Chaitanya Developers: RERA track record

Partnership ยท attribution by exact filing name, entity resolution in progress

Chaitanya Developers has 15 registrations in this build, including Sea Vista and Chaitanya Srusti. Its filings disclose 24 earlier MahaRERA projects: 21 of 24 past projects completed on time.

15Registrations in this build
24Past projects disclosed
on timeMedian delivery slip
0Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
Sea VistaRatnagiri, Maharashtra19877%Registered
Chaitanya SrustiPune, Maharashtra--Completed
Mahalaximi ResidencyPune, Maharashtra--Registration lapsed
CHAITANYA PRIDEPune, Maharashtra--Completed
Nirmaan HeightsMumbai Suburban, Maharashtra--Completed
OM RAJLAXMI CO-OP HSG SOCThane, Maharashtra--Registration lapsed
KAWADE PATIL RESIDENCYPune, Maharashtra--Registration lapsed
CHAITANYA HIGH POINTPune, Maharashtra--Registration lapsed
CHAITANYA KOHINOORMumbai Suburban, Maharashtra--Completed
Chaitanya Anand - Lunkhod CHSLMumbai Suburban, Maharashtra--Completed
KRISHNA VANSHThane, Maharashtra17550%Registered
PACIFIC TOWERPune, Maharashtra19373%Registered
Chaitanya NishigandhMaharashtra--Completed
Chaitanya ShreyasMumbai Suburban, Maharashtra--Completed
Ethics OliverMumbai City, Maharashtra512%Registered

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
SBI Employees Sanman CHSL
18 Oct 201118 Oct 2011On time
SBI Employees Sanman CHSL - OC Received
18 Oct 201118 Oct 2011On time
CHAITANYA PLATINUM
31 Mar 201231 Mar 2012On time
SBI Staff New Aradhana CHSL
10 Apr 201210 Oct 2012+6 months
Horizon Heights
31 Aug 201516 Sep 2015+1 months
Om Shree Shakti CHSL
4 Sep 20154 Sep 2015On time
Om Shree Shakti CHSL - OC Received
4 Sep 20154 Sep 2015On time
SBI Employees Nilambari CHSL
16 Jun 201616 Jun 2016On time
SBI Employees Nilambari CHSL - OC Received
16 Jun 201616 Jun 2016On time
Jeevan Kanchan CHSL - OC Received
3 Feb 20183 Feb 2018On time
Chaitanya Residency - OC Received
5 Jul 20185 Jul 2018On time
Chaitanya Residency
P51800000886
31 Oct 201831 Oct 2018On time

Frequently asked questions

How do I verify Chaitanya Developers as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with Chaitanya Developers?

Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.