Home / Browse projects / Ratnagiri, Maharashtra / Mangal Mahalaxmi

Registered No litigation declared Others project

Mangal Mahalaxmi

By Mangal Builders

RG-MH-60651 · RERA P52800014983 · Last updated on MahaRERA portal: 21 May 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 61 months
  • 6 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Ratnagiri registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 61 months from the original
30 of 55Construction stages doneacross 5 buildings; furthest along: Staircases, 84%
50 of 130Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 119 documents Report an error

Mangal Mahalaxmi is a Others project by Mangal Builders in Ratnagiri, Maharashtra, registered with MahaRERA as P52800014983 on 15 Jan 2018. Possession is promised by 31 Dec 2026. The completion date has moved by 61 months from the original filing. 80 of the 130 units on this registration are recorded sold or booked, and 30 of 55 construction stages are filed complete.

At a glance

Project

  • NameMangal Mahalaxmi
  • TypeOthers
  • Location
    • Opposite Mahalaxmi Temple
    • Mahalaxmi Che Maal
    • Brahmanwadi
    • Dapoli
    • Ratnagiri
    • 415712
  • Pincode415712
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52800014983
  • ReraGenie IDRG-MH-60651

Builder

  • NameMangal Builders
  • Entity typePartnership
  • PartnersBhuendrakumar Bhikamchand Jain, Mangal Shubh Vastu LLP

Key dates

this monthRegisteredJan 2018First promiseNov 2021Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on15 Jan 2018
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 28 Nov 2021)
  • Buildings5 building records
  • Documents filed119 files

Current status

62%80 of 130 units booked
81.5%Work done, per cost certificate

Figures as on 21 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building ANA4416016
Building BNA4442042
Building C and DNA3324933
Building ENA4424024
Building FNA3315015

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building5

As on 21 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

30 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Staircases, at 84%.

Building A73%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure5%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building B63%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure9%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.70%
Building C and D73%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure4%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building E65%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure7%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks84%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.82%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
Building F73%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure4%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 21 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes90%
Water SupplyYes90%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes90%
Storm Water DrainsYes80%
Landscaping & Tree PlantingYes60%
Street LightingYes80%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes80%
Solid Waste Management And DisposalYes70%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes85%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed149

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots149
Closed/Covered14
Open Space135
BuildingClosed/CoveredOpen SpaceTotal
Building A21719
Building B34447
Building C and D52833
Building E43034
Building F01616

Land and ownership4

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,600 sq m
Land owned byThe promoter, with other names on the file
Named landowners4
LandownerVillageDistrict
Dinesh Narayan JadhavBrahmanwadiRatnagiri
Vishwas Parshuram KhanwilkarKhed (M Cl)Ratnagiri
Suyog Sakharam KadamKhed (M Cl)Ratnagiri
Malti Mahadev GholeBrahmanwadiRatnagiri

Approvals and building plan

Sanctioning authorityTown Planning Authority Ratnagiri
Permissible FSI4154.82
Proposed, not sanctioned3,932 sq m
Buildings approved5
Buildings sanctioned5

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBahiratwadi, Pune
Estimated costRs 14.48 cr
Cost incurredRs 11.80 cr
Work done81.46%
BuildingWingEstimatedIncurred
Building BNARs 4.00 crRs 2.60 cr
Building ENARs 3.17 crRs 2.27 cr
Building ANARs 2.66 crRs 2.50 cr
Building C and DNARs 2.62 crRs 2.62 cr
Building FNARs 1.49 crRs 1.49 cr
-NARs 54.33 lakhRs 32.19 lakh

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectJay Aeram
EngineerPravin Landge
Chartered AccountantA N J K & CO LLP
Chartered AccountantG N MANTRI AND ASSOCIATES
PartnerRole in project
Mangal Builders-

Extensions applied for6

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52800011066Nov 2021 → Nov 2022

Reason as filed by the promoterThe project has been delayed on account of first wave of Covid -19, which started from second half of March 2020 and lasted till December 2020 i.e 9 months. During this period cyclone “Nisarga’ also impacted the project. The activities came to total standstill during this period. Further it was very difficult to get the labourers thereafter as most of the labourers from other states migrated and they started coming back only in the month of January and February 2021. During the month of April 2021, as the second wave of Covid-19 causalities increased, the lockdown was imposed in Maharashtra. T

EXT52800012914Nov 2021 → Nov 2023

Reason as filed by the promoterThe project site is located at Dapoli , District Ratnagiri. The area is prone to heavy rainfall. The construction was disturbed due to heavy rains. The commencement of construction activity was further delayed due to shortage of electricity, impacted movement of material and labour. The project comprise of five buildings A, B , CD, E and F. We have completed the construction of buildings CD and F and A , B and E are in progress.

EXT52800018471Nov 2021 → Jun 2024

Reason as filed by the promoterThe Project has been delayed on account of First & second wave of Covid-19 for almost 1 and half year due to which lockdown was imposed in Maharashtra. The lockdown restrictions impacted the movement of material & labour resulting into suspension of construction activities. Further project was suspended during the period May & June 2021 due to cyclone “Tauktae”.

EXT52800024320Nov 2021 → Dec 2024

Reason as filed by the promoterThe Project has been delayed on account of First & second wave of Covid-19 for almost 1 and half year due to which lockdown was imposed in Maharashtra. The lockdown restrictions impacted the movement of material & labour resulting into suspension of construction activities. Further project was suspended during the period May & June 2021 due to cyclone “Tauktae”. Due to unavailability of required material & labour project completion is getting delayed. However as on date 90% project is completed. Project is almost 90% is completed as per Architect certificates.

EXT52800027795Nov 2021 → Dec 2025

Reason as filed by the promoterWe, hereby apply for extension u/s 7(3) of the registered project bearing vide no. P52800014983 up to 30/12/2025.

EA18022619891Nov 2021 → Dec 2026

Reason as filed by the promoterWe have obtained Occupancy Certificate dated 05/06/2025 for the Following Buildings - Building A, Building C and D, Building F. The above-mentioned buildings are complete in all aspects with respect to construction and development works. The Project has been affected by the shortage of skilled labour force due to the recent festive seasons. Shortage of raw material has also resulted into the delay of the construction in view of the latest sanctioned plans received for Building B and Building E upto the Parking + 6 Floors

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 3 Jan 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 16 Jul 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 18 Jul 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 3 Jan 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed119

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 119 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 Architect Certificate March 2026.pdf21 May 2026
Withdrawal Update Form 2File: Form 2 Engineers Certificate March 2026.pdf21 May 2026
Withdrawal Update Form 3File: Form 3 CA Certificate March 2026_11zon.pdf21 May 2026
Withdrawal Update Form 1File: form 1 Architect Certificate - Dec 2025.pdf18 Feb 2026
Withdrawal Update Form 2File: form 2 Engineer Certificate - Dec 2025.pdf18 Feb 2026
Withdrawal Update Form 3File: Form 3 CA Certificate - Dec 2025.pdf18 Feb 2026
Form 1File: Form 1 Architect Certificate -March 2025.pdf20 Nov 2025
Form 2File: Form 2 Engineer Certificate - March 2025.pdf20 Nov 2025
Form 3File: CA Certificate - March 2025 - Sign.pdf20 Nov 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Inventory - June 2025.pdf20 Nov 2025
Withdrawal Update Form 1File: Form 1 Architect Certificate -March 2025.pdf20 Nov 2025
Withdrawal Update Form 1File: Form 1 Architect Certificate - June 2025.pdf20 Nov 2025
Withdrawal Update Form 1File: Form 1 Architect Certificate - September 2025.pdf20 Nov 2025
Withdrawal Update Form 2File: Form 2 Engineer Certificate - March 2025.pdf20 Nov 2025
Withdrawal Update Form 2File: Form 2 Engineer Certificate - June 2025.pdf20 Nov 2025
Withdrawal Update Form 2File: Form 2 Engineer Certificate - September 2025.pdf20 Nov 2025
Withdrawal Update Form 3File: CA Certificate - March 2025 - Sign.pdf20 Nov 2025
Withdrawal Update Form 3File: CA Certificate - June 2025 - Sign.pdf20 Nov 2025
Withdrawal Update Form 3File: Form 3 CA Certificate - September 2025 - Sign.pdf20 Nov 2025
Form 5 (FY 2024-2025)File: Form 5 Annual Audit Report for Mangal Mahalaxmi FY 2024-25.pdf20 Nov 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Annual Audit Report - FY 2023-24 - Sign.pdf21 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate - June 2024.pdf20 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate - September 2024.pdf20 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate - December 2024.pdf20 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate - June 2024.pdf20 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate - September 2024.pdf20 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate - December 2024.pdf20 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Quality Assurance Certificate - March 2021.pdf20 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A Quality Assurance Certificate - March 2022.pdf20 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Quality Assurance Certificate - March 2023.pdf20 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Quality Assurance Certificate - March 2024.pdf7 Mar 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory - June 2024.pdf6 Mar 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory - September 2024.pdf6 Mar 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory - December 2024.pdf6 Mar 2025
Details of encumbrances concerned to FinanceFile: Encumbrance certificate with Finance and Legal.pdf5 Mar 2025
Declaration in FORM BFile: Form B -Declaration by promoter.pdf5 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate - June 2024.pdf5 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate - September 2024.pdf5 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate - December 2024.pdf5 Mar 2025
Certificates of CA (Form 3)File: CA Certificate - June 2024 - Signed.pdf5 Mar 2025
Certificates of CA (Form 3)File: CA Certificate - September 2024 - Signed.pdf5 Mar 2025
Certificates of CA (Form 3)File: CA Certificate - December 2024 - Signed.pdf5 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate - June 2024.pdf5 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate - September 2024.pdf5 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate - December 2024.pdf5 Mar 2025
CERSAI detailsFile: CERSAI Declaration.pdf5 Mar 2025
Details of encumbrances concerned to LegalFile: Encumbrance certificate with Finance and Legal.pdf5 Mar 2025
Other - TechnicalFile: Plinth Certificate.pdf5 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form_5_Mangal_Builders_22-23.pdf6 Aug 2024
Declaration in FORM BFile: form B affidavit.pdf9 Jul 2024
Disclosure of sold/ booked inventoryFile: disclosure of inventory.pdf9 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form_1_Q1.pdf29 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form_1_Q2.pdf29 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form_1_Q3.pdf29 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form_1_Q4.pdf29 Apr 2024
Disclosure of sold/ booked inventoryFile: MB_Int_25Jun23.pdf29 Apr 2024
Disclosure of sold/ booked inventoryFile: MB_Int_Q2.pdf29 Apr 2024
Disclosure of sold/ booked inventoryFile: MB_Int_Q3.pdf29 Apr 2024
Disclosure of sold/ booked inventoryFile: MB_inventory_25Mar24.pdf29 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form_2.pdf25 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form_2_Q2.pdf25 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form_2_Q3.pdf25 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form_2_Q4.pdf25 Apr 2024
Certificates of CA (Form 3)File: Form_3_Q1.pdf25 Apr 2024
Certificates of CA (Form 3)File: Form_3_Q2.pdf25 Apr 2024
Certificates of CA (Form 3)File: Form_3_Q3.pdf25 Apr 2024
Certificates of CA (Form 3)File: Form_3_Q4.pdf25 Apr 2024
Declaration in FORM BFile: FormB_Affidavit.pdf20 Jan 2024
Disclosure of sold/ booked inventoryFile: letter 25_9_2023.pdf11 Jan 2024
Declaration in FORM BFile: FormB_Affidavit.pdf4 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: form 2A.pdf4 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1_Final.pdf7 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 new_Final.pdf7 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FROM-2A MANGAL MAHALXSHMI.pdf7 Feb 2023
Certificates of CA (Form 3)File: form 3-signed by promoter.pdf7 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form-5_MANGAL BUILDERS.pdf7 Feb 2023
Building plan approvalFile: BP 5.PDF18 Jul 2022
Building Plan Approval (IOD)File: BP 5.PDF18 Jul 2022
Building plan approvalFile: BP 1.PDF16 Jul 2022
Building plan approvalFile: BP 2.PDF16 Jul 2022

How this compares with Ratnagiri

62%of this project is bookeddistrict median 23%
15%of Ratnagiri projects moved their completion datethis one moved by 61 months
30%of Ratnagiri registrations have lapsed or been cancelledthis one is on the register

Computed across the 1,100+ Ratnagiri projects on ReraGenie, from their own filings.

Keep Mangal Mahalaxmi on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Mahalaxmi Che Maal1,100+ in Ratnagiri

2 kmMangal MahalaxmiCompleted 8Lapsed / revoked 3Other 6Dot size: filed unitsN

Filed coordinates, straight-line distance. 17 registered projects within 2 km.

Builder: Mangal Builders

Mangal Builders has 1 registration on MahaRERA, including Mangal Mahalaxmi. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Ratnagiri district page.

Frequently asked questions

What are my rights if Mangal Mahalaxmi is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Mangal Mahalaxmi?

The registered promoter entity is Mangal Builders, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Mangal Mahalaxmi?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Mangal Mahalaxmi?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Mangal Mahalaxmi?

The professionals named in the filing: Architect: Jay Aeram; Engineer: Pravin Landge; Chartered Accountant: A N J K & CO LLP; Chartered Accountant: G N MANTRI AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Mangal Mahalaxmi?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Mangal Mahalaxmi. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Mangal Mahalaxmi to a free account