Registered No litigation declared Residential / Group Housing project

Mahindra Codename Crown Tower A and Tower B

By Mahindra Lifespace Developers limited

RG-MH-66382 · RERA P52100055161 · Last updated on MahaRERA portal: 16 Jul 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 3 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Mar 2030Possession promisedmoved 3 months from the original
0 of 22Construction stages doneacross 2 buildings; furthest along: Excavation, 0%
1Complaints at MahaRERAon this registration
Jump to the 128 documents Report an error

Mahindra Codename Crown Tower A and Tower B is a Residential / Group Housing project by Mahindra Lifespace Developers limited in Pune, Maharashtra, registered with MahaRERA as P52100055161 on 4 Mar 2024. Possession is promised by 31 Mar 2030. The completion date has moved by 3 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameMahindra Codename Crown Tower A and Tower B
  • TypeResidential / Group Housing
  • Location
    • Solitaire Township road
    • Wagholi
    • Haveli
    • Pune
    • 412207
  • Pincode412207
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100055161
  • ReraGenie IDRG-MH-66382

Builder

  • NameMahindra Lifespace Developers limited
  • Entity typeCompany
  • CINL45200MH1999PLC118949
  • CIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • ChairpersonArun Kumar Tilak Raj Nanda
  • Managing DirectorArvind Subramanian
  • Other registrations66 more →
  • Completed25 of 67
  • No longer live20 lapsed, de-registered or revoked
  • Declared earlier projects66 →

Key dates

this monthRegisteredMar 2024First promiseDec 2029Revised toMar 2030

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on4 Mar 2024
  • Promised completion31 Mar 2030
  • Revised completionRevised to 31 Mar 2030 (originally 31 Dec 2029)
  • Buildings2 building records
  • Documents filed128 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower ANA360000
Tower BNA380000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 16 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Excavation, at 0%.

Tower A0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Tower B0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities16

As on 16 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%
Club HousesYes0%

Parking filed547

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots547
Closed/Covered547
BuildingClosed/CoveredTotal
Tower A320320
Tower B227227

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,192 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityPune Metropolitan Regional Development Authority
Permissible FSI53834.26
Proposed, not sanctioned52,834 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch5 C-Ii,Mittal Court, 224, Nariman Point Mumbai Maharashtra - 400021

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
EngineerK C Shah Designs LLP
EngineerSachin Jagdale
Chartered AccountantP G BHAGWAT LLP
Chartered AccountantNilesh Vasantlal Shah
PartnerRole in project
Mahindra Lifespace Developers limited-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100019679Dec 2029 → Mar 2030

Reason as filed by the promoterDue to unforeseen delays in obtaining the amended Commencement Certificate from the competent authority, it has become evident that the Project will not be completed by the Original Completion Date.

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12601205Shubham Shivajirao KaraleMahindra Lifespace Developers limited06/03/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 4 Feb 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 22 Apr 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 Apr 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 22 Apr 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2030

