This is a sample home-buyer report, generated from the real MahaRERA filing for Gloria Grand, Baner, Pune. About this sample · What the reports cover
or press Ctrl+P / Cmd+P
ReraGenie Buyer Report · Sample
Report date: 16 August 2026
Latest RERA filing: 29 June 2026
Bavadhan · Pune district · PIN 411021

Gloria Grand

by Paranjape Schemes (Construction) Ltd  ·  MahaRERA P52100001380  ·  ReraGenie RG-MH-07707
Registration
Active
since 27 Jul 2017
Possession promised
31 Dec 2026
45 months after the first promise
Units booked
246 of 291
84.5% as filed
Latest RERA filing
29 Jun 2026
48 days before the report date

01At a glance

  • Gloria Grand is a 291 unit project of 4 buildings on 8,371 sq m at Bavadhan, Pune, registered 27 July 2017 by Paranjape Schemes (Construction) Ltd.
  • It is 84.5% booked (246 of 291 units as filed), above the 20.8% median of the 76 projects of all ages with sales data within 2 km.
  • Possession has moved from Mar 2023 to 31 Dec 2026, a slip of 45 months.
  • Construction stands at 91.7% of the Rs 108.6 crore cost the promoter filed.
  • Across this promoter's 32 registrations, 6 have lapsed, including Madhukosh E at 97.7% sold.
  • The filing discloses 2 buyer complaints and 1 court case, covered below.
Source: MahaRERA project filing P52100001380 and 31 sibling filings of the same promoter, captured 16 August 2026.

02Red flags and clear checks

On the record

Possession has slipped 45 months, against a 0 month median for PIN 411021.
H1 reports 24.9% construction with possession promised in 4 months.
5 of this promoter's other registrations lapsed while 73.6% to 97.7% sold, so a strong sales figure here does not by itself secure completion.
2 buyer complaints on the filing.

Clear

Registration is active, and the promoter owns the project land outright.
No encumbrance is declared on the land, and the CERSAI declaration is filed.
84.5% booked, above the 20.8% median of projects within 2 km that file sales.
Filings are current: the last document landed 48 days ago, against the district median of 102 days for active projects.
7 declared past projects were completed on or before the promised date.
Red means the condition has happened. Amber is a caution on record. These are filed facts, not opinions.

03The promoter's record

MahaRERA registers each project alone, so this project's page never mentions what happened to the others. Joining every registration of Paranjape Schemes (Construction) Ltd gives the delivery record a buyer actually needs.

32
MahaRERA registrations
18
completed
9
finished on the first promised date
6
registrations lapsed

Where this project sits in the promoter's record

Possession slip in months, one dot per registration. Gold marks this project.
015304560 months18 projects at zeroGloria Grand · 45
Slip is the gap between a project's first promised completion and its current filed date.
This promoter's registrationsRegisteredUnitsSoldStatusPromised
Madhukosh ESep 20208697.7%LapsedFeb 2026
Forest Trails Everglades H3 and H4Oct 201926093.1%LapsedDec 2025
Trident C, DMar 201830892.2%LapsedDec 2025
Madhukosh A 1Jan 20208486.9%LapsedFeb 2026
Trident Business ParkAug 202020873.6%LapsedJun 2026
Azure Aster G and HJan 20201781.1%LapsedFeb 2026
The Rivolo Residences at Forest TrailsOct 20213174.2%ActiveDec 2027
The Orchard ResidencesApr 20241266.7%ActiveMar 2029
Gloria Grand · this reportJul 201729184.5%ActiveDec 2026

The pattern worth knowing: 5 of this promoter's lapsed registrations were well sold when validity ended, including Madhukosh E at 97.7%, Forest Trails Everglades H3 and H4 at 93.1%, Trident C, D at 92.2%. On this record, strong bookings have not by themselves kept a registration in force.

One firm, more than one MahaRERA profile. 6 of the registrations above sit under a different MahaRERA promoter profile carrying the same firm name. That is how the portal records a promoter who registers again later; the projects are linked here by name and by the phase references in the filings themselves.

Declared past projects. The promoter declares 8 earlier projects on this filing, of which 7 were completed on or before the promised date. These are the promoter's own declarations, filed before RERA registration existed for them.

Source: status, sales and complaint tables of every filing sharing this promoter's MahaRERA profile, name or phase references.

04The possession story

As per the promoter's filings up to 29 Jun 2026

1 extension, 45 months, 4 months to run

Registration to the currently filed completion date
First promise Mar 202345 month sliptodayRegistered Jul 2017Now Dec 2026
Source: registration and extension records of the MahaRERA filing.
"Various approvals etc have been received quite late. Covid has also caused considerable delay in the execution of the project both in terms of time as well as other resources. A detailed note has been attached herewith explaining to all the reasons for delay and therefore request for extension."Extension application filed by Paranjape Schemes (Construction) Ltd

Context from the corpus, which the MahaRERA page cannot show:

  • The median possession slip across the 381 registered projects in PIN 411021 is zero months. This project's 45 months is far into the tail.
  • Of the 3752 Pune projects registered in 2017: 2471 completed, 1080 lapsed, 176 active.
  • The promise now due in 4 months rests on H1, at 24.9% reported.
Source: completion dates across the published MahaRERA filings.

