New projects and RERA data in Ratnagiri district, Maharashtra
1170 projects are registered in Ratnagiri district: 20,737 units across them, 52 registered in the last 12 months. Sales and inventory trends accumulate from each future quarterly update; this page shows the first one.
Of the 1170 covered registrations, 181 have revised their promised completion date and 4 declare litigation. The median project here is 23% booked as of the current data. Every figure comes from the projects' own MahaRERA filings.
Also free on ReraGenie: a monthly RERA report for the seven biggest markets in Maharashtra (Pune, Mumbai, Thane, Navi Mumbai, Nagpur, Nashik and Vasai-Virar): what registered that month, the possession pipeline and the busiest pincodes, from the filings. See the latest editions.
When Ratnagiri projects promise possession
Promised possession year as filed by the builder with MahaRERA, split by what the registration says today. Of 1,170 projects with a promised date, 493 are recorded delivered, 321 are still on the register and 356 have a registration that has lapsed or been cancelled.
DeliveredOn the registerRegistration lapsed or cancelled
398 projects promise possession in 2026 or later. Years outside 2017 to 2035 hold 2 further projects and are not shown. Facts as per filings on RERA website.
14,179 flats are promised in 2026 or later, across the 65% of those projects that file a flat count. Hatched years are ones where most builders never filed a count, so the bar understates real supply and cannot be compared with the years beside it. Years outside 2017 to 2035 hold 2 further projects and are not shown. Facts as per filings on RERA website.
How far Ratnagiri possession dates have moved
Builders may revise the possession date they filed at registration. Each bar is the year a project first promised, split by how far that date has since moved. 180 of 1,170 projects (15%) have moved at least once; the median move is 24 months and the longest is 129 months.
Kept the original dateMoved by under 2 yearsMoved by 2 years or more
Read down a bar to see how much of that year's cohort held its promise. Facts as per filings on RERA website.
Hatched years are ones where most builders never filed a flat count, so the bar understates the real total. Read down a bar to see how much of that year's cohort held its promise. Facts as per filings on RERA website.
Permissions and land in Ratnagiri
Whose name the land is in
Every one of the 1,170 registrations on this page answers this: on 638 the promoter is the only owner named; on 503 the promoter is an owner with other names on the file, which is what a joint development looks like on paper; on 29 the promoter is not an owner. Where other names are on the file, ask which of them signs your agreement for sale. A landowner who is not a party to it is a question for your lawyer before you pay, not a defect in the project.
Where in Ratnagiri: projects by taluka
1,170 of the 1,170 registrations on this page name their taluka.
| Taluka | Projects | Share |
|---|---|---|
| Ratnagiri | 370 | 32% |
| Chiplun | 272 | 23% |
| Dapoli | 196 | 17% |
| Khed | 154 | 13% |
| Guhagar | 86 | 7% |
| Lanja | 44 | 4% |
| 3 other talukas | 48 | 4% |
Projects in Ratnagiri
Showing 1 to 60 of 1,170 projects.
Largest first, by the unit count in the filing.
| Project | Developer | Units | Booked | Registered | Status |
|---|---|---|---|---|---|
| Mandke LighthouseASGOLI GOAN, 415703 | Mandke and Mandke Infrastructure Pvt. Ltd. | 692 | 0% | 27 Nov 2017 | Registered |
| TomorrowViewDistrict Ratnagiri, 415714 | House of Abhinandan Lodha Estate Holdings Private Limited | 494 | 78% | 27 Mar 2023 | Completed |
| KONKAN TRAILS LIFESPACEFARASHI BUS STOP, 415712 | KONKANTRAILSLIFESPACELLP | 435 | 14% | 12 Apr 2018 | Completed |
| Codename Tomorrowland Ph-2Padale, 415714 | House of Abhinandan Lodha Estate Holdings Private Limited | 387 | 96% | 1 Oct 2021 | Completed |
| Cape of Bliss Phase 1ARatnagiri, 415712 | HOABL Management LLP | 385 | 20% | 25 Aug 2023 | Completed |
| VIAA VISIONTADIL, 415712 | VIAA VISION | 333 | 4% | 12 Nov 2018 | Registered |
| ARIHANT THE PARK PHASE - INEAR MIDC, 415639 | RATNAGIRI DREAM HOMES PVT. LTD. | 309 | 61% | 1 Sep 2021 | Registered |
| Club OceanAsud, 415713 | Club Ocean Land Developers LLP | 299 | 3% | 24 Nov 2025 | Registered |
| COASTAL BREEZEChandranagar, 415712 | UNIVERSAL PROPERTIES | 275 | 39% | 20 Nov 2017 | Completed |
| OCEAN INFINITYFISHRISE COLLEGE, 415629 | DEEPAK YASHWANT SALVI | 253 | 26% | 22 Nov 2019 | Registered |
| Horizon View ExoticMirjoli, 415605 | Nasir Abdul Rehaman Khot | 250 | 15% | 13 Mar 2019 | Registered |
| Navkar EnclaveRatnagiri, 415612 | Evergreen Associates | 237 | 19% | 10 May 2019 | Registration lapsed |
| Tomorroworld - Tomorrowland Phase IVPADLE, 415714 | House of Abhinandan Lodha Estate Holdings Private Limited | 231 | 30% | 21 Nov 2022 | Completed |
| Kalpavriksha HeritageRatnagiri, 415612 | Kalpavriksha Builders & Developers | 226 | 35% | 30 May 2020 | Registered |
| GOLD VALLEY SEA VIEW PHASE 1Velneshwar, 415729 | GOKANIRMITEE | 203 | 51% | 7 Aug 2017 | Completed |
| Sea VistaMalgund, 415615 | Chaitanya Developers | 198 | 77% | 9 Aug 2017 | Registered |
| VRUNDAVANGavhe, 415712 | EMPIRE REALTORS AND DEVELOPERS | 189 | 10% | 24 Aug 2017 | Completed |
| SAI SAMARTH MAULILANJA, 416701 | SAMARTH BUILDER | 167 | 37% | 31 Jul 2017 | Registered |
| Codename Tomorrowland Ph-3Anjarle, 415714 | House of Abhinandan Lodha Estate Holdings Private Limited | 156 | 60% | 9 Feb 2022 | Completed |
| Cape of Bliss Phase IKolthare, 415712 | Lodha Management LLP | 152 | 72% | 22 Feb 2023 | Completed |
| ROYAL CITY PARKKarvanchiwadi, 415639 | MAHESH AMRUTLAL BORIYA | 152 | 30% | 5 Aug 2017 | Registration lapsed |
| LAXMI KEHSAV NAGAR PHASE IIGANESH NAGAR, 415612 | DEEPAK YASHWANT SALVI | 143 | 86% | 4 Jul 2018 | Registered |
| PALM HORIZONTAL DAPOLI DIST RATNAGIRI, 415720 | SHIVKAILAS DEVELOPMENT CORPORATION | 142 | 8% | 27 Oct 2022 | Registration lapsed |
| THE WINDNEAR GOVNMENT POLYTECHNIC COLLAGE, 415612 | Arihant Vastu Nirman Pvt. Ltd | 142 | 6% | 20 Oct 2025 | Registered |
| Cape of Bliss 1BKolthare, 415712 | HOABL Management Private Limited | 140 | 1% | 28 Aug 2025 | Registered |
| ANTARNADGimhavane, 415712 | GAURANG ASSOCIATES | 134 | 55% | 1 Sep 2017 | Registration lapsed |
| ATRIAMirjoli, 415605 | Sushant Suresh Chiplunkar | 133 | 11% | 21 Mar 2023 | Registered |
| Mangal MahalaxmiMahalaxmi Che Maal, 415712 | Mangal Builders | 130 | 62% | 15 Jan 2018 | Registered |
| VARSAKOLTHARE DAPOLI, 415712 | PUSHPAM CITY SPACES DAPOLI LLP | 130 | 11% | 2 May 2025 | Registered |
| SAI SAMARTH HERITAGELANJA, 416701 | SAI SAMARTH BUILDERS | 127 | 42% | 28 Nov 2020 | Registered |
| ORCHID PLATINO PHASE - INachane, 415639 | ORCHID BUILDERS & DEVELOPERS | 124 | 0% | 22 Jun 2026 | Registered |
| Taj City Centre and Taj ResidencyLanja, 416701 | K. M. DEVELOPERS | 124 | 45% | 5 Mar 2019 | Registration lapsed |
| SIDDHIVINAYAK NAGAR PHASE - IVNachane, 415639 | Siddhivinayak Builders & Developers | 120 | 0% | 16 Mar 2026 | Registered |
| Codename Tomorrowland Ph-1Padale, 415714 | House of Abhinandan Lodha Estate Holdings Private Limited | 119 | 66% | 1 Oct 2021 | Completed |
| THE WOODLANDCH. SHIVAJI MAHARAJ NAGAR, 415612 | Siddhivinayak Realty | 119 | 34% | 9 Aug 2023 | Registered |
| AKAR VANAJU ESTATERATNAGIRI, 415612 | AKAR INFRASTRUCTURE | 116 | 22% | 7 Jan 2025 | Registered |
| Sun City Phase - IKhed, 415709 | Nitin Talathi & Co | 116 | 28% | 8 Jan 2025 | Registered |
| GOLDEN HEIGHTSShringartali, 415724 | Qaisar Qasim Chunawala | 115 | 0% | 1 Oct 2025 | Registered |
| PARKAR RESIDENCYGhanekhunt, 415722 | Altaf Ahmed Bebal | 114 | 0% | 24 Sep 2025 | Registered |
| Ankoor SamayraKatalwadi, 415620 | Prolific Constructions | 112 | 0% | 5 Mar 2019 | Registration lapsed |
| EKAANT FOREST HOMESJamsud, 415703 | AAKANKSHA AJAY SALVI | 112 | 39% | 5 Aug 2017 | Completed |
| SYMPHONY PALMS PHASE 1Gavhe, 415712 | Konkan Vikas Development Company Ltd | 109 | 36% | 22 Sep 2017 | Registration lapsed |
| Gold TowerBazaar peth, 415605 | Salim Haji yusuf Memon | 107 | 25% | 3 Nov 2021 | Completed |
| AARAMBH HOMESSUPALWADI STOP, 415639 | YASHRAJ ENTERPRISES | 106 | 42% | 24 Nov 2021 | Registered |
| H - CUBE - HAJI HAROON HEIGHTSM.G. Road, 415612 | AL - SHIFA DEVELOPERS | 104 | 30% | 11 Oct 2021 | Registered |
| PHATAK SOLITAIREJalgaon, 415712 | M/s Phatak Developers | 104 | 23% | 22 Jun 2022 | Completed |
| Avenew BuildconSukondi, 415714 | Avenew Buildcon | 101 | 0% | 6 Mar 2023 | Registered |
| RAUT HEIGHTSDAPOLI, 415712 | RAUT BROTHERS | 99 | 19% | 9 Apr 2019 | Registered |
| SINDHURATNA ENCLAVEKODAVALI, 416720 | SINDHURATNA BUILDERS AND DEVELOPERS | 98 | 65% | 20 Apr 2018 | Registered |
| DISHA HEIGHTSPimpli Khurd Chiplun, 415604 | DISHA ASSOCIATES | 97 | 2% | 18 Feb 2026 | Registered |
| Modern HeightsKherdi (CT), 415605 | Modern Construction | 96 | 1% | 16 Oct 2017 | Registered |
| Neermiti ResidencyShanti Nagar, 415639 | Imran Mujahid Mulla | 96 | 0% | 16 May 2024 | Registered |
| PADMAVATIKolthare, 415712 | LODHA ASSOCIATES | 96 | 0% | 8 Aug 2019 | Completed |
| KKSHITIJGurhekar wadi, 415703 | MARVEL REALTY | 94 | 0% | 24 Apr 2018 | De-registered |
| Anand ParkKarvanchiwadi, 415639 | SD Associates | 93 | 29% | 19 Jul 2023 | Registered |
| FATIMA HEIGHTSOPP BANDHKAM BHAWAN, 415605 | ROZI CONSTRUCTION AND DEVELOPERS | 91 | 19% | 20 Apr 2022 | Registered |
| PAYASDAANKOLTHARE, 415712 | SANDEEP NARENDRAKUMAR SHAH | 91 | 97% | 21 Jan 2020 | Registered |
| R R COMPLEXDERVAN FATA, 415606 | TAMANNA BUILDERS & DEVELOPERS | 90 | 17% | 24 Feb 2023 | Registered |
| SIDDHATANU LANDMARKAT CAMP DAPOLI, 415712 | SIDDHTANU DEVELOVERS | 90 | 0% | 11 Aug 2026 | Registered |
| CITY PRIDEMandangad, 415203 | Mahammad Salim Sayyad | 85 | 38% | 15 Oct 2021 | Registered |
Developers active in Ratnagiri