Documents filed128

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 128 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Tower A B - Form 1.pdf16 Jul 2026
Form 2File: Mahindra Codename Crown Tower A and B - Engineering Certificate Jun 26 - R0.pdf16 Jul 2026
Form 3File: Wagholi Tower AB Certificate.pdf16 Jul 2026
Disclosure of Sold and Booked InventoryFile: Disclosure Of Sold or Booked Inventory IvyLush Wagholi - Phase 1 2 3.pdf16 Jul 2026
Form 2A (FY 2025-2026)File: Mahindra IvyLush (Codename Crown) (QA Certificate) - Mar26 - R0.pdf20 Apr 2026
Form 1File: Tower-A B.pdf18 Apr 2026
Form 2File: Mahindra IvyLush Tower A and B - Engineering Certificate Mar 26 - R0.pdf18 Apr 2026
Form 3File: Wagholi - Tower A B - Q4 - FY 2025-26.pdf18 Apr 2026
Disclosure of Sold and Booked InventoryFile: Disclosure Of Sold or Booked Inventory IvyLush Wagholi - Phase 1 2 3.pdf18 Apr 2026
Form 1File: Mahindra Crown Phase 1 - Architect Certificate Dec25 Tower A and B - R0.pdf15 Jan 2026
Form 2File: Mahindra Codename Crown Tower A and B - Engineering Certificate Dec25 - R0.pdf15 Jan 2026
Form 3File: Wagholi - Tower A B - Q3 - FY 2025-26 Certificate.pdf15 Jan 2026
Disclosure of Sold and Booked InventoryFile: Disclosure Wagholi A B.pdf15 Jan 2026
Form 1File: Tower A B.pdf13 Oct 2025
Form 2File: Mahindra Codename Crown Tower A and B - Engineering Certificate Sep25 - R0.pdf13 Oct 2025
Form 3File: Wagholi Tower A B Q2 FY2025-26 CA Certificate.pdf13 Oct 2025
Disclosure of Sold and Booked InventoryFile: Disclosure Wagholi A B.pdf13 Oct 2025
Form 5 (FY 2024-2025)File: 20_Form 5 Report - Mahindra Codename Crown Tower A and Tower B.pdf22 Sep 2025
Form 1File: Form 1 Mahindra Crown Phase 1 - Architect Certificate Jun25 Phase I Tower A and B - R0.pdf17 Jul 2025
Form 2File: Form 2 Mahindra Codename Crown Tower A and Tower B - Engineering Certificate Jun25 - R0.pd17 Jul 2025
Form 3File: Form 3 Wagholi Tower AB Q1 FY2025-26 Certificate.pdf17 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure Wagholi A B.pdf17 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Mahindra Crown Phase 1 - Architect Certificate Mar25 Phase I Tower A and B - R0.pdf16 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Wagholi - Tower A and B - Q4 - FY 2024-25 Certificate.pdf16 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Mahindra Codename Crown Tower A and B - Engineering Certificate Mar25 - R0.pdf16 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Mahindra IvyLush (Codename Crown) (QA Certificate) - Mar25 - R0.pdf16 Apr 2025
Details of encumbrances concerned to FinanceFile: Letter of Encumbrances with respect to Finance Tower A and B 27012025.pdf30 Jan 2025
Proforma of Allotment letterFile: Allotment letter Ivylush Tower A and B 28012025.pdf30 Jan 2025
Details of encumbrances concerned to LegalFile: Letter of Encumbrances with respect to Finance Tower A and B 27012025.pdf30 Jan 2025
Proforma of Agreement for saleFile: AFS Ivylush Tower A and B 28012025.pdf30 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Dec24 Phase I Tower A B - R0.pdf15 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Tower A B Q3FY2024-25 CA Certificate.pdf15 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineering Certificate Dec24 Tower A B - R0.pdf15 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Mahindra Crown Phase 1 - Architect Certificate Sep24 - R0.pdf15 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Wagholi - Phase 1 - CA Certificate - Q2.pdf15 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Mahindra Crown Phase I - Engineering Certificate Sep24 - R0.pdf15 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Crown A B F24.pdf8 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Mahindra Crown Phase 1 - Architect Certificate Jun-24 Phase I.pdf18 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Mahindra Codename Crown Phase I - Engineering Certificate Jun-24.pdf18 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Wagholi_-_Tower_A___B_-_Q1_-_FY_2024-25_-_CERT.pdf18 Jul 2024
Other - TechnicalFile: MLDL - Letter for updation of Authorized Signatories.pdf15 Jul 2024
Declaration in FORM BFile: Form B- Tower A and Tower B.pdf7 May 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory- Tower A and Tower B.pdf7 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23).pdf3 May 2024
Layout approvalFile: Layout A and B.pdf22 Apr 2024
Building plan approvalFile: 05-Tower A.pdf22 Apr 2024
Building plan approvalFile: 06-Tower A.pdf22 Apr 2024
Building plan approvalFile: 07-Tower A.pdf22 Apr 2024
Building plan approvalFile: 08-Tower A.pdf22 Apr 2024
Building plan approvalFile: 09-Tower A.pdf22 Apr 2024
Building plan approvalFile: 10-TOWER B.pdf22 Apr 2024
Building plan approvalFile: 11-TOWER B.pdf22 Apr 2024
Building plan approvalFile: 12-TOWER B.pdf22 Apr 2024
Building plan approvalFile: 13-TOWER B.pdf22 Apr 2024
Building plan approvalFile: 14-TOWER B.pdf22 Apr 2024
Copy of Layout Approval (in case of layout)File: Layout A and B.pdf22 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: 05-Tower A.pdf22 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: 06-Tower A.pdf22 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: 07-Tower A.pdf22 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: 08-Tower A.pdf22 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: 09-Tower A.pdf22 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: 10-TOWER B.pdf22 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: 11-TOWER B.pdf22 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: 12-TOWER B.pdf22 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: 13-TOWER B.pdf22 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: 14-TOWER B.pdf22 Apr 2024
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf22 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Mahindra Codenam Crown QA certificate.pdf19 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Mahindra Codename Crown Tower A B Form 1.pdf18 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Mahindra Codename Crown Tower A B Form 2.pdf18 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Mahindra Codenam Crown Tower A B Form 3.pdf18 Apr 2024
Other - LegalFile: LOI 12 04 2023.pdf28 Feb 2024
Other - LegalFile: INTEGRATED BUSINESS ECOSYSTEM CATYLIST.pdf28 Feb 2024
Other - LegalFile: ASHDAN DEVELOPERS PRIVATE LTD TOWER AB.pdf28 Feb 2024
Other - LegalFile: 20231010_Confirmation Deed.pdf28 Feb 2024
Other - TechnicalFile: 2 Other - INDEX II.pdf26 Feb 2024
Other - TechnicalFile: GetUserDocumentFileContent.pdf26 Feb 2024
CERSAI detailsFile: Declaration for CERSAI Tower A and B.pdf21 Feb 2024
Details of encumbrances concerned to FinanceFile: Letter of Encumbrances Finance and legal.pdf20 Feb 2024
Details of encumbrances concerned to LegalFile: Letter of Encumbrances Finance and legal.pdf20 Feb 2024