05Within 2 km of the project

Using the coordinates in the filing, every registered project within a 2 km radius is compared, a tighter and more honest vicinity than a whole pincode: 214 projects are registered there, of which 76 file sales figures.

214
registered projects within 2 km
20.8%
median bookings among the 76 that file sales, across all ages
84.5%
this project
Neighbours within 2 kmDistUnitsSoldStatusPossession
Gloria Grand · this report0.029184.5%ActiveDec 2026
Sai Empire0.4400%DraftDec 2032
Nyati Equinox II0.523840.3%ActiveMay 2027
Mont Vert Axis0.514658.2%ActiveDec 2028
Savanna Hills0.57486.5%ActiveDec 2027
Surabhi Shree0.53683.3%LapsedDec 2024
Rose Garden0.5180%CompletedMar 2019
Nyati Equinox I0.61,15775.5%ActiveSep 2028
Cielo By Vtp Luxe0.653052.1%ActiveDec 2028
Joywoods A Wing0.611476.3%ActiveDec 2026
The nearest neighbours that file unit counts, by distance from the coordinates each promoter filed. Sales as filed; projects that have not filed unit counts are excluded from the table and the median.

What the neighbourhood says. 57 of the 214 registered projects within 2 km are active, holding 6,840 sanctioned units between them.

06Sanctions, units and sales, building by building

As per the promoter's filings up to 29 Jun 2026

All 4 buildings are fully sanctioned: every proposed floor is a sanctioned floor, and nothing waits beyond sanction.

BuildingFloors sanctionedUseUnitsSold + bookedUnsold% booked% construction
B120 of 20Residential108891982.4%96.4%
B225 of 25Residential138136298.6%96.4%
H17 of 7Commercial240240%24.9%
H27 of 7Residential21210100%100%
Whole project4 of 4 buildings267 res · 24 comm2912464584.5%91.7%

Where the unsold units sit

H1 holds 53% of the unsold stock
45unsoldH1 · 24B1 · 19B2 · 2
  • B2, H2 are sold through, with 2 or fewer units left.
  • The buildings are not progressing together. H2 reports 100% while H1 reports 24.9%. Which building your unit is in changes your situation in this project.
  • No units are recorded as mortgaged in the filing.
Source: building sanction table and floor wise inventory disclosure of the MahaRERA filing. Percent booked is sold plus booked over sanctioned units. Most promoters do not file the building level split; where it is absent this section shows project totals only.

07Construction and money

As per the promoter's filings up to 29 Jun 2026

91.7% of the filed cost is spent

Rs crore, promoter filed
Estimated108.6Incurred99.691.7% of estimate, as filed in the latest quarterly update

The buildings are not progressing together

Promoter's filed work done share of cost
B1 · 108 units96%B2 · 138 units96%H1 · 24 units25%H2 · 21 units100%
  • Layout level development works. Rs 22.6 crore of the estimate covers development outside the buildings themselves, of which 89.2% is filed as spent.
  • Shared amenities are at 65.7%. The amenity checklist covers water supply, sewerage, storm water drains, street lighting, fire safety and the rest of what makes a building habitable rather than merely built.
  • Parking is filed as zero. The parking table exists in the filing but records no slots for any wing. Ask the promoter for the sanctioned parking plan in writing.
Source: cost, activity and parking tables of the MahaRERA filing.

08Who you are dealing with

Your agreement for sale is signed with the promoter entity below, exactly as named in the filing. The professionals certify construction progress and accounts, and their certificates are what unlock the promoter's money from the 70% account.

RoleName, as filedRegistration on file
PromoterPARANJAPE SCHEMES (CONSTRUCTION) LTDCompany
ArchitectAnkur AssociatesCouncil of Architecture CA/98/22909
EngineerChnadrashekharregistration number not filed
Chartered AccountantKapure & KapureMembership 147451
Chartered AccountantM S K A & AssociatesMembership 111700
  • Match the name on your agreement to the filing. The entity above is printed exactly as MahaRERA holds it, capitals and all, because this is the row to check your agreement for sale against. A different or additional entity there is a question to raise before signing.
  • Official communication address, as filed: 1, SOMNATH, RAM MANDIR ROAD, VILE PARLE (EAST), NEAR TILAK MANDIR, Mumbai City, Mumbai City, Mumbai City, MAHARASHTRA, 400057. MahaRERA encrypts the promoter's phone number and email in the public filing, so this report does not carry them.
  • The filing carries no CIN, LLPIN or GSTIN for this entity, and MahaRERA has no authorised signatory field. Ask for the board authorisation of whoever signs.
Source: promoter and professionals tables of the MahaRERA filing. Real estate agents registered on the project are deliberately not listed: they certify nothing, and the filing carries their personal contact details.

