New projects and RERA data in Ratnagiri district, Maharashtra

1170 projects are registered in Ratnagiri district: 20,737 units across them, 52 registered in the last 12 months. Sales and inventory trends accumulate from each future quarterly update; this page shows the first one.

1170Projects covered
52Registered, last 12 months
20,737Units declared
14,732Units not yet booked
181Completion dates revised
4With declared litigation

Of the 1170 covered registrations, 181 have revised their promised completion date and 4 declare litigation. The median project here is 23% booked as of the current data. Every figure comes from the projects' own MahaRERA filings.

Also free on ReraGenie: a monthly RERA report for the seven biggest markets in Maharashtra (Pune, Mumbai, Thane, Navi Mumbai, Nagpur, Nashik and Vasai-Virar): what registered that month, the possession pipeline and the busiest pincodes, from the filings. See the latest editions.

When Ratnagiri projects promise possession

Promised possession year as filed by the builder with MahaRERA, split by what the registration says today. Of 1,170 projects with a promised date, 493 are recorded delivered, 321 are still on the register and 356 have a registration that has lapsed or been cancelled.

DeliveredOn the registerRegistration lapsed or cancelled

050100150200today2017: 7 projects, delivered2017: 3 projects, registration lapsed or cancelled’172018: 54 projects, delivered2018: 2 projects, registration lapsed or cancelled’182019: 50 projects, delivered2019: 28 projects, registration lapsed or cancelled’192020: 20 projects, delivered2020: 10 projects, registration lapsed or cancelled’202021: 47 projects, delivered2021: 32 projects, registration lapsed or cancelled’212022: 70 projects, delivered2022: 58 projects, registration lapsed or cancelled’222023: 64 projects, delivered2023: 78 projects, registration lapsed or cancelled’232024: 72 projects, delivered2024: 51 projects, registration lapsed or cancelled’242025: 59 projects, delivered2025: 65 projects, registration lapsed or cancelled’252026: 29 projects, delivered2026: 72 projects, on the register2026: 26 projects, registration lapsed or cancelled’262027: 10 projects, delivered2027: 81 projects, on the register2027: 2 projects, registration lapsed or cancelled’272028: 10 projects, delivered2028: 82 projects, on the register2028: 1 projects, registration lapsed or cancelled’282029: 1 projects, delivered2029: 37 projects, on the register’292030: 29 projects, on the register’302031: 10 projects, on the register’312032: 4 projects, on the register’322033: 1 projects, on the register’332035: 3 projects, on the register’35

398 projects promise possession in 2026 or later. Years outside 2017 to 2035 hold 2 further projects and are not shown. Facts as per filings on RERA website.

01,2502,5003,7505,000today2017: 15 flats, delivered (only 1 of 10 projects filed a flat count)’172018: 91 flats, delivered (only 4 of 56 projects filed a flat count)’182019: 442 flats, delivered (only 11 of 78 projects filed a flat count)2019: 112 flats, registration lapsed or cancelled (only 11 of 78 projects filed a flat count)’192020: 435 flats, delivered (only 1 of 30 projects filed a flat count)’202021: 164 flats, delivered (only 7 of 79 projects filed a flat count)2021: 206 flats, registration lapsed or cancelled (only 7 of 79 projects filed a flat count)’212022: 358 flats, delivered (only 10 of 128 projects filed a flat count)2022: 442 flats, registration lapsed or cancelled (only 10 of 128 projects filed a flat count)’222023: 389 flats, delivered (only 13 of 142 projects filed a flat count)2023: 309 flats, registration lapsed or cancelled (only 13 of 142 projects filed a flat count)’232024: 1,024 flats, delivered (only 12 of 123 projects filed a flat count)2024: 207 flats, registration lapsed or cancelled (only 12 of 123 projects filed a flat count)’242025: 1,560 flats, delivered (only 30 of 124 projects filed a flat count)2025: 490 flats, registration lapsed or cancelled (only 30 of 124 projects filed a flat count)’252026: 523 flats, delivered2026: 2,341 flats, on the register2026: 762 flats, registration lapsed or cancelled’262027: 120 flats, delivered2027: 2,794 flats, on the register’272028: 228 flats, delivered2028: 2,448 flats, on the register’282029: 1,691 flats, on the register’292030: 2,048 flats, on the register’302031: 542 flats, on the register’312032: 438 flats, on the register’322033: 75 flats, on the register’332035: 169 flats, on the register’35