Samir Shrinivas Kale (36), Arihant Vastu Nirman Pvt. Ltd (14), Prasad Prabhakar Waghdhare (10), Dinesh Mohanlal Jain (8), House of Abhinandan Lodha Estate Holdings Private Limited (7), DEEPAK YASHWANT SALVI (7). Each link opens the promoter's track record built from their own filings.
Frequently asked questions
How do I shortlist among the Ratnagiri projects listed above?
Compare each project against its neighbours, not against the brochure. The median project on this page is 23% booked, which is the benchmark to hold any single project against. A project selling much slower than the district may have a pricing or credibility problem; one selling much faster deserves a look at whether construction is keeping pace with collections. Then open the developer link to check their delivery record on other projects, and compare filed carpet areas rather than super built-up marketing areas.
What does a revised completion date on a Ratnagiri project actually mean?
The promoter has moved their deadline with the regulator, usually under section 6, which allows an extension of up to one year for reasons beyond their control. It does not move the date in your agreement for sale: your section 18 claim for delay interest or refund runs from the possession date you signed for. Before booking a project with a revision on record, ask which approvals or works the new date depends on.
What stamp duty will I pay on a flat in Ratnagiri district?
The rate depends on the local body: roughly 6 to 7 percent inside municipal corporations, 4 percent in municipal council areas and 3 percent in gram panchayat areas, with women buying in their sole name paying 1 percent less. The registration fee is 1 percent of value, capped at Rs 30,000. Duty is charged on the higher of your agreement value and the ready reckoner value. ReraGenie has a free Maharashtra stamp duty calculator under Tools.
What does it mean that some Ratnagiri registrations have lapsed?
A RERA registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then, the registration lapses and the project stops being a registered project: the promoter may not legally market or sell in it, and the Authority can act under section 7 against a defaulting promoter. It does not cancel your agreement for sale or your section 18 rights if you have already booked, and it does not mean construction has stopped. Ask the promoter for the current registration position in writing, and verify it on the MahaRERA portal before you pay any further instalment.
What if a Ratnagiri project shows strong sales but slow construction?
That shape means the promoter is collecting money faster than they are building, which is fine under a disciplined promoter and dangerous under a stretched one. The law helps: withdrawals from the project account need architect, engineer and CA certificates in proportion to progress. Check the promoter's delivery record, and watch the next quarterly filing (due within 20 days of each quarter end) to see whether the construction line moves.
Does something here look wrong, or is there a number you expected to find and did not? Every figure on this page is summed from the projects' own MahaRERA filings, and we read every report.
Report an errorShare feedbackData from official MahaRERA filings.