Home / Developers / DEEPAK YASHWANT SALVI
DEEPAK YASHWANT SALVI: RERA track record
Individual ยท attribution by exact filing name, entity resolution in progress
DEEPAK YASHWANT SALVI has 7 registrations on MahaRERA, including ASHISH PLAZA and LAXMI KEHSAV NAGAR PHASE II. Its filings disclose 5 earlier MahaRERA projects: declares 5 of 5 past projects completed on time.
Projects by this developer
Showing all 7 projects.
Largest first, by the unit count in the filing.
| Project | Location | Units | Booked | Registered | Status |
|---|---|---|---|---|---|
| OCEAN INFINITYP52800023055 | FISHRISE COLLEGE, Ratnagiri, 415629 | 253 | 26% | 22 Nov 2019 | Registered |
| LAXMI KEHSAV NAGAR PHASE IIP52800017021 | GANESH NAGAR, Ratnagiri, 415612 | 143 | 86% | 4 Jul 2018 | Registered |
| SAI PLAZAP52800021129 | BANDAR ROAD, Ratnagiri, 415612 | 1 | 0% | 10 Jun 2019 | Completed |
| SAI RATNAP52800021176 | MARUTI MANDIR, Ratnagiri, 415612 | 1 | 0% | 14 Jun 2019 | Completed |
| ASHISH PLAZAP52800016995 | RAILWAY STATION, Ratnagiri, 415612 | - | - | 28 Jun 2018 | Completed |
| BLUE MONTP52800051050 | Jaystambha, Ratnagiri, 415612 | - | - | 22 May 2023 | Registered |
| SHANTADURGA SANKULP52800016988 | SALVI STOP, Ratnagiri, 415612 | - | - | 26 Jun 2018 | Completed |
What this promoter declares as its own experience
DEEPAK YASHWANT SALVI declares experience on 5 earlier projects. One carries a registration number we could match on MahaRERA, under this promoter's own name.
One of these declarations can be compared with the dates that project's own registration holds. It gives the same original completion date that registration holds.
From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| DYS PLAZA | 30 Oct 2010 | 31 May 2010 | On time |
| SUHASPLAZA | 15 May 2017 | 10 May 2017 | On time |
| SUHAS PLAZA | 15 May 2017 | 10 May 2017 | On time |
| Suhas Plaza | 30 Jun 2017 | 31 May 2017 | On time |
| SAI RATNA P52800021176 | 30 May 2023 | 7 Sep 2021 | On time |
Frequently asked questions
How do I verify DEEPAK YASHWANT SALVI as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with DEEPAK YASHWANT SALVI?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.
Spotted a project attributed to the wrong developer, or something else wrong on this page? Projects are grouped by the promoter name as filed, so a firm that registers under two spellings can split across two pages. Tell us and we will check it against the filings.
Report an errorShare feedbackData from official MahaRERA filings. How we handle corrections is on the about page.