14,179 flats are promised in 2026 or later, across the 65% of those projects that file a flat count. Hatched years are ones where most builders never filed a count, so the bar understates real supply and cannot be compared with the years beside it. Years outside 2017 to 2035 hold 2 further projects and are not shown. Facts as per filings on RERA website.

How far Ratnagiri possession dates have moved

Builders may revise the possession date they filed at registration. Each bar is the year a project first promised, split by how far that date has since moved. 180 of 1,170 projects (15%) have moved at least once; the median move is 24 months and the longest is 129 months.

Kept the original dateMoved by under 2 yearsMoved by 2 years or more

050100150200Originally due 2017: 10 projects kept the original date, 100% of the year’17Originally due 2018: 54 projects kept the original date, 79% of the yearOriginally due 2018: 6 projects moved by under 2 years, 9% of the yearOriginally due 2018: 8 projects moved by 2 years or more, 12% of the year’18Originally due 2019: 74 projects kept the original date, 72% of the yearOriginally due 2019: 6 projects moved by under 2 years, 6% of the yearOriginally due 2019: 23 projects moved by 2 years or more, 22% of the year’19Originally due 2020: 23 projects kept the original date, 66% of the yearOriginally due 2020: 8 projects moved by under 2 years, 23% of the yearOriginally due 2020: 4 projects moved by 2 years or more, 11% of the year’20Originally due 2021: 68 projects kept the original date, 76% of the yearOriginally due 2021: 9 projects moved by under 2 years, 10% of the yearOriginally due 2021: 13 projects moved by 2 years or more, 14% of the year’21Originally due 2022: 106 projects kept the original date, 82% of the yearOriginally due 2022: 10 projects moved by under 2 years, 8% of the yearOriginally due 2022: 14 projects moved by 2 years or more, 11% of the year’22Originally due 2023: 123 projects kept the original date, 84% of the yearOriginally due 2023: 5 projects moved by under 2 years, 3% of the yearOriginally due 2023: 18 projects moved by 2 years or more, 12% of the year’23Originally due 2024: 113 projects kept the original date, 81% of the yearOriginally due 2024: 13 projects moved by under 2 years, 9% of the yearOriginally due 2024: 14 projects moved by 2 years or more, 10% of the year’24Originally due 2025: 92 projects kept the original date, 79% of the yearOriginally due 2025: 21 projects moved by under 2 years, 18% of the yearOriginally due 2025: 3 projects moved by 2 years or more, 3% of the year’25Originally due 2026: 84 projects kept the original date, 95% of the yearOriginally due 2026: 3 projects moved by under 2 years, 3% of the yearOriginally due 2026: 1 projects moved by 2 years or more, 1% of the year’26Originally due 2027: 75 projects kept the original date, 99% of the yearOriginally due 2027: 1 projects moved by under 2 years, 1% of the year’27Originally due 2028: 87 projects kept the original date, 100% of the year’28Originally due 2029: 37 projects kept the original date, 100% of the year’29Originally due 2030: 24 projects kept the original date, 100% of the year’30Originally due 2031: 10 projects kept the original date, 100% of the year’31Originally due 2032: 4 projects kept the original date, 100% of the year’32Originally due 2033: 1 projects kept the original date, 100% of the year’33Originally due 2035: 3 projects kept the original date, 100% of the year’35

Read down a bar to see how much of that year's cohort held its promise. Facts as per filings on RERA website.

01,2502,5003,7505,000Originally due 2017: 15 flats kept the original date, 100% of the year (only 1 of 10 projects filed a flat count)’17Originally due 2018: 91 flats kept the original date, 79% of the year (only 6 of 68 projects filed a flat count)Originally due 2018: 30 flats moved by under 2 years, 9% of the year (only 6 of 68 projects filed a flat count)Originally due 2018: 59 flats moved by 2 years or more, 12% of the year (only 6 of 68 projects filed a flat count)’18Originally due 2019: 524 flats kept the original date, 72% of the year (only 14 of 103 projects filed a flat count)Originally due 2019: 112 flats moved by 2 years or more, 22% of the year (only 14 of 103 projects filed a flat count)’19Originally due 2020: 435 flats kept the original date, 66% of the year (only 4 of 35 projects filed a flat count)Originally due 2020: 46 flats moved by under 2 years, 23% of the year (only 4 of 35 projects filed a flat count)Originally due 2020: 90 flats moved by 2 years or more, 11% of the year (only 4 of 35 projects filed a flat count)’20Originally due 2021: 370 flats kept the original date, 76% of the year (only 13 of 90 projects filed a flat count)Originally due 2021: 152 flats moved by under 2 years, 10% of the year (only 13 of 90 projects filed a flat count)Originally due 2021: 269 flats moved by 2 years or more, 14% of the year (only 13 of 90 projects filed a flat count)’21Originally due 2022: 602 flats kept the original date, 82% of the year (only 15 of 130 projects filed a flat count)Originally due 2022: 96 flats moved by under 2 years, 8% of the year (only 15 of 130 projects filed a flat count)Originally due 2022: 169 flats moved by 2 years or more, 11% of the year (only 15 of 130 projects filed a flat count)’22Originally due 2023: 581 flats kept the original date, 84% of the year (only 21 of 146 projects filed a flat count)Originally due 2023: 490 flats moved by 2 years or more, 12% of the year (only 21 of 146 projects filed a flat count)’23Originally due 2024: 1,214 flats kept the original date, 81% of the year (only 22 of 140 projects filed a flat count)Originally due 2024: 104 flats moved by under 2 years, 9% of the year (only 22 of 140 projects filed a flat count)Originally due 2024: 554 flats moved by 2 years or more, 10% of the year (only 22 of 140 projects filed a flat count)’24Originally due 2025: 1,710 flats kept the original date, 79% of the year (only 45 of 116 projects filed a flat count)Originally due 2025: 1,089 flats moved by under 2 years, 18% of the year (only 45 of 116 projects filed a flat count)Originally due 2025: 545 flats moved by 2 years or more, 3% of the year (only 45 of 116 projects filed a flat count)’25Originally due 2026: 2,123 flats kept the original date, 95% of the year (only 40 of 88 projects filed a flat count)Originally due 2026: 169 flats moved by under 2 years, 3% of the year (only 40 of 88 projects filed a flat count)Originally due 2026: 42 flats moved by 2 years or more, 1% of the year (only 40 of 88 projects filed a flat count)’26Originally due 2027: 1,954 flats kept the original date, 99% of the yearOriginally due 2027: 26 flats moved by under 2 years, 1% of the year’27Originally due 2028: 2,516 flats kept the original date, 100% of the year’28Originally due 2029: 1,613 flats kept the original date, 100% of the year’29Originally due 2030: 1,409 flats kept the original date, 100% of the year’30Originally due 2031: 542 flats kept the original date, 100% of the year’31Originally due 2032: 438 flats kept the original date, 100% of the year’32Originally due 2033: 75 flats kept the original date, 100% of the year’33Originally due 2035: 169 flats kept the original date, 100% of the year’35

Hatched years are ones where most builders never filed a flat count, so the bar understates the real total. Read down a bar to see how much of that year's cohort held its promise. Facts as per filings on RERA website.

Permissions and land in Ratnagiri

Whose name the land is in

Every one of the 1,170 registrations on this page answers this: on 638 the promoter is the only owner named; on 503 the promoter is an owner with other names on the file, which is what a joint development looks like on paper; on 29 the promoter is not an owner. Where other names are on the file, ask which of them signs your agreement for sale. A landowner who is not a party to it is a question for your lawyer before you pay, not a defect in the project.

Where in Ratnagiri: projects by taluka

1,170 of the 1,170 registrations on this page name their taluka.

TalukaProjectsShare
Ratnagiri37032%
Chiplun27223%
Dapoli19617%
Khed15413%
Guhagar867%
Lanja444%
3 other talukas484%

Projects in Ratnagiri

Showing 1 to 60 of 1,170 projects.

Largest first, by the unit count in the filing.

ProjectDeveloperUnitsBookedRegisteredStatus
Mandke LighthouseASGOLI GOAN, 415703Mandke and Mandke Infrastructure Pvt. Ltd.6920%27 Nov 2017Registered
TomorrowViewDistrict Ratnagiri, 415714House of Abhinandan Lodha Estate Holdings Private Limited49478%27 Mar 2023Completed
KONKAN TRAILS LIFESPACEFARASHI BUS STOP, 415712KONKANTRAILSLIFESPACELLP43514%12 Apr 2018Completed
Codename Tomorrowland Ph-2Padale, 415714House of Abhinandan Lodha Estate Holdings Private Limited38796%1 Oct 2021Completed
Cape of Bliss Phase 1ARatnagiri, 415712HOABL Management LLP38520%25 Aug 2023Completed
VIAA VISIONTADIL, 415712VIAA VISION3334%12 Nov 2018Registered
ARIHANT THE PARK PHASE - INEAR MIDC, 415639RATNAGIRI DREAM HOMES PVT. LTD.30961%1 Sep 2021Registered
Club OceanAsud, 415713Club Ocean Land Developers LLP2993%24 Nov 2025Registered
COASTAL BREEZEChandranagar, 415712UNIVERSAL PROPERTIES27539%20 Nov 2017Completed
OCEAN INFINITYFISHRISE COLLEGE, 415629DEEPAK YASHWANT SALVI25326%22 Nov 2019Registered
Horizon View ExoticMirjoli, 415605Nasir Abdul Rehaman Khot25015%13 Mar 2019Registered
Navkar EnclaveRatnagiri, 415612Evergreen Associates23719%10 May 2019Registration lapsed
Tomorroworld - Tomorrowland Phase IVPADLE, 415714House of Abhinandan Lodha Estate Holdings Private Limited23130%21 Nov 2022Completed
Kalpavriksha HeritageRatnagiri, 415612Kalpavriksha Builders & Developers22635%30 May 2020Registered
GOLD VALLEY SEA VIEW PHASE 1Velneshwar, 415729GOKANIRMITEE20351%7 Aug 2017Completed
Sea VistaMalgund, 415615Chaitanya Developers19877%9 Aug 2017Registered
VRUNDAVANGavhe, 415712EMPIRE REALTORS AND DEVELOPERS18910%24 Aug 2017Completed
SAI SAMARTH MAULILANJA, 416701SAMARTH BUILDER16737%31 Jul 2017Registered
Codename Tomorrowland Ph-3Anjarle, 415714House of Abhinandan Lodha Estate Holdings Private Limited15660%9 Feb 2022Completed
Cape of Bliss Phase IKolthare, 415712Lodha Management LLP15272%22 Feb 2023Completed
ROYAL CITY PARKKarvanchiwadi, 415639MAHESH AMRUTLAL BORIYA15230%5 Aug 2017Registration lapsed
LAXMI KEHSAV NAGAR PHASE IIGANESH NAGAR, 415612DEEPAK YASHWANT SALVI14386%4 Jul 2018Registered
PALM HORIZONTAL DAPOLI DIST RATNAGIRI, 415720SHIVKAILAS DEVELOPMENT CORPORATION1428%27 Oct 2022Registration lapsed
THE WINDNEAR GOVNMENT POLYTECHNIC COLLAGE, 415612Arihant Vastu Nirman Pvt. Ltd1426%20 Oct 2025Registered
Cape of Bliss 1BKolthare, 415712HOABL Management Private Limited1401%28 Aug 2025Registered
