01The subject in brief
- Balaji Symphony phase 3 is a 430 unit project of 3 buildings on 6,679 sq m at Panvel, Thane (PIN 410206), registered 25 July 2017 by Vinay Agrawal.
- The catchment is 857 registrations within 5 km: 265 active holding 25,216 filed units, 422 completed, 142 lapsed or revoked.
- At 430 units the subject is larger than 323 of the 332 catchment projects with a filed unit count.
- It is 100% booked, above the 20.4% median of the 232 active projects in the catchment that file sales.
- Possession has moved from Jun 2021 to 30 Jun 2028, a slip of 84 months.
- The promoter carries 4 MahaRERA registrations: 2 completed, 2 active, 0 lapsed. Part III reads the book.
02The parcel and its title
The parcel is filed at 6,679 sq m (1.65 acres) under CIDCO. That is a larger land assembly than 2723 of the 2858 parcels registered in this pincode.
- The promoter is filed as owner of the land, with no other landowner listed: no landowner share agreement sits between the reader and the title.
- No encumbrance is declared on the land.
- A legal title report is on the filing: "1 Copy of the legal title report", uploaded 21 July 2017.
Filed boundaries of the parcel
| East | 172-0 |
| West | 178-0 |
| North | 188-2 |
| South | 45-18 |
Boundary entries usually name the adjoining survey numbers and roads: the starting point for a title search and for reading what can be assembled around this parcel.
03Built intensity and sanction headroom
The plan summary files a built-up area of 25,963 sq m against the 6,679 sq m parcel, a built intensity of 3.89x (filed built-up over plot, both as filed).
- That works the parcel harder than 2440 of the 2761 projects in PIN 410206 with comparable filings.
- The plan summary counts 3 buildings sanctioned.
Built intensity across PIN 410206
04Product, inventory and parking
The product is 430 units across 3 buildings, 100% booked as filed, building by building below.
| Building | Floors sanctioned | Use | Units | Unsold | % booked | % construction |
|---|---|---|---|---|---|---|
| Wing B | 36 of 36 | Residential | 145 | 0 | 100% | 99.7% |
| Wing C | 36 of 36 | Residential | 116 | 0 | 100% | 99.7% |
| Wing E | 36 of 36 | Residential | 169 | 0 | 100% | 99.7% |
- The filed massing averages 4.0 units per sanctioned floor across 108 floors: the closest the filing comes to a configuration read, since MahaRERA files no BHK mix.
Parking: 3 spaces for 430 units, 0.01 per unit, 100% covered, as filed. That is more parking per unit than 0 of the 318 catchment projects filing both figures (median 0.85).
05The catchment as filed
Every registration around the subject, as filed: 857 within 5 km, of which 265 are active, 422 completed and 142 lapsed or revoked. The map, the rings and the ownership of that supply follow.
Registered supply within 5 km
| Ring | Registrations | Active | Completed | Lapsed/revoked | Active units |
|---|---|---|---|---|---|
| Within 2 km | 95 | 38 | 41 | 14 | 3,480 (45 filed) |
| Within 5 km | 857 | 265 | 422 | 142 | 25,216 (332 filed) |
What this supply is, by the promoters' own declared type: 524 residential / group housing, 253 others, 57 mixed, 17 commercial, 6 plotted.
Who holds the catchment
661 distinct promoter names operate within 5 km. The five largest by filed units hold 19.5% of the known stock:
- 5.6%City And Industrial Development Corporation Of Maharashtra Limited · 2 projects, 1,765 units
- 5%Arihant Abode Limited · 2 projects, 1,571 units
- 4.2%Sanvo Resorts Pvt. Ltd. · 30 projects, 1,343 units
- 2.8%Callista Realty Limited · 1 project, 902 units
- 1.9%Villa Realcon LLP · 1 project, 616 units
PIN 410206 as a whole holds 2,858 other registrations: 761 active, 1306 completed, 724 lapsed or revoked.
06What this market absorbs
MahaRERA files no sales history, so no single project can show its own absorption. But 232 active projects of different ages in this catchment file a sales figure, and photographed on the same day they sketch the curve: how far sales typically stand after one year, three, five.
