Home / Browse projects / Ratnagiri, Maharashtra / ROYAL CITY PARK

Registration lapsed No litigation declared Residential / Group Housing project

ROYAL CITY PARK

By MAHESH AMRUTLAL BORIYA

RG-MH-66132 · RERA P52800003484 · Last updated on MahaRERA portal: 13 Mar 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 46 months past the filed date
  • Completion date moved by 18 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Ratnagiri registration emailed to you, free during the pilot beta.
Dec 2022Possession promised46 months past this date
10 of 22Construction stages doneacross 2 buildings; furthest along: Staircases, 20%
106 of 152Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 24 documents Report an error

ROYAL CITY PARK is a Residential / Group Housing project by MAHESH AMRUTLAL BORIYA in Ratnagiri, Maharashtra, registered with MahaRERA as P52800003484 on 5 Aug 2017. Possession was promised by 15 Dec 2022 and is now 46 months past that date. The completion date has moved by 18 months from the original filing. 46 of the 152 units on this registration are recorded sold or booked, and 10 of 22 construction stages are filed complete.

At a glance

Project

  • NameROYAL CITY PARK
  • TypeResidential / Group Housing
  • Location
    • RATNAGIRI
    • Karvanchiwadi
    • 415639
  • Pincode415639
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52800003484
  • ReraGenie IDRG-MH-66132

Builder

  • NameMAHESH AMRUTLAL BORIYA
  • Entity typeIndividual
  • Other registrations2 more →
  • Completed1 of 3
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

46 months past promisethis monthRegisteredAug 2017First promiseJun 2021Revised toDec 2022

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on5 Aug 2017
  • Promised completion15 Dec 2022
  • Revised completionRevised to 15 Dec 2022 (originally 15 Jun 2021)
  • Buildings2 building records
  • Documents filed24 files

Current status

30%46 of 152 units booked

Figures as on 13 Mar 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ROYAL CITY PARKNA121084084
WING H I AND J KNA121068068

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 13 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Staircases, at 20%.

ROYAL CITY PARK48%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises10%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks20%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING H I AND J K48%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises10%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks20%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 13 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes50%
Water SupplyYes70%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes60%
Open ParkingYes0%

Parking filed364

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots364
Closed/Covered340
Open Space24
BuildingClosed/CoveredOpen SpaceTotal
ROYAL CITY PARK17012182
WING H I AND J K17012182

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,859 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on12 Jul 2025

Approvals and building plan

Sanctioning authorityUPVIBHAGH ADHIKARI
Permissible FSI9952.16
Proposed, not sanctioned9,952 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMALAD EAST

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMILIND RAJARAM YADAV
EngineerMANOJ SHASHIKANT JOSHI
Chartered AccountantRAHUL D SINGH
PartnerRole in project
MAHESH AMRUTLAL BORIYA-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52800010014Jun 2021 → Jun 2022

Reason as filed by the promoterPROJECT COMPLETED BUT SOME FLATS ARE NOT SOLD

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed24

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Disclosure of Interest in Other Real Estate OrganizationsFile: Scan_0018 (1)-4.pdf13 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: C A CERTIFICATE 2019 20.pdf13 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: C A CERTIFICATE 2017 18.pdf13 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: C A CERTIFICATE 2018 19.pdf6 Aug 2021
Declaration about Commencement CertificateFile: Form D.pdf28 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: From 2 A.pdf28 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: From 2 A.pdf9 Jul 2021
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD FLATS.pdf9 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: C A Certificate.pdf9 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: C A Certificate.pdf9 Jul 2021
Layout approvalFile: BUILDING PLAN.pdf29 Jul 2017
Building plan approvalFile: BUILDING PLAN.pdf29 Jul 2017
PAN CardFile: PAN CARD.pdf29 Jul 2017
Copy of the legal title reportFile: Search Report.pdf29 Jul 2017
Details of encumbrancesFile: Search Report.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: BUILDING PLAN.pdf29 Jul 2017
Building Plan Approval (IOD)File: BUILDING PLAN.pdf29 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: commencement certificate.pdf29 Jul 2017
Declaration in FORM BFile: B FORM.pdf29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf29 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf29 Jul 2017
Certificates of CA (Form 3)File: CA Certificate.pdf29 Jul 2017
Proforma of Allotment letterFile: Agreement for sale 1.pdf29 Jul 2017
Proforma of Allotment letterFile: Agreement for sale 2.pdf29 Jul 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
ROYAL APPARTMENTKHEDASHI RATNAGIRI20CompletedMar 2017Mar 2017

How this compares with Ratnagiri

30%of this project is bookeddistrict median 23%
15%of Ratnagiri projects moved their completion datethis one moved by 18 months
30%of Ratnagiri registrations have lapsed or been cancelledthis one is among them

Computed across the 1,100+ Ratnagiri projects on ReraGenie, from their own filings.

Keep ROYAL CITY PARK on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Karvanchiwadi1,100+ in Ratnagiri

2 kmROYAL CITY PARKCompleted 10Lapsed / revoked 4Other 5Dot size: filed unitsN

Filed coordinates, straight-line distance. 19 registered projects within 2 km.

Builder: MAHESH AMRUTLAL BORIYA

MAHESH AMRUTLAL BORIYA has 3 registrations on MahaRERA, including ROYAL CITY PARK and ROYAL CITY PARK PHASE II. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Ratnagiri district page.

Frequently asked questions

What does it mean that ROYAL CITY PARK shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if ROYAL CITY PARK is delayed beyond 15 Dec 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ROYAL CITY PARK?

The registered promoter entity is MAHESH AMRUTLAL BORIYA, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ROYAL CITY PARK?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ROYAL CITY PARK?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ROYAL CITY PARK?

The professionals named in the filing: Architect: MILIND RAJARAM YADAV; Engineer: MANOJ SHASHIKANT JOSHI; Chartered Accountant: RAHUL D SINGH. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ROYAL CITY PARK?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ROYAL CITY PARK. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ROYAL CITY PARK to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.