Home / Browse projects / Mumbai Suburban, Maharashtra / MAHINDRA ALCOVE WING D AND E

Registration lapsed No litigation declared Residential / Group Housing project

MAHINDRA ALCOVE WING D AND E

By Mahindra Lifespace Developers limited

RG-MH-29389 · RERA P51800028352 · Last updated on MahaRERA portal: 15 Jan 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 4 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jun 2026Possession promised4 months past this date
2 of 22Construction stages doneacross 2 buildings; furthest along: Basement (if any), 60%
0Complaints at MahaRERAon this registration
Jump to the 138 documents Report an error

MAHINDRA ALCOVE WING D AND E is a Residential / Group Housing project by Mahindra Lifespace Developers limited in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800028352 on 18 Feb 2021. Possession was promised by 30 Jun 2026 and is now 4 months past that date.

At a glance

Project

  • NameMAHINDRA ALCOVE WING D AND E
  • TypeResidential / Group Housing
  • Location
    • VILLAGE SAKI in 'L' Ward
    • OFF SAKI VIHAR ROAD
    • CHANDIVALI
    • Kurla
    • Mumbai Suburban
    • 400072
  • Pincode400072
  • RERA no.P51800028352
  • ReraGenie IDRG-MH-29389

Builder

  • NameMahindra Lifespace Developers limited
  • Entity typeCompany
  • CINL45200MH1999PLC118949
  • CIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • ChairpersonArun Kumar Tilak Raj Nanda
  • Managing DirectorArvind Subramanian
  • Other registrations66 more →
  • Completed25 of 67
  • No longer live20 lapsed, de-registered or revoked
  • Declared earlier projects66 →

Key dates

4 months past promisethis monthRegisteredFeb 2021PromisedJun 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on18 Feb 2021
  • Promised completion30 Jun 2026
  • Revised completionNone
  • Buildings2 building records
  • Documents filed138 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Mahindra Alcove Wing DNA200000
Mahindra Alcove Wing ENA200000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 15 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Basement (if any), at 60%.

Mahindra Alcove Wing D29%
ActivityProgress
Excavation100%
Basement (if any)60%
Podiums (if any)50%
Plinth60%
Stilt Floor50%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Mahindra Alcove Wing E29%
ActivityProgress
Excavation100%
Basement (if any)60%
Podiums (if any)50%
Plinth60%
Stilt Floor50%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities17

As on 15 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable
Swimming PoolYes0%
ClubhouseYes0%

Parking filed177

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots177
Closed/Covered177
BuildingClosed/CoveredTotal
Mahindra Alcove Wing D105105
Mahindra Alcove Wing E7272

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area877 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
M/S. PAREKH & BROTHERSMumbai CityMumbai City

Approvals and building plan

Sanctioning authorityMUNICIPAL CORPORATION OF GREATER MUMBAI
Permissible FSI9191.55
Proposed, not sanctioned9,192 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAXIS BANK WORLI NAKA

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectEDIFICE
EngineerWTP Cost Advisory services India Pvt. Ltd.
Chartered AccountantP G BHAGWAT LLP
Chartered AccountantA B D AND CO LLP
PartnerRole in project
Mahindra Lifespace Developers limited-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 11 Mar 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 21 Mar 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 21 Mar 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 8 Dec 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed138

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 138 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Form 1 TD-E Q3 FY26.pdf15 Jan 2026
Form 2File: Form 2 TD-E Q3 FY26.pdf15 Jan 2026
Form 3File: Form 3 Q3FY26 TD-E.pdf15 Jan 2026
Disclosure of Sold and Booked InventoryFile: Alcove Q3 FY26 TD-E disclosure.pdf15 Jan 2026
Form 1File: Form 1 TD&E Q2FY26.pdf15 Oct 2025
Form 2File: Form 2 TD&E Q2FY26.pdf15 Oct 2025
Form 3File: Alcove Q2 FY26 TD&TE FORM3.pdf15 Oct 2025
Disclosure of Sold and Booked InventoryFile: Alcove Q2 FY26 TD&TE disclosure.pdf15 Oct 2025
Form 1File: Form 1 Alcove Wing D and E.pdf18 Jul 2025
Form 2File: Mahindra Alcove Wing D&E_250711193557_0001.pdf18 Jul 2025
Form 3File: Form 3_Alcove Wing D & E.pdf18 Jul 2025
Disclosure of Sold and Booked InventoryFile: Promoters Dec Tower D and E.pdf18 Jul 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Mahindra_Alcove_Wing_D___E_March_25-Final.pdf16 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Q4 FY 2025.pdf15 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Wing D-E.pdf14 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: wing D.pdf10 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: wing E.pdf10 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: wing D-E.pdf10 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Tower D - E.pdf2 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Tower D - E.pdf2 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Tower D and E.pdf14 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Tower D and E.pdf14 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: MLDL Alcove_WING-D and E_ Q2_FY25.pdf9 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Tower D.pdf9 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Tower E.pdf9 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Tower D.pdf9 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Tower E.pdf9 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: MLDL Alcove_WING-D and E_ Q2_FY25.pdf9 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Alcove D and E form 5.pdf8 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Alcove D and E form 5.pdf8 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Tower D.pdf19 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Tower E.pdf19 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_P51800028352_Alcove.pdf18 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Q1 Fy25.pdf18 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Tower D_E.pdf18 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: SKM_28724041718541.pdf18 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Tower D.pdf17 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Tower E.pdf17 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 14 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf17 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 01 FORM 3 _ALCOVE_Form_3_D_E.pdf17 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: M-MLDL-AND-Wing D-RERA Q3_2023_24_signed.pdf16 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: M-MLDL-AND-Wing E-RERA Q3_2023_24_signed.pdf16 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: MLDL CHANDIVALI_WING-D_E_ Q3_DEC23-Final_signed.pdf16 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ALCOVE__Dec_-23_D_E_signed.pdf16 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Alcove Quality Assurance Certificate_signed.pdf17 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: M-MLDL-AND-Wing D-RERA Q2_2023_24_signed.pdf16 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: M-MLDL-AND-Wing E-RERA Q2_2023_24_signed.pdf16 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: MLDL CHANDIVALI_WING-D_E_ Q2_SEPT23-Final_signed.pdf16 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: D_E_Sep23_CA_certificate_signed.pdf16 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Alcove D_E.pdf29 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: M-MLDL-AND-RERA Wing D-Q1-230705_signed.pdf15 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: M-MLDL-AND-RERA Wing E-Q1-230705_signed.pdf15 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: MLDL CHANDIVALI_WING-D_E_ Q1_JUNE23-Final_signed.pdf15 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Alcove_D_E wing_signed.pdf15 Jul 2023
Other - FinanceFile: PGB_MLDL RERA letter.pdf15 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: M-MLDL-AND-Wing D-RERA Q4_2022_23_signed.pdf19 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: M-MLDL-AND-Wing E-RERA Q4_2022_23_signed.pdf19 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: MLDL CHANDIVALI-WING-D_E-Q4-MAR23-Final_signed.pdf19 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Alcove Quality Assurance Certificate_signed.pdf19 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Alcove D _ E Cer Q4_signed.pdf19 Apr 2023
Other - TechnicalFile: Consolidated Declaration - no change in plans and FSI - Wing D and E - 14th April 2023.pdf14 Apr 2023
Layout approvalFile: 1-layout plan.pdf21 Mar 2023
Layout approvalFile: 2-STILT FLOOR.pdf21 Mar 2023
Layout approvalFile: 3-PARKING FLOOR.pdf21 Mar 2023
Building plan approvalFile: 17-WING D E.pdf21 Mar 2023
Building plan approvalFile: 18-WING D E.pdf21 Mar 2023
Building plan approvalFile: 19-WING D E.pdf21 Mar 2023
Building plan approvalFile: 20-WING D E.pdf21 Mar 2023
Building plan approvalFile: 21-WING D E.pdf21 Mar 2023
Building plan approvalFile: 22 -WING D E.pdf21 Mar 2023
Building plan approvalFile: 23-WING D E.pdf21 Mar 2023
Copy of Layout Approval (in case of layout)File: 1-layout plan.pdf21 Mar 2023
Copy of Layout Approval (in case of layout)File: 2-STILT FLOOR.pdf21 Mar 2023
Copy of Layout Approval (in case of layout)File: 3-PARKING FLOOR.pdf21 Mar 2023
Building Plan Approval / NA Order for plotted developmentFile: 17-WING D E.pdf21 Mar 2023
Building Plan Approval / NA Order for plotted developmentFile: 18-WING D E.pdf21 Mar 2023
Building Plan Approval / NA Order for plotted developmentFile: 19-WING D E.pdf21 Mar 2023
Building Plan Approval / NA Order for plotted developmentFile: 20-WING D E.pdf21 Mar 2023
Building Plan Approval / NA Order for plotted developmentFile: 21-WING D E.pdf21 Mar 2023
Building Plan Approval / NA Order for plotted developmentFile: 22 -WING D E.pdf21 Mar 2023

