Home / Browse projects / Ratnagiri, Maharashtra / Mangal Mahalaxmi
Mangal Mahalaxmi
RG-MH-60651 · RERA P52800014983 · Last updated on MahaRERA portal: 21 May 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 61 months
- 6 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Ratnagiri registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Mangal Mahalaxmi is a Others project by Mangal Builders in Ratnagiri, Maharashtra, registered with MahaRERA as P52800014983 on 15 Jan 2018. Possession is promised by 31 Dec 2026. The completion date has moved by 61 months from the original filing. 80 of the 130 units on this registration are recorded sold or booked, and 30 of 55 construction stages are filed complete.
At a glance
Project
- NameMangal Mahalaxmi
- TypeOthers
- Location
- Opposite Mahalaxmi Temple
- Mahalaxmi Che Maal
- Brahmanwadi
- Dapoli
- Ratnagiri
- 415712
- Pincode415712
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52800014983
- ReraGenie IDRG-MH-60651
Builder
- NameMangal Builders
- Entity typePartnership
- PartnersBhuendrakumar Bhikamchand Jain, Mangal Shubh Vastu LLP
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on15 Jan 2018
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 28 Nov 2021)
- Buildings5 building records
- Documents filed119 files
Current status
Figures as on 21 May 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Building A | NA | 4 | 4 | 16 | 0 | 16 |
| Building B | NA | 4 | 4 | 42 | 0 | 42 |
| Building C and D | NA | 3 | 3 | 24 | 9 | 33 |
| Building E | NA | 4 | 4 | 24 | 0 | 24 |
| Building F | NA | 3 | 3 | 15 | 0 | 15 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building5
As on 21 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
30 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Staircases, at 84%.
Building A73%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 5% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building B63%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 9% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 80% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 75% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 75% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 70% |
Building C and D73%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 4% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building E65%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 7% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 80% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 84% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 82% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 80% |
Building F73%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 4% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 21 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 90% |
| Water Supply | Yes | 90% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 90% |
| Storm Water Drains | Yes | 80% |
| Landscaping & Tree Planting | Yes | 60% |
| Street Lighting | Yes | 80% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 80% |
| Solid Waste Management And Disposal | Yes | 70% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 85% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed149
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| Building A | 2 | 17 | 19 |
| Building B | 3 | 44 | 47 |
| Building C and D | 5 | 28 | 33 |
| Building E | 4 | 30 | 34 |
| Building F | 0 | 16 | 16 |
Land and ownership4
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Dinesh Narayan Jadhav | Brahmanwadi | Ratnagiri |
| Vishwas Parshuram Khanwilkar | Khed (M Cl) | Ratnagiri |
| Suyog Sakharam Kadam | Khed (M Cl) | Ratnagiri |
| Malti Mahadev Ghole | Brahmanwadi | Ratnagiri |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Building B | NA | Rs 4.00 cr | Rs 2.60 cr |
| Building E | NA | Rs 3.17 cr | Rs 2.27 cr |
| Building A | NA | Rs 2.66 cr | Rs 2.50 cr |
| Building C and D | NA | Rs 2.62 cr | Rs 2.62 cr |
| Building F | NA | Rs 1.49 cr | Rs 1.49 cr |
| - | NA | Rs 54.33 lakh | Rs 32.19 lakh |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Jay Aeram |
| Engineer | Pravin Landge |
| Chartered Accountant | A N J K & CO LLP |
| Chartered Accountant | G N MANTRI AND ASSOCIATES |
| Partner | Role in project |
|---|---|
| Mangal Builders | - |
Extensions applied for6
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe project has been delayed on account of first wave of Covid -19, which started from second half of March 2020 and lasted till December 2020 i.e 9 months. During this period cyclone “Nisarga’ also impacted the project. The activities came to total standstill during this period. Further it was very difficult to get the labourers thereafter as most of the labourers from other states migrated and they started coming back only in the month of January and February 2021. During the month of April 2021, as the second wave of Covid-19 causalities increased, the lockdown was imposed in Maharashtra. T
Reason as filed by the promoterThe project site is located at Dapoli , District Ratnagiri. The area is prone to heavy rainfall. The construction was disturbed due to heavy rains. The commencement of construction activity was further delayed due to shortage of electricity, impacted movement of material and labour. The project comprise of five buildings A, B , CD, E and F. We have completed the construction of buildings CD and F and A , B and E are in progress.