Promoter's earlier projects16

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

12 delivered on promise4 delivered late
ProjectLocationFlatsStatusPromisedDelivered
WindchimesMahindra Homes Pvt Ltd Sy No 37PART 2 37 PART 3 Opposite BPL Bannerghatta Road Arekere Bangalore 560075454CompletedDec 2018Dec 2018
Boisar Phase IIGut No.50 Plot No.1 Village Kambalgaon Taluka Palghar District Palghar238CompletedDec 2017Jun 2017
BOISAR Phase IGut No 50 Plot No 1 Village Kambalgaon Taluka Palghar District Palghar359CompletedJun 2017Jan 2017
LartistaMahindra Lifespace Developers Ltd Mahindra Towers 5th Floor Dr G M Bhosale Marg Worli Mumbai 400 01821CompletedSep 2016Sep 2016
Avadi Phase IBlock No 84 WARD No 1 Paruthipattu Village Avadi Municipalty Taluka Poonamallee604CompletedJun 2016Apr 2016
AshvitaMahindra Lifespace Developers Limited Sy No 78 PART 2 AND 78 PART3 Near Hitech city MMTS railway station Hafeezpet Road Kukatpally Hyderabad 500072664CompletedJun 2016May 2016
Aura PH5Village Chauma Sector 110A Gurgaon Manesar Urban Complex150CompletedJan 2015Late, Sep 2016
Aura PH4Village Chauma Sector 110A Gurgaon Manesar Urban Complex142CompletedJan 2015Late, Dec 2015
Aura PH3Village Chauma Sector 110A Gurgaon Manesar Urban Complex110CompletedOct 2014Late, Aug 2015
Aura PH2Village Chauma Sector 110A Gurgaon Manesar Urban Complex166CompletedNov 2013Late, Oct 2014
Splendour Phase 2CTS NO 617 part 617 30 617 39 PLOT B L B S Marg BHANDUP W MUMBAI 400078re233CompletedNov 2013Jun 2013
Aura PH1Village Chauma Sector 110A Gurgaon Manesar Urban Complex231CompletedMay 2013May 2013
AngelicaBldg C on plot bearing cts no 899 A TO E of village pahadi goregaon S.V.Road Mumbai67CompletedMar 2013Mar 2013
AspenBldg A on plot bearing cts no 899A TO E of village pahadi goregaon S.V.Road Mumbai68CompletedDec 2012Dec 2012
Splendour Phase 1CTS NO 617 part 617 30 617 39 PLOT B L B S Marg BHANDUP W MUMBAI 400078265CompletedAug 2011Aug 2011
ChlorisMilestone 16 PART 3 Sector 19 Faridabad160CompletedJul 2011Jul 2011

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 3 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Mahindra Codename Crown Tower A and Tower B on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Wagholi13,700+ in Pune

2 kmMahindra Codename Crown Completed 12Lapsed / revoked 4Other 38Dot size: filed unitsN

Filed coordinates, straight-line distance. 54 registered projects within 2 km.

Builder: Mahindra Lifespace Developers limited

Mahindra Lifespace Developers limited has 67 registrations on MahaRERA, including Antheia C1 and Antheia A4. Its filings disclose 66 earlier MahaRERA projects: declares 37 of 41 past projects completed on time. Litigation is declared on 7 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Mahindra Codename Crown Tower A and Tower B is delayed beyond 31 Mar 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Mahindra Codename Crown Tower A and Tower B?

The registered promoter entity is Mahindra Lifespace Developers limited, a company as per the filing. Its CIN L45200MH1999PLC118949 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Mahindra Codename Crown Tower A and Tower B?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Mahindra Codename Crown Tower A and Tower B?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Mahindra Codename Crown Tower A and Tower B?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Mahindra Codename Crown Tower A and Tower B?

The professionals named in the filing: Engineer: K C Shah Designs LLP; Engineer: Sachin Jagdale; Chartered Accountant: P G BHAGWAT LLP; Chartered Accountant: Nilesh Vasantlal Shah. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Mahindra Codename Crown Tower A and Tower B?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Mahindra Codename Crown Tower A and Tower B. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Mahindra Codename Crown Tower A and Tower B to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.