Promoter's earlier projects16

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

12 delivered on promise4 delivered late
ProjectLocationFlatsStatusPromisedDelivered
WindchimesMahindra Homes Pvt Ltd Sy No 37PART 2 37 PART 3 Opposite BPL Bannerghatta Road Arekere Bangalore 560075454CompletedDec 2018Dec 2018
Boisar Phase IIGut No.50 Plot No.1 Village Kambalgaon Taluka Palghar District Palghar238CompletedDec 2017Jun 2017
BOISAR Phase IGut No 50 Plot No 1 Village Kambalgaon Taluka Palghar District Palghar359CompletedJun 2017Jan 2017
LartistaMahindra Lifespace Developers Ltd Mahindra Towers 5th Floor Dr G M Bhosale Marg Worli Mumbai 400 01821CompletedSep 2016Sep 2016
Avadi Phase IBlock No 84 WARD No 1 Paruthipattu Village Avadi Municipalty Taluka Poonamallee604CompletedJun 2016Apr 2016
AshvitaMahindra Lifespace Developers Limited Sy No 78 PART 2 AND 78 PART3 Near Hitech city MMTS railway station Hafeezpet Road Kukatpally Hyderabad 500072664CompletedJun 2016May 2016
Aura PH5Village Chauma Sector 110A Gurgaon Manesar Urban Complex150CompletedJan 2015Late, Sep 2016
Aura PH4Village Chauma Sector 110A Gurgaon Manesar Urban Complex142CompletedJan 2015Late, Dec 2015
Aura PH3Village Chauma Sector 110A Gurgaon Manesar Urban Complex110CompletedOct 2014Late, Aug 2015
Aura PH2Village Chauma Sector 110A Gurgaon Manesar Urban Complex166CompletedNov 2013Late, Oct 2014
Splendour Phase 2CTS NO 617 part 617 30 617 39 PLOT B L B S Marg BHANDUP W MUMBAI 400078re233CompletedNov 2013Jun 2013
Aura PH1Village Chauma Sector 110A Gurgaon Manesar Urban Complex231CompletedMay 2013May 2013
AngelicaBldg C on plot bearing cts no 899 A TO E of village pahadi goregaon S.V.Road Mumbai67CompletedMar 2013Mar 2013
AspenBldg A on plot bearing cts no 899A TO E of village pahadi goregaon S.V.Road Mumbai68CompletedDec 2012Dec 2012
Splendour Phase 1CTS NO 617 part 617 30 617 39 PLOT B L B S Marg BHANDUP W MUMBAI 400078265CompletedAug 2011Aug 2011
ChlorisMilestone 16 PART 3 Sector 19 Faridabad160CompletedJul 2011Jul 2011

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MAHINDRA ALCOVE WING D AND E on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near CHANDIVALI6,700+ in Mumbai Suburban

Builder: Mahindra Lifespace Developers limited

Mahindra Lifespace Developers limited has 67 registrations on MahaRERA, including Antheia C1 and Antheia A4. Its filings disclose 66 earlier MahaRERA projects: declares 37 of 41 past projects completed on time. Litigation is declared on 7 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that MAHINDRA ALCOVE WING D AND E shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if MAHINDRA ALCOVE WING D AND E is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MAHINDRA ALCOVE WING D AND E?

The registered promoter entity is Mahindra Lifespace Developers limited, a company as per the filing. Its CIN L45200MH1999PLC118949 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MAHINDRA ALCOVE WING D AND E?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for MAHINDRA ALCOVE WING D AND E?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MAHINDRA ALCOVE WING D AND E?

The professionals named in the filing: Architect: EDIFICE; Engineer: WTP Cost Advisory services India Pvt. Ltd.; Chartered Accountant: P G BHAGWAT LLP; Chartered Accountant: A B D AND CO LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MAHINDRA ALCOVE WING D AND E?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MAHINDRA ALCOVE WING D AND E. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MAHINDRA ALCOVE WING D AND E to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.