ANTARNADGimhavane, 415712GAURANG ASSOCIATES13455%1 Sep 2017Registration lapsed
ATRIAMirjoli, 415605Sushant Suresh Chiplunkar13311%21 Mar 2023Registered
Mangal MahalaxmiMahalaxmi Che Maal, 415712Mangal Builders13062%15 Jan 2018Registered
VARSAKOLTHARE DAPOLI, 415712PUSHPAM CITY SPACES DAPOLI LLP13011%2 May 2025Registered
SAI SAMARTH HERITAGELANJA, 416701SAI SAMARTH BUILDERS12742%28 Nov 2020Registered
ORCHID PLATINO PHASE - INachane, 415639ORCHID BUILDERS & DEVELOPERS1240%22 Jun 2026Registered
Taj City Centre and Taj ResidencyLanja, 416701K. M. DEVELOPERS12445%5 Mar 2019Registration lapsed
SIDDHIVINAYAK NAGAR PHASE - IVNachane, 415639Siddhivinayak Builders & Developers1200%16 Mar 2026Registered
Codename Tomorrowland Ph-1Padale, 415714House of Abhinandan Lodha Estate Holdings Private Limited11966%1 Oct 2021Completed
THE WOODLANDCH. SHIVAJI MAHARAJ NAGAR, 415612Siddhivinayak Realty11934%9 Aug 2023Registered
AKAR VANAJU ESTATERATNAGIRI, 415612AKAR INFRASTRUCTURE11622%7 Jan 2025Registered
Sun City Phase - IKhed, 415709Nitin Talathi & Co11628%8 Jan 2025Registered
GOLDEN HEIGHTSShringartali, 415724Qaisar Qasim Chunawala1150%1 Oct 2025Registered
PARKAR RESIDENCYGhanekhunt, 415722Altaf Ahmed Bebal1140%24 Sep 2025Registered
Ankoor SamayraKatalwadi, 415620Prolific Constructions1120%5 Mar 2019Registration lapsed
EKAANT FOREST HOMESJamsud, 415703AAKANKSHA AJAY SALVI11239%5 Aug 2017Completed
SYMPHONY PALMS PHASE 1Gavhe, 415712Konkan Vikas Development Company Ltd10936%22 Sep 2017Registration lapsed
Gold TowerBazaar peth, 415605Salim Haji yusuf Memon10725%3 Nov 2021Completed
AARAMBH HOMESSUPALWADI STOP, 415639YASHRAJ ENTERPRISES10642%24 Nov 2021Registered
H - CUBE - HAJI HAROON HEIGHTSM.G. Road, 415612AL - SHIFA DEVELOPERS10430%11 Oct 2021Registered
PHATAK SOLITAIREJalgaon, 415712M/s Phatak Developers10423%22 Jun 2022Completed
Avenew BuildconSukondi, 415714Avenew Buildcon1010%6 Mar 2023Registered
RAUT HEIGHTSDAPOLI, 415712RAUT BROTHERS9919%9 Apr 2019Registered
SINDHURATNA ENCLAVEKODAVALI, 416720SINDHURATNA BUILDERS AND DEVELOPERS9865%20 Apr 2018Registered
DISHA HEIGHTSPimpli Khurd Chiplun, 415604DISHA ASSOCIATES972%18 Feb 2026Registered
Modern HeightsKherdi (CT), 415605Modern Construction961%16 Oct 2017Registered
Neermiti ResidencyShanti Nagar, 415639Imran Mujahid Mulla960%16 May 2024Registered
PADMAVATIKolthare, 415712LODHA ASSOCIATES960%8 Aug 2019Completed
KKSHITIJGurhekar wadi, 415703MARVEL REALTY940%24 Apr 2018De-registered
Anand ParkKarvanchiwadi, 415639SD Associates9329%19 Jul 2023Registered
FATIMA HEIGHTSOPP BANDHKAM BHAWAN, 415605ROZI CONSTRUCTION AND DEVELOPERS9119%20 Apr 2022Registered
PAYASDAANKOLTHARE, 415712SANDEEP NARENDRAKUMAR SHAH9197%21 Jan 2020Registered
R R COMPLEXDERVAN FATA, 415606TAMANNA BUILDERS & DEVELOPERS9017%24 Feb 2023Registered
SIDDHATANU LANDMARKAT CAMP DAPOLI, 415712SIDDHTANU DEVELOVERS900%11 Aug 2026Registered
CITY PRIDEMandangad, 415203Mahammad Salim Sayyad8538%15 Oct 2021Registered
Planning a launch in Ratnagiri? The area market report packs one pincode's whole filed market into one document: every registration and what it has become, when the active stock promises to land, what the market absorbs, the operators and who finances them. A flat Rs 2,999 per pincode. Area report · Rs 2,999  Read a full sample

Developers active in Ratnagiri

Samir Shrinivas Kale (36), Arihant Vastu Nirman Pvt. Ltd (14), Prasad Prabhakar Waghdhare (10), Dinesh Mohanlal Jain (8), House of Abhinandan Lodha Estate Holdings Private Limited (7), DEEPAK YASHWANT SALVI (7). Each link opens the promoter's track record built from their own filings.

Frequently asked questions

How do I shortlist among the Ratnagiri projects listed above?

Compare each project against its neighbours, not against the brochure. The median project on this page is 23% booked, which is the benchmark to hold any single project against. A project selling much slower than the district may have a pricing or credibility problem; one selling much faster deserves a look at whether construction is keeping pace with collections. Then open the developer link to check their delivery record on other projects, and compare filed carpet areas rather than super built-up marketing areas.

What does a revised completion date on a Ratnagiri project actually mean?

The promoter has moved their deadline with the regulator, usually under section 6, which allows an extension of up to one year for reasons beyond their control. It does not move the date in your agreement for sale: your section 18 claim for delay interest or refund runs from the possession date you signed for. Before booking a project with a revision on record, ask which approvals or works the new date depends on.

What stamp duty will I pay on a flat in Ratnagiri district?

The rate depends on the local body: roughly 6 to 7 percent inside municipal corporations, 4 percent in municipal council areas and 3 percent in gram panchayat areas, with women buying in their sole name paying 1 percent less. The registration fee is 1 percent of value, capped at Rs 30,000. Duty is charged on the higher of your agreement value and the ready reckoner value. ReraGenie has a free Maharashtra stamp duty calculator under Tools.

What does it mean that some Ratnagiri registrations have lapsed?

A RERA registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then, the registration lapses and the project stops being a registered project: the promoter may not legally market or sell in it, and the Authority can act under section 7 against a defaulting promoter. It does not cancel your agreement for sale or your section 18 rights if you have already booked, and it does not mean construction has stopped. Ask the promoter for the current registration position in writing, and verify it on the MahaRERA portal before you pay any further instalment.

What if a Ratnagiri project shows strong sales but slow construction?

That shape means the promoter is collecting money faster than they are building, which is fine under a disciplined promoter and dangerous under a stretched one. The law helps: withdrawals from the project account need architect, engineer and CA certificates in proportion to progress. Check the promoter's delivery record, and watch the next quarterly filing (due within 20 days of each quarter end) to see whether the construction line moves.

Does something here look wrong, or is there a number you expected to find and did not? Every figure on this page is summed from the projects' own MahaRERA filings, and we read every report.

Report an errorShare feedback

Data from official MahaRERA filings.

Report an error or share feedback

About Ratnagiri district. Every figure on this page is summed from the projects' own filings, so if a number looks wrong it helps to say which one.