mumbai Suburban-Jul 2017CompletedOct 2021Registered original: Oct 2019Oct 2021
M SpaceP51800000179Borivali, Mumbai Suburban-Jul 2017CompletedMar 2021Registered original: Sep 2019Mar 2021
Antheia A3P52100000171Pimpri, Pune-Jul 2017CompletedDec 2020Dec 2020
Happinest Boisar Phase V CFCP99000014295Kambalgaon, Palghar-Nov 2017CompletedNov 2020Nov 2020
Happinest Boisar Phase IVP99000014293Kambalgaon, Palghar-Nov 2017CompletedNov 2020Nov 2020

How this compares with Pune

100%of this project is bookeddistrict median 29%
28%of Pune projects moved their completion datethis one moved by 4 months
25%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 14,000+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Mahindra Citadel Phase 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Pimpri14,000+ in Pune

2 kmMahindra Citadel Phase 1Completed 34Lapsed / revoked 23Other 135Dot size: filed unitsN

Filed coordinates, straight-line distance. 192 registered projects within 2 km.

Builder: Mahindra Lifespace Developers limited

Mahindra Lifespace Developers limited has 67 registrations on MahaRERA, including Antheia C1 and Antheia A4. Its filings disclose 66 earlier MahaRERA projects: declares 37 of 41 past projects completed on time. Litigation is declared on 7 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Mahindra Citadel Phase 1 is delayed beyond 30 Oct 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Mahindra Citadel Phase 1?

The registered promoter entity is Mahindra Lifespace Developers limited, a company as per the filing. Its CIN L45200MH1999PLC118949 and GSTIN 27AAACG8904C1ZV can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Mahindra Citadel Phase 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Mahindra Citadel Phase 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Mahindra Citadel Phase 1?

The professionals named in the filing: Architect: SANKALP DESIGNERS; Engineer: Sachin Khot; Engineer: K C Shah Designs LLP; Chartered Accountant: P G BHAGWAT LLP; Chartered Accountant: Nilesh Vasantlal Shah; Chartered Accountant: DELOITTE HASKINS & SELLS LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Mahindra Citadel Phase 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Mahindra Citadel Phase 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Mahindra Citadel Phase 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.