Percent sold against months on the register
- Projects 0-1 years on the register: median 0% sold (81 projects).
- Projects 1-2 years on the register: median 20.4% sold (42 projects).
- Projects 2-3 years on the register: median 50.5% sold (54 projects).
- Projects 3-4 years on the register: median 41.5% sold (21 projects).
- Projects 4-5 years on the register: median 44.1% sold (11 projects).
- Projects 5-6 years on the register: median 59.1% sold (7 projects).
- Projects 6-7 years on the register: median 52.6% sold (5 projects).
- Projects 7-8 years on the register: median 68.9% sold (11 projects).
- 8 of the 232 are at 95% or better: effectively sold through while still under construction.
- 7 projects have been on the register five years or more and remain under 40% sold: the stock this market has not taken.
- The subject, 109 months on the register at 100% sold, stands above 6 of the 8 catchment projects within a year of its age.
07Supply pipeline and vintages
What entered this pincode, year by year, and what each vintage has become. New supply is entering slower than the previous three years: 527 registrations in 2024-2026 against 699 in 2021-2023. Of the 1786 registrations now five or more years old, 549 (31%) have lapsed or been revoked rather than completing.
Registrations per year in PIN 410206
When the competing stock says it will land, by promised possession year of the active projects in the catchment. 1 active neighbour is already past their promised date holding 15 filed units: stock that was promised and has not arrived, and still competes for the same buyers.
Promised possession of active neighbours
08The inventory the subject competes with
The next buyer in this catchment chooses between these inventories. 16,816 unsold units sit across 227 active projects that file sales within 5 km; the ten largest holders: The subject itself is fully booked as filed and adds nothing to this competing stock.
| Project | Promoter | Units | Unsold | % sold | Possession promised |
|---|---|---|---|---|---|
| Brillante · 3.7 km | Callista Realty Limited | 902 | 714 | 20.8% | May 2028 |
| Plot No -1 Sector - 28 Khandeshwar Railway Station · 4.0 km | City And Industrial Devel… | 1,589 | 682 | 57.1% | Dec 2027 |
| Florence · 4.2 km | Villa Realcon LLP | 616 | 511 | 17% | Dec 2030 |
| Rising Sun · 3.4 km | Lakhotia Multi Business P… | 503 | 503 | 0% | Mar 2030 |
| Kanakia Valley · 2.2 km | Kanakia Transparent Devel… | 500 | 500 | 0% | Dec 2030 |
| Olive Boulevard · 0.1 km | Olive Infra & Lifestyle L… | 441 | 441 | 0% | Dec 2029 |
| Commanders Heera Siddhi Homes Phase III · 2.2 km | Megaplex Properties LLP | 480 | 417 | 13.1% | Dec 2027 |
| Bharat Enclave · 1.5 km | TPV Lands LLP | 422 | 344 | 18.5% | Jun 2028 |
| Gami Mirava · 2.2 km | Lal Gebi Infra Private Li… | 327 | 327 | 0% | Dec 2029 |
| Arihant Aspire Phase IV · 4.5 km | Arihant Abode Limited | 361 | 289 | 19.9% | Mar 2032 |
09How this market executes
Across 829 projects in the 5 km catchment the median possession slip is 0 months; 106 (13%) have moved their date by more than a year.
- The subject has slipped 84 months; 0 of the 829 compared projects have slipped further.
- 142 of the 857 registrations within 5 km (17%) have lapsed or been revoked, against 24% across the 7,804 registrations of the district.
- 1 active neighbour is past their promised possession date without a completion on record.
- The completed cohort ran a median of 31 months from registration to its final promised date (422 completed registrations): the observed cycle time of this catchment.
- Of the 422 completed registrations, 322 (76%) carry an occupancy-certificate-shaped document on their register: the paper trail of delivery, read by document title.
Possession slip across the 5 km catchment
10The operator and the book
Vinay Agrawal carries 4 MahaRERA registrations, the first in 2017: 2 completed (1 on the first promised date), 0 lapsed, and the rest live.
- The live book beyond the subject is 1 active registration holding 145 filed units: the concurrent load the subject shares its management and its 70% accounts discipline with.
- None of the other registrations is in Thane: this district is a first outing for the promoter on MahaRERA.
- Across the whole book the filings disclose 69 buyer complaints and 0 court cases.
The book over time
The registrations, most recent first
| Project | District | Registered | Status | Units | % sold | Slip, mo |
|---|---|---|---|---|---|---|
| Balaji Symphony phase 4 | Raigarh | Jul 2021 | Active | 145 | 49.7% | 0 |
| Balaji Symphony | Raigarh | Jul 2017 | Completed | not filed | not filed | 0 |
| Balaji Symphony phase 2 | Raigarh | Jul 2017 | Completed | not filed | not filed | 12 |
How the book was assembled: 3 by the same MahaRERA promoter profile (definitive).
11The certifying bench
The professionals whose certificates move this project's money and progress, and how widely each signs across the district. A bench that signs many filings is established capacity; one that signs only this filing is new to the record, and both are facts a counterparty prices.
| Certifies | Name | Footprint |
|---|---|---|
| Architect | Vastospati | no other filing in Thane |
| Architect | Space age Consultant | 6 other filings in Thane |
| Architect | Pankaj Pandurang More | no other filing in Thane |
| Engineer | Epicon consultants pvt ltd | 8 other filings in Thane |
| Chartered Accountant | Vakilna & Co | no other filing in Thane |
Under RERA the architect certifies progress (Form 1), the engineer the works (Form 2), and the CA the cost and withdrawals from the 70% account (Form 3): these three signatures are what release the project's money.
The filing also names 1 other consultant: Bitush & Rajib Construction pvt ltd.
- 1 RERA-registered agent is empanelled on this project: its filed distribution reach. Agent identities and contact details are out of scope of this report by design.
12Cost structure and remaining spend
The promoter files a project cost of Rs 0.0 crore, of which Rs 0.0 crore (99.7%) is certified as incurred: Rs 0.0 crore of spend remains between here and the finished project, as filed.
- The filing records the 70% separate account with 1 bank entry: the account structure RERA's 70% rule runs through.
Estimated against incurred
| Cost head | Estimated, Rs cr | Incurred, Rs cr | Certified done |
|---|---|---|---|
| Wing B | 0.0 | 0.0 | 99.7% |
| Wing C | 0.0 | 0.0 | 99.7% |
| Wing E | 0.0 | 0.0 | 99.7% |
13The risk register
On the subject itself
- 3 buyer complaints are on the filing, by year of filing: 1 in 2021, 2 in 2023. Orders are on record for 3 of them.
- 1 matter has gone to the Appellate Tribunal on this project (latest status: Appeal Submitted): a dispute that outlived its first order.
Registrations that died with buyers inside
24 registrations within 5 km lapsed or were revoked at 50% sold or better. Each is a filed precedent of this micro-market taking money and not delivering a registration:
- 100% soldShadow Nest · 1.7 km · Lapsed · 21 units
- 100% soldMazagon Dock Meenakshi Co-Op Hsg Soc Ltd · 2.4 km · Lapsed · 1 units
- 100% soldBelleza · 2.8 km · Lapsed · 1 units
- 98.5% soldShikara Orchid · 0.9 km · Lapsed · 68 units
- 98.3% soldSpringfield 3 · 2.2 km · Lapsed · 58 units
32 neighbouring parcels carry a declared encumbrance: Balaji Symphony phase 4 (0.0 km), Olive Boulevard (0.1 km), Balaji Pride - Phase I (0.8 km), Bharat Enclave (1.5 km) and 28 more.
49 of the 857 catchment registrations (6%) disclose court cases, against 14% across the district; the heaviest is Hillshore 1,2,3,4,5,6,7,8,9,10,11 LCL - 0012 with 11 cases.
126 matters across 37 catchment projects have reached the Appellate Tribunal: disputes that outlived their first order.
14Extensions and regulatory friction
The subject has filed 3 extensions. The reasons below are the promoter's own words from the application, unedited beyond length:
Completion revised to Jun 2022
"Lack of manpower and supplies due to Covid-19 pandemic to finish construction of Phase III comprising of wings B, C and E."
Completion revised to Jun 2023
"We declare that the work has been 100% completed and the application for OC has been submitted. We will request you grant us an extension until 30th June 2023 under the Power of Authority to enable us to register the pending agreement of the allottees. We hereby assure you that we will acquire the Occupancy Certificate within the given time."
Completion revised to Jun 2028
"In accordance with circular no 28, we hereby apply for extension of our project order no. 40 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19"
175 of the 857 registrations within 5 km (20%) have filed at least one extension, against 24% across the district: the base rate of delay a business plan in this catchment competes with.
15Filing discipline
A counterparty that keeps filing is one still running the project. The last document here landed 170 days ago; the median active project in Thane last filed 96 days ago.
- 27 Feb 2026Architect certificate (Form 1), Engineer certificate (Form 2), CA certificate (Form 3)
- 24 Feb 2026Architect certificate (Form 1), Engineer certificate (Form 2), CA certificate (Form 3)
- 27 Feb 2025Architect certificate (Form 1), Engineer certificate (Form 2)
- 11 Feb 2025CA certificate (Form 3)
- 17 Aug 2024CA certificate (Form 3)
- 12 Aug 2024Architect certificate (Form 1), Engineer certificate (Form 2)
16What the documents say
- The register holds 146 filed documents, the latest on 27 February 2026.
- The newest legal title report is "1 Copy of the legal title report" (21 Jul 2017).
In the delivered analysis the filed documents behind this register, the title report, sanction letters and commencement certificates first among them, are read at generation time and summarised here in plain language with each document's own date: the chain of title, what exactly is sanctioned, and any condition a lender or partner would want quoted.
17Method and coverage
Every comparison in this analysis is computed from the promoters' own filings, joined across the corpus. This table is the basis and the coverage of each join, because a figure without its N is an assertion:
| Join | Basis | Coverage |
|---|---|---|
| Catchment rings | 2 km and 5 km straight-line from the filed coordinate | 857 registrations |
| Unit counts in the catchment | filed on a minority of projects; every unit total states its own N | 332 of 857 |
| Sales in the catchment | building-table sales, active projects only | 232 of 265 active |
| Parking comparables | filed parking over filed units | 781 of 857 |
| Pincode distributions | PIN 410206 | 2858 registrations |
| District distributions | Thane | 7,804 registrations |
| Intensity guard | filed built-up over plot, kept when 0.05x-15x | 2761 in the pincode, 90 excluded |
| Cost comparables | filed estimated cost over filed built-up, kept when Rs 2,000-400,000 per sq m | 2299 in the district |
| Filed land rates | plot agreement consideration over plot area (NA plot tables), kept when Rs 50-500,000 per sq m | 0 plot agreements across 12 catchment developments |
| Declared-delivery benchmark | promoters' own sworn past-project declarations, corpus-wide, judged only where both dates are declared | 46,307 declared projects |
| Promoter book | profile id (definitive), phase reference, normalised name (weaker, stated) | 3 by profile |
- The absorption read is a CROSS-SECTION: many projects of different ages photographed on the same day, never the sales history of one project. MahaRERA publishes current state only.
- Where two filed tables disagree (sales above all), the building table is used and the disagreement is shown, not resolved silently.
- Positions are stated as counts within a named set, never as scores. Nothing in this document is a recommendation.
18What the filings do not contain
- No flat prices. MahaRERA files no transaction values for apartments. The one exception in the whole corpus is the plotted (NA) tables, where sold plots carry their agreement consideration; where that exists it is read in Part II. For everything else, the land-transaction add-on exists because the answer needs registry records and human review, not this corpus.
- No carpet areas and no BHK mix. The per-unit configuration a launch plan needs is simply not in the filings; the massing figures in Part I are the closest filed proxy.
- No buyer identities or demand-side data. Who is absorbing this market cannot be read from RERA.
- A third of filings, and therefore some neighbours, carry no usable coordinate and fall outside every ring drawn here.
- No lapse dates. MahaRERA publishes only the status name; a lapsed registration was valid until its last filed completion date, and that is the only date stated.
- History accrues from observation. MahaRERA shows current state only; ReraGenie's change ledger records movement from the day it began watching, so trend depth grows with time and is stated wherever used.