ReraGenieLog inGet a buyer report

Home / Browse projects / Ratnagiri, Maharashtra / ATRIA

Registered No litigation declared Residential / Group Housing project

ATRIA

By Sushant Suresh Chiplunkar

RG-MH-05213 · RERA P52800050180 · Last updated on MahaRERA portal: 17 Jun 2026

Source: official MahaRERA filing

Red flags

  • Rs 1.50 crore secured on the land, in favour of THE CHIPLUN URBAN CO OP BANK LTD CHIPLUN

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Ratnagiri registration emailed to you, free during the pilot beta.
Dec 2028Possession promisedno revision filed
4 of 44Construction stages doneacross 4 buildings; furthest along: Slabs of Super Structure, 98%
118 of 133Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 72 documents Report an error

ATRIA is a Residential / Group Housing project by Sushant Suresh Chiplunkar in Ratnagiri, Maharashtra, registered with MahaRERA as P52800050180 on 21 Mar 2023. Possession is promised by 31 Dec 2028. 15 of the 133 units on this registration are recorded sold or booked, and 4 of 44 construction stages are filed complete.

At a glance

Project

  • NameATRIA
  • TypeResidential / Group Housing
  • Location
    • Ratnagiri Guhagar Bypass
    • Mirjoli
    • Chiplun
    • Ratnagiri
    • 415605
  • Pincode415605
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52800050180
  • ReraGenie IDRG-MH-05213

Builder

  • NameSushant Suresh Chiplunkar
  • Entity typeIndividual
  • Other registrations1 more →
  • No longer live1 lapsed, de-registered or revoked

Key dates

this monthRegisteredMar 2023PromisedDec 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on21 Mar 2023
  • Promised completion31 Dec 2028
  • Revised completionNone
  • Buildings4 building records
  • Documents filed72 files

Current status

11%15 of 133 units booked
23.0%Work done, per cost certificate

Figures as on 17 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING 1 Wing ANA7525025
BUILDING 1 Wing BNA7525025
BUILDING 2NA8660060
BUILDING 3NA8623023

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 17 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Slabs of Super Structure, at 98%.

BUILDING 1 Wing A0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING 1 Wing B0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING 255%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure98%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING 30%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 17 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed223

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots223
Closed/Covered4
Open Space219
BuildingClosed/CoveredOpen SpaceTotal
BUILDING 1 Wing A15859
BUILDING 1 Wing B15960
BUILDING 216061
BUILDING 314243

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area5,520 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofTHE CHIPLUN URBAN CO OP BANK LTD CHIPLUN
Secured amountRs 1.50 crore
CERSAI search filedYes
Declared on28 Oct 2025

Approvals and building plan

Sanctioning authoritySub Divisional Office Chiplun
Permissible FSI6610.85
Proposed, not sanctioned6,611 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShrikripa Building Shivaji Chowk Chiplun
Estimated costRs 16.95 cr
Cost incurredRs 3.90 cr
Work done23.01%
BuildingWingEstimatedIncurred
BUILDING 2NARs 6.15 crRs 3.87 cr
BUILDING 3NARs 3.50 cr-
BUILDING 1 Wing ANARs 2.65 cr-
BUILDING 1 Wing BNARs 2.65 cr-
-NARs 2.00 crRs 3.00 lakh

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSiddik A Momin
EngineerSiddik A Momin
Chartered AccountantFarheen Kazi
Chartered AccountantANIKET S SOHANI
PartnerRole in project
Sushant Suresh Chiplunkar-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 13 Mar 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 13 Mar 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 Mar 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 13 Mar 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2028

Documents filed72

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Architect Certificate 31-12-2025.pdf17 Jun 2026
Withdrawal Update Form 1File: CA Certificate 31-03-2026.pdf17 Jun 2026
Withdrawal Update Form 2File: Engineer Certificate 31-12-2025.pdf17 Jun 2026
Withdrawal Update Form 2File: Engineer Certificate 31-03-2026.pdf17 Jun 2026
Withdrawal Update Form 3File: CA Certificate 31-12-2025.pdf17 Jun 2026
Withdrawal Update Form 3File: CA Certificate 31-03-2026.pdf17 Jun 2026
Withdrawal Update Form 1File: Architect Certificate 30-09-2025.pdf12 May 2026
Withdrawal Update Form 2File: Engineer Certificate 30-09-2025.pdf12 May 2026
Withdrawal Update Form 3File: CA Certificate 30-09-2025.pdf12 May 2026
Form 1File: Architect Certificate 31-03-2025.pdf29 Apr 2026
Form 2File: Engineer Certificate 31-03-2025.pdf29 Apr 2026
Form 3File: CA Certificate 31-03-2025.pdf29 Apr 2026
Disclosure of Sold and Booked InventoryFile: Sold Inventory 31-03-2025.pdf29 Apr 2026
Withdrawal Update Form 1File: Architect Certificate 30-06-2025.pdf29 Apr 2026
Withdrawal Update Form 2File: Engineer Certificate 30-06-2025.pdf29 Apr 2026
Withdrawal Update Form 3File: CA Certificate 30-06-2025.pdf29 Apr 2026
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Sold 2.pdf6 Apr 2025
Disclosure of sold/ booked inventoryFile: Sold 1.pdf6 Apr 2025
Disclosure of sold/ booked inventoryFile: Sold 3.pdf6 Apr 2025
Disclosure of sold/ booked inventoryFile: Sold 2.pdf6 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 F Y 2023-24.pdf6 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate 30-06-2024.pdf25 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate 30-09-2024.pdf25 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate 31-12-2024.pdf25 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate 30-06-2024.pdf25 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate 30-09-2024.pdf25 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate 31-12-2024.pdf25 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate 30-06-2024.pdf25 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate 30-09-2024.pdf25 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate 31-12-2024.pdf25 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate 31-12-2023.pdf12 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate 31-03-2024.pdf12 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's certificate 31-12-2023.pdf12 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's certificate 31-03-2024.pdf12 May 2024
Disclosure of sold/ booked inventoryFile: Sushant Sold 1.pdf12 May 2024
Disclosure of sold/ booked inventoryFile: Sushant Sold 2.pdf12 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate 31-12-2023.pdf12 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate 31-03-2024.pdf12 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5.pdf4 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate 30-06-2023.pdf20 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate 30-09-2023.pdf20 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate 30-06-2023.pdf20 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate 30-09-2023.pdf20 Nov 2023
Disclosure of sold/ booked inventoryFile: SMC Sold 1.pdf20 Nov 2023
Disclosure of sold/ booked inventoryFile: SMC Sold 2.pdf20 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate 30-06-2023.pdf20 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate 30-09-2023.pdf20 Nov 2023
CERSAI detailsFile: CERSAI - Undertaking.pdf16 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf16 Mar 2023
Other - FinanceFile: CA Certificate.pdf16 Mar 2023
CERSAI detailsFile: CERSAI_Search_Report_200262864715_For_Asset_Based_Search_14_03_2023_11_31_05_712.pdf14 Mar 2023
Layout approvalFile: Blueprint 1.pdf13 Mar 2023
Building plan approvalFile: Blueprint 1.pdf13 Mar 2023
Building plan approvalFile: Blueprint 2.pdf13 Mar 2023
Building plan approvalFile: Blueprint 3.pdf13 Mar 2023
PAN CardFile: PAN Sushant.pdf13 Mar 2023
Copy of the legal title reportFile: Search Report.pdf13 Mar 2023
Details of encumbrances concerned to FinanceFile: Encumbrance.pdf13 Mar 2023
Details of encumbrances concerned to LegalFile: Encumbrance.pdf13 Mar 2023
Copy of Layout Approval (in case of layout)File: Blueprint 1.pdf13 Mar 2023
Building Plan Approval / NA Order for plotted developmentFile: Blueprint 1.pdf13 Mar 2023
Building Plan Approval / NA Order for plotted developmentFile: Blueprint 2.pdf13 Mar 2023
Building Plan Approval / NA Order for plotted developmentFile: Blueprint 3.pdf13 Mar 2023
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf13 Mar 2023
Declaration about Commencement CertificateFile: Format D.pdf13 Mar 2023
Declaration in FORM BFile: Form B.pdf13 Mar 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate Organizations.pdf13 Mar 2023
Proforma of Agreement for saleFile: Model Copy Of ASF.pdf13 Mar 2023
Proforma of Allotment letterFile: Allotment Letter.pdf13 Mar 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration about Separate Bank Account for real estate projects.pdf13 Mar 2023
Deviation Report with respect to Allotment letterFile: NO DEVIATION FROM ALLOTMENT LETTER.pdf13 Mar 2023
Deviation Report with respect to model copy of AgreementFile: Deviation from Agreement for Sale.pdf13 Mar 2023

How this compares with Ratnagiri

11%of this project is bookeddistrict median 23%
15%of Ratnagiri projects moved their completion datethis one has not
30%of Ratnagiri registrations have lapsed or been cancelledthis one is on the register

Computed across the 1,100+ Ratnagiri projects on ReraGenie, from their own filings.

Keep ATRIA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Mirjoli1,100+ in Ratnagiri

2 kmATRIACompleted 43Lapsed / revoked 28Other 17Dot size: filed unitsN

Filed coordinates, straight-line distance. 88 registered projects within 2 km.

Builder: Sushant Suresh Chiplunkar

Sushant Suresh Chiplunkar has 2 registrations on MahaRERA, including Shravani Residency and ATRIA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Ratnagiri district page.

Frequently asked questions

What are my rights if ATRIA is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ATRIA?

The registered promoter entity is Sushant Suresh Chiplunkar, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ATRIA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ATRIA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ATRIA?

The professionals named in the filing: Architect: Siddik A Momin; Engineer: Siddik A Momin; Chartered Accountant: Farheen Kazi; Chartered Accountant: ANIKET S SOHANI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ATRIA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ATRIA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ATRIA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.