09Land and title

  • The filing records the promoter as owner of the land, 8,370.61 sq m, under Pune Municipal Corporation, with no other landowner listed.
  • No encumbrance is declared on the land, and the promoter filed the CERSAI declaration on 17 Jul 2025, the registry check for undisclosed mortgages.
  • A legal title report is on the filing: "1 Copy of the legal title report", uploaded 11 July 2017.

The title flow. The delivered report summarises this document in plain language: who held the land first, how it reached the promoter, and any cases, claims or mortgages the title lawyer recorded, each stated with the document's own date. The summary is read from the document itself at the time the report is generated.

Source: land, encumbrance and CERSAI tables and the document register of the MahaRERA filing. A title search by your own lawyer remains prudent before any agreement.

10Filing discipline and recent activity

A promoter who keeps filing is a promoter still running the project. The last document here landed 48 days ago; the median active project in Pune last filed 102 days ago.

  • 29 Jun 2026Architect certificate (Form 1), Engineer certificate (Form 2), CA certificate (Form 3)
  • 8 Nov 2025CA annual audit (Form 5)
  • 5 May 20251 Disclosure of sold/ booked inventory
  • 18 Apr 2025Architect certificate (Form 1)
  • 11 Apr 2025CA certificate (Form 3), Engineer certificate (Form 2)
  • 27 Feb 2025Architect certificate (Form 1)
Source: document register of the MahaRERA filing, most recent first. This list refreshes at every data update.

11Complaints and court cases, in plain words

A buyer complaint filed with MahaRERA

on file
What the filing says, simply

A buyer took this project to MahaRERA. The complaint and any order on it sit in the project's document list, which is where the outcome can be read; the filing's data fields do not state it.

A buyer complaint filed with MahaRERA

on file
What the filing says, simply

A buyer took this project to MahaRERA. The complaint and any order on it sit in the project's document list, which is where the outcome can be read; the filing's data fields do not state it.

A follow up application on an earlier complaint

on file

Applications of this kind are usually filed when a party says an earlier order has not been complied with. Read the application and the order it refers to in the document list.

A court case disclosed on the filing

377/15 · C J S D PUNE · Matter is kept for hearing

Matter is kept for hearing No interim order is recorded against the project.

Restated from the complaint and litigation tables of the MahaRERA filing. The court and authority records, not this summary, are authoritative.

12What the documents say

93 documents are on the filing. The checklist below shows what a buyer should expect on record for a project at this stage, and what is actually there.

  • Commencement certificate, latest dated 10 Jul 2024. The permission to start construction.
  • Legal title report, latest dated 11 Jul 2017. The lawyer's check of who owns the land.
  • Professional certificates, Forms 1, 2 and 3, latest dated 29 Jun 2026. The architect, engineer and CA certificates that release money from the 70% account.
  • Form 5 audited accounts, latest dated 8 Nov 2025. The annual audit of the project account.
  • Allotment or agreement proforma, latest dated 14 Nov 2022. The draft you should compare against the one you are given.
  • Occupancy certificate. The completion signal: the building declared fit to move in. (not due yet: possession is promised Dec 2026)

The checklist reads document titles as filed; a certificate inside a generically named scan will show as not found even when it exists. Absences marked not due are stage, not fault.

In the delivered report this section also carries extracts read from the filed documents themselves, generated at the time of the order so they reflect that day's document list.

Source: document register of the MahaRERA filing.

13Booking pace

MahaRERA publishes today's sales figure and discards yesterday's. ReraGenie records every change, so this section accumulates the project's booking history from the first day of coverage.

First observation on record: 246 of 291 units sold or booked as of 16 August 2026. A single observation is a point, not a trend; the pace chart appears once the filed figure moves.

14Your rights under the RERA Act

  1. If possession is late, you may exit with interest. Section 18 lets you withdraw and recover everything paid plus interest at SBI MCLR + 2%, about 10.90% on the schedule current in June 2026. Stay invested instead and the promoter owes you that interest for every month of delay.
  2. 70% of your money is locked to this project. Collections must go to a designated account and be withdrawn only against certified construction and land cost.
  3. You buy carpet area, not built up area. The agreement must state RERA carpet area, and the price cannot rise if the area shrinks on completion.
  4. Five year defect liability. Structural or workmanship defects reported within five years of possession must be fixed by the promoter at no cost, within 30 days.
  5. No plan changes without consent. Altering your unit needs your consent. Altering the project's layout or common areas needs two thirds of all buyers.
  6. A complaint is cheap and direct. Any buyer can file against a project with the authority online for a nominal fee, and adjudicating officers can award compensation. MahaRERA's official step by step video on filing a complaint: youtu.be/mBXlbeN-zo4
A plain reading of the Real Estate (Regulation and Development) Act, 2016. The statutory text prevails over this summary.

15What the filings do not contain

MahaRERA filings carry no sale prices, no carpet areas per unit and no BHK configurations. Any price or size you are quoted comes from the promoter, not the regulator, so have it written into the agreement for sale. This report never estimates a number the filing does not contain: where a fact is absent above, it is absent from the filing.