Home / Browse projects / Ratnagiri, Maharashtra / Cape of Bliss Phase I
Cape of Bliss Phase I
RG-MH-63818 · RERA P52800049714 · Last updated on MahaRERA portal: 29 Sep 2025
Source: official MahaRERA filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 2 other registrations.
See what the report covers Free either way: or have every new Ratnagiri registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Cape of Bliss Phase I is a Plotted project by Lodha Management LLP in Ratnagiri, Maharashtra, registered with MahaRERA as P52800049714 on 22 Feb 2023. The registration is recorded completed; possession was promised by 30 Dec 2025. 110 of the 152 units on this registration are recorded sold or booked.
At a glance
Project
- NameCape of Bliss Phase I
- TypePlotted
- Location
- Dapoli
- Kolthare
- Ratnagiri
- 415712
- Pincode415712
- RERA no.P52800049714
- ReraGenie IDRG-MH-63818
Builder
- NameLodha Management LLP
- Entity typePartnership
- CINU70200MH2025PTC458960
- LLPINAAA-6497
- CIN and LLPIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
- PartnersSamujjwal Ghosh, Rakesh Gupta
- Other registrations2 more →
- Completed3 of 3
- Declared earlier projects5 →
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on22 Feb 2023
- Promised completion30 Dec 2025
- Revised completionNone
- BuildingsNot stated in filing
- Documents filed71 files
Current status
Figures as on 29 Sep 2025, this project's latest MahaRERA filing.
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 29 Sep 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
NA Plot Without Structure:
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Progress on shared amenities16
As on 29 Sep 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 80% |
| Water Supply | Yes | 85% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | No | Not applicable |
| Storm Water Drains | Yes | 80% |
| Landscaping & Tree Planting | Yes | 75% |
| Street Lighting | Yes | 80% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 85% |
| Aggregate area of recreational Open Space | Yes | 90% |
| Open Parking | No | Not applicable |
| Compound Wall Demarcation | Yes | 85% |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Tansika Misal |
| Architect | Bhalachandra Gothankar |
| Engineer | Dinesh Balkrishna Satam |
| Chartered Accountant | Chirag Sarvaiya |
| Chartered Accountant | U S MISHRA AND ASSOCIATES |
| Partner | Role in project |
|---|---|
| HOABL Management Private Limited | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 11 Sep 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 8 Sep 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 13 Feb 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 8 Sep 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 9 Mar 2025
Documents filed71
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 5 (FY 2024-2025)File: Form 5_COB 1_signed.pdf | 29 Sep 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: COB 1 - Architect Certificate.pdf | 19 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Cape of Bliss Phase I-P52800049714-CA certificate.pdf | 19 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: COB 1 - Engineer Certificate.pdf | 19 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory.pdf | 19 Apr 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion Certificate_COB 1_17-01-2025.pdf | 9 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AC_COB 1.pdf | 20 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA_LM LLP PH1.pdf | 20 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: EC_COB1.pdf | 20 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory-Cape of Bliss I-.pdf | 20 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AC_Cape of bliss I.pdf | 19 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA_LM LLP-Cape of Bilss I.pdf | 19 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: EC_COB I.pdf | 19 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory-Cape of Bliss I_signed.pdf | 19 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: 8 COB Phase 1_Form 5_promoter signed.pdf | 7 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Cape of Bliss Phase I - Architect certificate-signed.pdf | 20 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Cape of Bliss Phase I - Engineer certificate_signed.pdf | 20 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory- Cape of Bliss Phase I.pdf | 20 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Cape of Bliss Phase I - CA certificate.pdf | 20 Jul 2024 |
| Home Buyer /Allottee Grievance Redressal CellFile: Lodha Management LLP.pdf | 5 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A_COB 1_signed.pdf | 27 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR.pdf | 20 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Er.pdf | 20 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory - Cape of Bliss Phase I.pdf | 20 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA.pdf | 20 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AC_COB 1.pdf | 20 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: EC_COB 1.pdf | 20 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory-Cape of Bliss Phase I.pdf | 20 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: LMLLP_P1.pdf | 20 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AC_COB-1_signed.pdf | 17 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: CoB 1.pdf | 17 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: COB Phase 1.pdf | 17 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA_COB1.pdf | 17 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form5_COB_ 1.pdf | 1 Oct 2023 |
| Copy of the legal title reportFile: TITLE REPORT_compressed.pdf | 11 Sep 2023 |
| Disclosure of sold/ booked inventoryFile: Sold unsold_Cape of Bliss Phase I.pdf | 11 Sep 2023 |
| Layout approvalFile: Phase 1CoB_compressed.pdf | 8 Sep 2023 |
| Copy of Layout Approval (in case of layout)File: Phase 1CoB_compressed.pdf | 8 Sep 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: Phase -1 N AOrder.pdf | 8 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate COB P1.pdf | 6 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: EC_COB Phase 1.pdf | 6 Sep 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: LM LLP P1 Form 3_SIG_compressed.pdf | 6 Sep 2023 |
| Proforma of Agreement for saleFile: Final Draft AFS - COB Phase 1 - RERA.pdf | 27 Jun 2023 |
| Deviation Report with respect to model copy of AgreementFile: Final Deviation Report - COB Phase 1 - RERA.pdf | 27 Jun 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: T-1 Tahsildar Letter.pdf | 14 Feb 2023 |
| Proforma of Allotment letterFile: Allotment Letter-Phase I_legal_signed.pdf | 14 Feb 2023 |
| Deviation Report with respect to Allotment letterFile: Deviation of Allotment Letter-Phase I_legal_signed.pdf | 14 Feb 2023 |
| Other - TechnicalFile: 1.pdf | 14 Feb 2023 |
| Other - TechnicalFile: 2.pdf | 14 Feb 2023 |
| Other - TechnicalFile: 3.pdf | 14 Feb 2023 |
| Other - TechnicalFile: 4.pdf | 14 Feb 2023 |
| Layout approvalFile: 1 Copy of Layout Approval (in case of layout)_rotated.pdf | 13 Feb 2023 |
| Building plan approval or NA orderFile: 1 Copy of Layout Approval (in case of layout)_rotated.pdf | 13 Feb 2023 |
| Copy of the legal title reportFile: Title Report.pdf | 13 Feb 2023 |
| Copy of the legal title reportFile: Rera Title report kolthare 39(1 3 4)_compressed.pdf | 13 Feb 2023 |
| Copy of Layout Approval (in case of layout)File: 1 Copy of Layout Approval (in case of layout)_rotated.pdf | 13 Feb 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 1 Copy of Layout Approval (in case of layout)_rotated.pdf | 13 Feb 2023 |
| Declaration about Commencement CertificateFile: Form D.pdf | 13 Feb 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: LM LLP P1 Form 3.pdf | 13 Feb 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: GetUserDocumentFileContent.pdf | 13 Feb 2023 |
| PAN CardFile: PAN Card.pdf | 8 Feb 2023 |
| Details of encumbrances concerned to FinanceFile: Details of encumbrances concerned to Finance-Phase I_signed.pdf | 8 Feb 2023 |
| Details of encumbrances concerned to FinanceFile: Details of encumbrances concerned to Legal-Phase I_signed.pdf | 8 Feb 2023 |
| Details of encumbrances concerned to LegalFile: Details of encumbrances concerned to Finance-Phase I_signed.pdf | 8 Feb 2023 |
| Details of encumbrances concerned to LegalFile: Details of encumbrances concerned to Legal-Phase I_signed.pdf | 8 Feb 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: P1 TP Order 39-1.pdf | 8 Feb 2023 |
| Declaration in FORM BFile: Form B.pdf | 8 Feb 2023 |
| CERSAI detailsFile: CERSAI_Search_Report_200259884486_For_Asset_Based_Search_08_02_2023_17_45_01_656.pdf | 8 Feb 2023 |
| Proforma of Agreement for saleFile: Cape of Bliss Phase I - AFS - RERA Format.pdf | 8 Feb 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration for Separate Bank Account-Phase I_signed.pdf | 8 Feb 2023 |
| Deviation Report with respect to model copy of AgreementFile: Deviation Report with Agreement_signed.pdf | 8 Feb 2023 |
Promoter's earlier projects4
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| Waves of BlissP52800053247 | Kolthare, Ratnagiri | 22 | Oct 2023 | Ongoing | Dec 2025 | Not delivered |
| Cape of Bliss Phase 1AP52800052438 | Ratnagiri, Ratnagiri | 385 | Aug 2023 | Ongoing | Dec 2025 | Not delivered |
| Isle of Bliss Phase IIIP52800049974 | Ratnagiri, Ratnagiri | 64 | Mar 2023 | Completed | Dec 2024 | Dec 2024 |
| Isle of Bliss Phase IIP52800050299 | Ratnagiri, Ratnagiri | 49 | Apr 2023 | Completed | Dec 2024 | Dec 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Ratnagiri
Computed across the 1,100+ Ratnagiri projects on ReraGenie, from their own filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 2 other registrations, which the RERA portal never shows together
- All 71 filed documents as one ZIP, foldered, with a manifest
Keep Cape of Bliss Phase I on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Kolthare1,100+ in Ratnagiri
KONKAN TRAILS LIFESPACE
KONKANTRAILSLIFESPACELLP
Cape of Bliss Phase 1A
HOABL Management LLP
VIAA VISION
VIAA VISION
COASTAL BREEZE
UNIVERSAL PROPERTIES
VRUNDAVAN
EMPIRE REALTORS AND DEVELOPERS
Cape of Bliss 1B
HOABL Management Private Limited
See every Ratnagiri project, with the district possession charts
Builder: Lodha Management LLP
Lodha Management LLP has 3 registrations on MahaRERA, including Cape of Bliss Phase I and Isle of Bliss Phase III. Its filings disclose 5 earlier MahaRERA projects: declares 3 of 3 past projects completed on time. Read the full track record. See more projects on the Ratnagiri district page.
Frequently asked questions
What are my rights if Cape of Bliss Phase I is delayed beyond 30 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Cape of Bliss Phase I?
The registered promoter entity is Lodha Management LLP, a partnership as per the filing. Its CIN U70200MH2025PTC458960 and LLPIN AAA-6497 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Cape of Bliss Phase I?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Cape of Bliss Phase I?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Cape of Bliss Phase I?
The professionals named in the filing: Architect: Tansika Misal; Architect: Bhalachandra Gothankar; Engineer: Dinesh Balkrishna Satam; Chartered Accountant: Chirag Sarvaiya; Chartered Accountant: U S MISHRA AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Cape of Bliss Phase I?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback