ReraGenieLog inGet a buyer report

Home / Browse projects / Ratnagiri, Maharashtra / Sea Vista

Registered No litigation declared Residential / Group Housing project

Sea Vista

By Chaitanya Developers

RG-MH-10953 · RERA P52800004514 · Last updated on MahaRERA portal: 30 Apr 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Ratnagiri registration emailed to you, free during the pilot beta.
Dec 2038Possession promisedno revision filed
378 of 803Construction stages doneacross 73 buildings; furthest along: Internal walls, 30%
45 of 198Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 145 documents Report an error

Sea Vista is a Residential / Group Housing project by Chaitanya Developers in Ratnagiri, Maharashtra, registered with MahaRERA as P52800004514 on 9 Aug 2017. Possession is promised by 30 Dec 2038. 153 of the 198 units on this registration are recorded sold or booked, and 378 of 803 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameSea Vista
  • TypeResidential / Group Housing
  • Location
    • Malgund
    • Ratnagiri
    • 415615
  • Pincode415615
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52800004514
  • ReraGenie IDRG-MH-10953

Builder

  • NameChaitanya Developers
  • Entity typePartnership
  • PartnersChandrashekhar Prabhakar Bhide, Gauri Chandrashekhar Bhide, Vaibhavi Chandrashekhar Bhide, Aditi Dhananjay Barve, Girija Chandrashekhar Bhide
  • Other registrations14 more →
  • Completed7 of 15
  • No longer live4 lapsed, de-registered or revoked
  • Declared earlier projects24 →

Key dates

this monthRegisteredAug 2017PromisedDec 2038

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on9 Aug 2017
  • Promised completion30 Dec 2038
  • Revised completionNone
  • Buildings73 building records
  • Documents filed145 files

Current status

77%153 of 198 units booked
60.6%Work done, per cost certificate

Figures as on 30 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING NO 1NA11101
BUILDING NO 2NA10101
BUILDING NO 3NA10101
BUILDING NO 4NA10101
BUILDING NO 5NA10101
BUILDING NO 6NA10101
BUILDING NO 7NA10101
BUILDING NO 8NA10101
BUILDING NO 9NA10101
BUILDING NO 10NA10101
BUILDING NO 11NA10101
BUILDING NO 12NA20202
BUILDING NO 16NA20101
BUILDING NO 17NA20101
BUILDING NO 18NA20202
BUILDING NO 19NA20202
BUILDING NO 20NA20101
BUILDING NO 24NA20202
BUILDING NO 25NA20202
BUILDING NO 26NA20101
BUILDING NO 27NA20101
BUILDING NO 28NA20101
BUILDING NO 29NA20202
BUILDING NO 30NA20202
BUILDING NO 31NA20202
BUILDING NO 32NA20202
BUILDING NO 33NA20202
BUILDING NO 34NA20101
BUILDING NO 35NA20202
BUILDING NO 36NA20202
BUILDING NO 37NA20101
BUILDING NO 38NA20101
BUILDING NO 39NA20202
BUILDING NO 40NA20101
BUILDING NO 41NA20101
BUILDING NO 42NA20101
BUILDING NO 43NA20202
BUILDING NO 44NA20101
BUILDING NO 45NA20101
BUILDING NO 46NA20101
BUILDING NO 49NA20101
BUILDING NO 50NA20202
BUILDING NO 51NA20202
BUILDING NO 52NA20101
BUILDING NO 56NA20011
BUILDING NO 57NA00011
BUILDING NO 58NA00011
BUILDING NO 59NA5040040
BUILDING NO 60NA5033033
BUILDING NO 61 F WINGNA4021021
BUILDING NO 62NA20202
BUILDING NO 63NA20202
BUILDING NO 64NA20202
BUILDING NO 65NA20202
BUILDING NO 66NA20202
BUILDING NO 67NA20202
BUILDING NO 68NA20202
BUILDING NO 69NA20202
BUILDING NO 70NA20202
BUILDING NO 71NA20202
BUILDING NO 72NA20101
BUILDING NO 73NA20101
BUILDING NO 13NA20202
BUILDING NO 14NA20202
BUILDING NO 15NA20202
BUILDING NO 47NA20101
BUILDING NO 48NA20101
BUILDING NO 54NA60022
BUILDING NO 55NA60033
BUILDING NO 53NA20101
BUILDING NO 21NA20101
BUILDING NO 22NA20202
BUILDING NO 23NA20202

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building20

As on 30 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 73 buildings; the table lists the first 20.

378 of 803 construction stages are filed complete across 73 buildings. The stage furthest along is Internal walls, at 30%.

BUILDING NO 182%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUILDING NO 273%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUILDING NO 373%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUILDING NO 464%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUILDING NO 573%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUILDING NO 673%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUILDING NO 764%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUILDING NO 830%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises30%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO 973%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUILDING NO 1073%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUILDING NO 110%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO 1273%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUILDING NO 1673%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUILDING NO 1773%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUILDING NO 1873%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUILDING NO 1973%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUILDING NO 2073%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUILDING NO 240%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO 2564%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUILDING NO 260%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 30 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes60%
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes45%
Landscaping & Tree PlantingYes0%
Street LightingYes80%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes80%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed98

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots98
Closed/Covered2
Open Space96
BuildingClosed/CoveredOpen SpaceTotal
BUILDING NO 1011
BUILDING NO 2011
BUILDING NO 3011
BUILDING NO 4011
BUILDING NO 5011
BUILDING NO 6011
BUILDING NO 7011
BUILDING NO 8011
BUILDING NO 9011
BUILDING NO 10011
BUILDING NO 11011
BUILDING NO 12011
BUILDING NO 16011
BUILDING NO 17011
BUILDING NO 18011
BUILDING NO 19011
BUILDING NO 20011
BUILDING NO 24011
BUILDING NO 25011
BUILDING NO 26011
BUILDING NO 27011
BUILDING NO 28011
BUILDING NO 29011
BUILDING NO 30011
BUILDING NO 31011
BUILDING NO 32011
BUILDING NO 33011
BUILDING NO 34011
BUILDING NO 35011
BUILDING NO 36011
BUILDING NO 37011
BUILDING NO 38011
BUILDING NO 39011
BUILDING NO 40011
BUILDING NO 41011
BUILDING NO 42011
BUILDING NO 43011
BUILDING NO 44011
BUILDING NO 45011
BUILDING NO 46011
BUILDING NO 49011
BUILDING NO 50011
BUILDING NO 51011
BUILDING NO 52011
BUILDING NO 56055
BUILDING NO 61 F WING066
BUILDING NO 64011
BUILDING NO 65011
BUILDING NO 67011
BUILDING NO 68011
BUILDING NO 69011
BUILDING NO 70011
BUILDING NO 71011
BUILDING NO 72011
BUILDING NO 73011
BUILDING NO 13011
BUILDING NO 14011
BUILDING NO 15011
BUILDING NO 47011
BUILDING NO 48011
BUILDING NO 54189
BUILDING NO 5511516
BUILDING NO 53011
BUILDING NO 21011
BUILDING NO 22011
BUILDING NO 23011

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area24,726 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authoritySDO Ratnagiri sub Division
Permissible FSI22385.0
Proposed, not sanctioned11,385 sq m
Buildings approved73
Buildings sanctioned73

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMayur Colony, Near Jog High School, kothrud, Pune -411038
Estimated costRs 25.43 cr
Cost incurredRs 15.42 cr
Work done60.63%
BuildingWingEstimatedIncurred
-NARs 2.70 crRs 90.77 lakh
BUILDING NO 54NARs 2.66 cr-
BUILDING NO 59NARs 2.45 crRs 2.33 cr
BUILDING NO 60NARs 1.60 crRs 2.00 cr
BUILDING NO 55NARs 1.31 cr-
BUILDING NO 61 F WINGNARs 1.12 crRs 1.54 cr
BUILDING NO 24NARs 25.77 lakhRs 1.98 lakh
BUILDING NO 25NARs 25.77 lakhRs 27.81 lakh
BUILDING NO 26NARs 25.77 lakh-
BUILDING NO 40NARs 25.77 lakhRs 106
BUILDING NO 62NARs 25.77 lakh-
BUILDING NO 63NARs 25.77 lakh-

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSATISH N JOSHI
ArchitectSanika Patankar
EngineerSanjay Patankar
EngineerHemant Mahadev Khapane
Chartered AccountantJayant Joshi & Company
PartnerRole in project
Chaitanya Developers-

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12500099MS LILLY OOMMEN VACATION AND LEISURE PVT LTDChaitanya Developers11/01/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 1 Feb 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 Jan 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 1 Feb 2025

Documents filed145

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 145 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1.pdf30 Apr 2026
Withdrawal Update Form 2File: Form 2.pdf30 Apr 2026
Withdrawal Update Form 3File: Form 3.pdf30 Apr 2026
Withdrawal Update Form 1File: Form 1.pdf21 Feb 2026
Withdrawal Update Form 1File: From 1.pdf21 Feb 2026
Withdrawal Update Form 2File: Form 2.pdf21 Feb 2026
Withdrawal Update Form 2File: From 2.pdf21 Feb 2026
Withdrawal Update Form 3File: Form 3.pdf21 Feb 2026
Withdrawal Update Form 3File: Form 3.pdf21 Feb 2026
Form 2A (FY 2024-2025)File: Form 2A.pdf12 Feb 2026
Form 1File: Form 1.pdf5 Dec 2025
Form 2File: Form 2.pdf5 Dec 2025
Form 3File: Form 3.pdf5 Dec 2025
Disclosure of Sold and Booked InventoryFile: Sold Booked.pdf5 Dec 2025
Form 5 (FY 2024-2025)File: Form 5 - 24-25.pdf4 Dec 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf30 Apr 2025
Certificates of CA (Form 3)File: FORM 3.pdf30 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf30 Apr 2025
Layout approvalFile: 1-5 - converted.pdf1 Feb 2025
Layout approvalFile: 2-5 - converted.pdf1 Feb 2025
Layout approvalFile: 3-5 - converted.pdf1 Feb 2025
Layout approvalFile: 4-5 - converted.pdf1 Feb 2025
Layout approvalFile: 5-5 - converted.pdf1 Feb 2025
Copy of Layout Approval (in case of layout)File: 1-5 - converted.pdf1 Feb 2025
Copy of Layout Approval (in case of layout)File: 2-5 - converted.pdf1 Feb 2025
Copy of Layout Approval (in case of layout)File: 3-5 - converted.pdf1 Feb 2025
Copy of Layout Approval (in case of layout)File: 4-5 - converted.pdf1 Feb 2025
Copy of Layout Approval (in case of layout)File: 5-5 - converted.pdf1 Feb 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: ORDER.pdf1 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - converted.pdf30 Jan 2025
Certificates of CA (Form 3)File: Form 3.pdf30 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf30 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5.pdf15 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf29 Oct 2024
Certificates of CA (Form 3)File: Form 3.pdf29 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf29 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf22 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf22 Apr 2024
Certificates of CA (Form 3)File: form 3.pdf22 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 31-3-23.pdf28 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 dec 23.pdf28 Mar 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 march 23.pdf28 Mar 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 dec 23.pdf28 Mar 2024
Certificates of CA (Form 3)File: form 3 31-12-23.pdf28 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 2020.pdf23 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 2021.pdf23 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2022.pdf23 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2023.pdf23 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 upto 31032023.pdf21 Mar 2024
Disclosure of sold/ booked inventoryFile: 1.pdf29 Jan 2022
Disclosure of sold/ booked inventoryFile: 2.pdf29 Jan 2022
Layout approvalFile: 20190126 Layout NA 180508 Drw 1 of 5.pdf26 Jan 2019
Layout approvalFile: 20190126 Layout NA 180508 Drw 2 of 5.pdf26 Jan 2019
Layout approvalFile: 20190126 Layout NA 180508 Drw 3 of 5.pdf26 Jan 2019
Layout approvalFile: 20190126 Layout NA 180508 Drw 4 of 5.pdf26 Jan 2019
Layout approvalFile: 20190126 Layout NA 180508 Drw 5 of 5.pdf26 Jan 2019
Copy of Layout Approval (in case of layout)File: 20190126 Layout NA 180508 Drw 1 of 5.pdf26 Jan 2019
Copy of Layout Approval (in case of layout)File: 20190126 Layout NA 180508 Drw 2 of 5.pdf26 Jan 2019
Copy of Layout Approval (in case of layout)File: 20190126 Layout NA 180508 Drw 3 of 5.pdf26 Jan 2019
Copy of Layout Approval (in case of layout)File: 20190126 Layout NA 180508 Drw 4 of 5.pdf26 Jan 2019
Copy of Layout Approval (in case of layout)File: 20190126 Layout NA 180508 Drw 5 of 5.pdf26 Jan 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20190126 ARCHITECTS_CERTIFICATE 180906-.pdf26 Jan 2019
Proforma of Allotment letterFile: AGREEMENT FOR SALE.pdf26 Jan 2019
Proforma of Allotment letterFile: CONVEYANCE DEED.pdf26 Jan 2019
OtherFile: 20190126 upload 7 12 1 to 3.pdf26 Jan 2019
Commencement Certificates / NA Order for plotted developmentFile: New_NA_Order_180508.PDF25 Jan 2019
Declaration in FORM BFile: Form B R2.PDF8 Aug 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE 2-4.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE 3-4.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE 4-4.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineers Certificate 1-3.PDF31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineers Certificate 2-3.PDF31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineers Certificate 3-3.PDF31 Jul 2017
Certificates of CA (Form 3)File: Form 3 CA Certificate 1-2.PDF31 Jul 2017
Certificates of CA (Form 3)File: Form 3 CA Certificate Anex A 2-2.PDF31 Jul 2017
Certificates of CA (Form 5)File: Form 5 CA Certificate .PDF31 Jul 2017
Copy of the legal title reportFile: POA of Owner 1_4.PDF30 Jul 2017
Copy of the legal title reportFile: POA of Owner 5_8.PDF30 Jul 2017
Copy of the legal title reportFile: POA of Owner 9_10.PDF30 Jul 2017
Copy of the legal title reportFile: Dvp agree 29 to 30.PDF30 Jul 2017

How this compares with Ratnagiri

77%of this project is bookeddistrict median 23%
15%of Ratnagiri projects moved their completion datethis one has not
30%of Ratnagiri registrations have lapsed or been cancelledthis one is on the register

Computed across the 1,100+ Ratnagiri projects on ReraGenie, from their own filings.

Keep Sea Vista on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Malgund1,100+ in Ratnagiri

Builder: Chaitanya Developers

Chaitanya Developers has 15 registrations on MahaRERA, including Sea Vista and Chaitanya Srusti. Its filings disclose 24 earlier MahaRERA projects: declares 21 of 24 past projects completed on time. Read the full track record. See more projects on the Ratnagiri district page.

Frequently asked questions

What are my rights if Sea Vista is delayed beyond 30 Dec 2038?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Sea Vista?

The registered promoter entity is Chaitanya Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Sea Vista?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Sea Vista?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Sea Vista?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Sea Vista?

The professionals named in the filing: Architect: SATISH N JOSHI; Architect: Sanika Patankar; Engineer: Sanjay Patankar; Engineer: Hemant Mahadev Khapane; Chartered Accountant: Jayant Joshi & Company. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Sea Vista?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Sea Vista. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Sea Vista to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.