Reason as filed by the promoterThe Project has been delayed on account of First & second wave of Covid-19 for almost 1 and half year due to which lockdown was imposed in Maharashtra. The lockdown restrictions impacted the movement of material & labour resulting into suspension of construction activities. Further project was suspended during the period May & June 2021 due to cyclone “Tauktae”.
Reason as filed by the promoterThe Project has been delayed on account of First & second wave of Covid-19 for almost 1 and half year due to which lockdown was imposed in Maharashtra. The lockdown restrictions impacted the movement of material & labour resulting into suspension of construction activities. Further project was suspended during the period May & June 2021 due to cyclone “Tauktae”. Due to unavailability of required material & labour project completion is getting delayed. However as on date 90% project is completed. Project is almost 90% is completed as per Architect certificates.
Reason as filed by the promoterWe, hereby apply for extension u/s 7(3) of the registered project bearing vide no. P52800014983 up to 30/12/2025.
Reason as filed by the promoterWe have obtained Occupancy Certificate dated 05/06/2025 for the Following Buildings - Building A, Building C and D, Building F. The above-mentioned buildings are complete in all aspects with respect to construction and development works. The Project has been affected by the shortage of skilled labour force due to the recent festive seasons. Shortage of raw material has also resulted into the delay of the construction in view of the latest sanctioned plans received for Building B and Building E upto the Parking + 6 Floors
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 3 Jan 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 16 Jul 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 18 Jul 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 3 Jan 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2026
Documents filed119
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 119 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 Architect Certificate March 2026.pdf | 21 May 2026 |
| Withdrawal Update Form 2File: Form 2 Engineers Certificate March 2026.pdf | 21 May 2026 |
| Withdrawal Update Form 3File: Form 3 CA Certificate March 2026_11zon.pdf | 21 May 2026 |
| Withdrawal Update Form 1File: form 1 Architect Certificate - Dec 2025.pdf | 18 Feb 2026 |
| Withdrawal Update Form 2File: form 2 Engineer Certificate - Dec 2025.pdf | 18 Feb 2026 |
| Withdrawal Update Form 3File: Form 3 CA Certificate - Dec 2025.pdf | 18 Feb 2026 |
| Form 1File: Form 1 Architect Certificate -March 2025.pdf | 20 Nov 2025 |
| Form 2File: Form 2 Engineer Certificate - March 2025.pdf | 20 Nov 2025 |
| Form 3File: CA Certificate - March 2025 - Sign.pdf | 20 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Inventory - June 2025.pdf | 20 Nov 2025 |
| Withdrawal Update Form 1File: Form 1 Architect Certificate -March 2025.pdf | 20 Nov 2025 |
| Withdrawal Update Form 1File: Form 1 Architect Certificate - June 2025.pdf | 20 Nov 2025 |
| Withdrawal Update Form 1File: Form 1 Architect Certificate - September 2025.pdf | 20 Nov 2025 |
| Withdrawal Update Form 2File: Form 2 Engineer Certificate - March 2025.pdf | 20 Nov 2025 |
| Withdrawal Update Form 2File: Form 2 Engineer Certificate - June 2025.pdf | 20 Nov 2025 |
| Withdrawal Update Form 2File: Form 2 Engineer Certificate - September 2025.pdf | 20 Nov 2025 |
| Withdrawal Update Form 3File: CA Certificate - March 2025 - Sign.pdf | 20 Nov 2025 |
| Withdrawal Update Form 3File: CA Certificate - June 2025 - Sign.pdf | 20 Nov 2025 |
| Withdrawal Update Form 3File: Form 3 CA Certificate - September 2025 - Sign.pdf | 20 Nov 2025 |
| Form 5 (FY 2024-2025)File: Form 5 Annual Audit Report for Mangal Mahalaxmi FY 2024-25.pdf | 20 Nov 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Annual Audit Report - FY 2023-24 - Sign.pdf | 21 Mar 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate - June 2024.pdf | 20 Mar 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate - September 2024.pdf | 20 Mar 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate - December 2024.pdf | 20 Mar 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate - June 2024.pdf | 20 Mar 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate - September 2024.pdf | 20 Mar 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate - December 2024.pdf | 20 Mar 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Quality Assurance Certificate - March 2021.pdf | 20 Mar 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A Quality Assurance Certificate - March 2022.pdf | 20 Mar 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Quality Assurance Certificate - March 2023.pdf | 20 Mar 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Quality Assurance Certificate - March 2024.pdf | 7 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Inventory - June 2024.pdf | 6 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Inventory - September 2024.pdf | 6 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Inventory - December 2024.pdf | 6 Mar 2025 |
| Details of encumbrances concerned to FinanceFile: Encumbrance certificate with Finance and Legal.pdf | 5 Mar 2025 |
| Declaration in FORM BFile: Form B -Declaration by promoter.pdf | 5 Mar 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate - June 2024.pdf | 5 Mar 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate - September 2024.pdf | 5 Mar 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate - December 2024.pdf | 5 Mar 2025 |
| Certificates of CA (Form 3)File: CA Certificate - June 2024 - Signed.pdf | 5 Mar 2025 |
| Certificates of CA (Form 3)File: CA Certificate - September 2024 - Signed.pdf | 5 Mar 2025 |
| Certificates of CA (Form 3)File: CA Certificate - December 2024 - Signed.pdf | 5 Mar 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate - June 2024.pdf | 5 Mar 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate - September 2024.pdf | 5 Mar 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate - December 2024.pdf | 5 Mar 2025 |
| CERSAI detailsFile: CERSAI Declaration.pdf | 5 Mar 2025 |
| Details of encumbrances concerned to LegalFile: Encumbrance certificate with Finance and Legal.pdf | 5 Mar 2025 |
| Other - TechnicalFile: Plinth Certificate.pdf | 5 Mar 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form_5_Mangal_Builders_22-23.pdf | 6 Aug 2024 |
| Declaration in FORM BFile: form B affidavit.pdf | 9 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: disclosure of inventory.pdf | 9 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form_1_Q1.pdf | 29 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form_1_Q2.pdf | 29 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form_1_Q3.pdf | 29 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form_1_Q4.pdf | 29 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: MB_Int_25Jun23.pdf | 29 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: MB_Int_Q2.pdf | 29 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: MB_Int_Q3.pdf | 29 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: MB_inventory_25Mar24.pdf | 29 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form_2.pdf | 25 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form_2_Q2.pdf | 25 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form_2_Q3.pdf | 25 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form_2_Q4.pdf | 25 Apr 2024 |
| Certificates of CA (Form 3)File: Form_3_Q1.pdf | 25 Apr 2024 |
| Certificates of CA (Form 3)File: Form_3_Q2.pdf | 25 Apr 2024 |
| Certificates of CA (Form 3)File: Form_3_Q3.pdf | 25 Apr 2024 |
| Certificates of CA (Form 3)File: Form_3_Q4.pdf | 25 Apr 2024 |
| Declaration in FORM BFile: FormB_Affidavit.pdf | 20 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: letter 25_9_2023.pdf | 11 Jan 2024 |
| Declaration in FORM BFile: FormB_Affidavit.pdf | 4 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: form 2A.pdf | 4 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1_Final.pdf | 7 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 new_Final.pdf | 7 Feb 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FROM-2A MANGAL MAHALXSHMI.pdf | 7 Feb 2023 |
| Certificates of CA (Form 3)File: form 3-signed by promoter.pdf | 7 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form-5_MANGAL BUILDERS.pdf | 7 Feb 2023 |
| Building plan approvalFile: BP 5.PDF | 18 Jul 2022 |
| Building Plan Approval (IOD)File: BP 5.PDF | 18 Jul 2022 |
| Building plan approvalFile: BP 1.PDF | 16 Jul 2022 |
| Building plan approvalFile: BP 2.PDF | 16 Jul 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Ratnagiri
Computed across the 1,100+ Ratnagiri projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 119 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Mangal Mahalaxmi on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Mahalaxmi Che Maal1,100+ in Ratnagiri
Filed coordinates, straight-line distance. 17 registered projects within 2 km.
KONKAN TRAILS LIFESPACE
KONKANTRAILSLIFESPACELLP
Cape of Bliss Phase 1A
HOABL Management LLP
VIAA VISION
VIAA VISION
COASTAL BREEZE
UNIVERSAL PROPERTIES
VRUNDAVAN
EMPIRE REALTORS AND DEVELOPERS
Cape of Bliss Phase I
Lodha Management LLP
See every Ratnagiri project, with the district possession charts
Builder: Mangal Builders
Mangal Builders has 1 registration on MahaRERA, including Mangal Mahalaxmi. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Ratnagiri district page.
Frequently asked questions
What are my rights if Mangal Mahalaxmi is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Mangal Mahalaxmi?
The registered promoter entity is Mangal Builders, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Mangal Mahalaxmi?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Mangal Mahalaxmi?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Mangal Mahalaxmi?
The professionals named in the filing: Architect: Jay Aeram; Engineer: Pravin Landge; Chartered Accountant: A N J K & CO LLP; Chartered Accountant: G N MANTRI AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Mangal Mahalaxmi?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback