ReraGenieLog inGet a buyer report

Home / Browse projects / Ratnagiri, Maharashtra / Mandke Lighthouse

Registered No litigation declared Mixed project

Mandke Lighthouse

By Mandke and Mandke Infrastructure Pvt. Ltd.

RG-MH-56484 · RERA P52800014361 · Last updated on MahaRERA portal: 10 Apr 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Ratnagiri registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedno revision filed
692 of 692Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 228 documents Report an error

Mandke Lighthouse is a Mixed project by Mandke and Mandke Infrastructure Pvt. Ltd. in Ratnagiri, Maharashtra, registered with MahaRERA as P52800014361 on 27 Nov 2017. Possession is promised by 30 Dec 2026. 0 of the 692 units on this registration are recorded sold or booked.

At a glance

Project

  • NameMandke Lighthouse
  • TypeMixed
  • Location
    • ASGOLI PALSHET ROAD
    • ASGOLI GOAN
    • Asgoli
    • Guhagar
    • Ratnagiri
    • 415703
  • Pincode415703
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52800014361
  • ReraGenie IDRG-MH-56484

Builder

  • NameMandke and Mandke Infrastructure Pvt. Ltd.
  • Entity typeCompany
  • Managing DirectorsMadhuri Sudhir Mandke, Indraneil Sudhir Mandke, Sudhir Yeshwant Mandke
  • Declared earlier projects4 →

Key dates

this monthRegisteredNov 2017PromisedDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on27 Nov 2017
  • Promised completion30 Dec 2026
  • Revised completionNone
  • Buildings4 building records
  • Documents filed228 files

Current status

0%0 of 692 units booked
79.5%Work done, per cost certificate

Figures as on 10 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Proposed construction of residential and commersial building ANA33381048
Proposed construction of residential and commersial building BNA43381048
Proposed construction of residential and commersial building CNA43381048
Building ANA44000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building5

As on 10 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Proposed construction of residential and commersial building ANot stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable
Proposed construction of residential and commersial building BNot stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable
Proposed construction of residential and commersial building CNot stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable
Building ANot stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable
NA Plot Without StructureNot stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 10 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes70%
Water SupplyYes70%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes20%
Storm Water DrainsYes50%
Landscaping & Tree PlantingYes40%
Street LightingYes40%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes30%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes40%
Aggregate area of recreational Open SpaceYes30%
Open ParkingNoNot applicable

Parking filed212

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots212
Closed/Covered2
Open Space210
BuildingClosed/CoveredOpen SpaceTotal
Proposed construction of residential and commersial building A07070
Proposed construction of residential and commersial building B17071
Proposed construction of residential and commersial building C17071

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area291,350 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on14 Jul 2026

Approvals and building plan

Sanctioning authorityRatnagiri Collector
Permissible FSI290035.0
Proposed, not sanctioned7,520 sq m
Buildings approved4
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch2002 PAUD ROAD, PUNE, SARASWATI BHAVAN, SNO 4/61, PAUD ROAD, NEAR MORE VIDYALAYA, PUNE - 411038
Estimated costRs 169.41 cr
Cost incurredRs 134.76 cr
Work done79.55%
BuildingWingEstimatedIncurred
Proposed construction of residential and commersial building ANARs 42.35 crRs 33.69 cr
Proposed construction of residential and commersial building BNARs 42.35 crRs 33.69 cr
Proposed construction of residential and commersial building CNARs 42.35 crRs 33.69 cr
Building ANARs 42.35 crRs 33.69 cr

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAgharkar Consultants
EngineerMayur Lakhe
Chartered AccountantNitin Inamdar
PartnerRole in project
Mandke and Mandke Infrastructure Pvt. Ltd.-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 3 Nov 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 3 Nov 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 6 Nov 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 2 Nov 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Dec 2026

Documents filed228

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 228 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Architect certificate studio.pdf10 Apr 2026
Withdrawal Update Form 2File: Form 2 upto 31-03-2026.pdf10 Apr 2026
Withdrawal Update Form 3File: Form 3 upto 31-03-2026.pdf10 Apr 2026
Form 2A (FY 2024-2025)File: Form 2A 2025.pdf23 Jan 2026
Form 5 (FY 2024-2025)File: Form 5 2025.pdf23 Jan 2026
Form 1File: form 1 upto 30-09-2025.pdf21 Jan 2026
Form 2File: Form 2 upto 30-09-2025.pdf21 Jan 2026
Form 3File: Form 3 upto 30-09-2025.pdf21 Jan 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Inventory upto 30-09-2025.pdf21 Jan 2026
Form 1File: form 1 upto 31-12-2025.pdf21 Jan 2026
Form 2File: Form 2 upto 31-12-2025.pdf21 Jan 2026
Form 3File: Form 3 upto 31-12-2025.pdf21 Jan 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Inventory upto 31-12-2025.pdf21 Jan 2026
Form 1File: form 1 upto 31-12-2024.pdf30 Jul 2025
Form 2File: Form 2 upto 31-12-2024.pdf30 Jul 2025
Form 3File: CA certificate upto 31-12-2024.pdf30 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold inventory upto 31-12-2024.pdf30 Jul 2025
Form 1File: form 1 upto 30-09-2024.pdf30 Jul 2025
Form 2File: Form 2 upto 30-09-2024.pdf30 Jul 2025
Form 3File: Form 3 upto 30-09-2024.pdf30 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold inventory upto 30-09-2024.pdf30 Jul 2025
Form 1File: form 1 upto 30-06-2024.pdf30 Jul 2025
Form 2File: Form 2 upto 30-06-2024.pdf30 Jul 2025
Form 3File: Form 3 upto 30-06-2024.pdf30 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold inventory upto 30-06-2024.pdf30 Jul 2025
Form 1File: form 1 upto 31-03-2024.pdf30 Jul 2025
Form 2File: Form 2 upto 31-03-2024.pdf30 Jul 2025
Form 3File: Form 3 upto 31-03-2024.pdf30 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold inventory upto 31-03-2024.pdf30 Jul 2025
Form 1File: form 1 upto 31-12-2023.pdf30 Jul 2025
Form 2File: Form 2 upto 31-12-2023.pdf30 Jul 2025
Form 3File: Form 3 upto 31-12-2023.pdf30 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold inventory upto 31-12-2023.pdf30 Jul 2025
Form 1File: form 1 upto 31-03-2025.pdf30 Jul 2025
Form 2File: Form 2 upto 31-03-2025.pdf30 Jul 2025
Form 3File: Form 3 upto 31-03-2025.pdf30 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold inventory upto 31-03-2025.pdf30 Jul 2025
Form 1File: form 1 upto 30-09-2023.pdf30 Jul 2025
Form 2File: Form 2 upto 30-09-2023.pdf30 Jul 2025
Form 3File: Form 3 upto 30-09-2023.pdf30 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold inventory upto 30-09-2023.pdf30 Jul 2025
Form 1File: form 1 upto 30-06-2023.pdf30 Jul 2025
Form 2File: Form 2 upto 30-06-2023.pdf30 Jul 2025
Form 3File: Form 3 upto 30-06-2023.pdf30 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold inventory upto 30-06-2023.pdf30 Jul 2025
Form 1File: form 1 upto 31-03-2023.pdf30 Jul 2025
Form 2File: Form 2 upto 31-03-2023.pdf30 Jul 2025
Form 3File: Form 3 upto 31-03-2023.pdf30 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold inventory upto 31-03-2023.pdf30 Jul 2025
Form 1File: Form 1 upto 30-06-2025.pdf30 Jul 2025
Form 2File: Form 2 upto 30-06-2025.pdf30 Jul 2025
Form 3File: CA Certificate upto 30-06-2025.pdf30 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold and Booked inventory upto 30-06-2025.pdf30 Jul 2025
Form 1File: form 1 upto 31-12-2022.pdf30 Jul 2025
Form 2File: Form 2 upto 31-12-2022.pdf30 Jul 2025
Form 3File: Form 3 upto 31-12-2022.pdf30 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold inventory upto 31-12-2022.pdf30 Jul 2025
Form 1File: form 1 upto 30-09-2022.pdf30 Jul 2025
Form 2File: Form 2 upto 30-09-2022.pdf30 Jul 2025
Form 3File: Form 3 upto 30-09-2022.pdf30 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold inventory upto 30-09-2022.pdf30 Jul 2025
Form 1File: form 1 upto 30-06-2022.pdf30 Jul 2025
Form 2File: Form 2 upto 30-06-2022.pdf30 Jul 2025
Form 3File: Form 3 upto 30-06-2022.pdf30 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold inventory upto 30-06-2022.pdf30 Jul 2025
Form 1File: form 1 upto 31-03-2022.pdf30 Jul 2025
Form 2File: Form 2 upto 31-03-2022.pdf30 Jul 2025
Form 3File: Form 3 upto 31-03-2022.pdf30 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold inventory upto 31-03-2022.pdf30 Jul 2025
Form 1File: form 1 upto 31-12-2021.pdf30 Jul 2025
Form 2File: Form 2 upto 31-12-2021.pdf30 Jul 2025
Form 3File: Form 3 upto 31-12-2021.pdf30 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold inventory upto 31-12-2021.pdf30 Jul 2025
Form 1File: form 1 upto 30-09-2021.pdf30 Jul 2025
Form 2File: Form 2 upto 30-09-2021.pdf30 Jul 2025
Form 3File: Form 3 upto 30-09-2021.pdf30 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold inventory upto 30-09-2021.pdf30 Jul 2025
Form 1File: form 1 upto 30-06-2021.pdf30 Jul 2025
Form 2File: Form 2 upto 30-06-2021.pdf30 Jul 2025
Form 3File: Form 3 upto 30-06-2021.pdf30 Jul 2025

Promoter's earlier projects4

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise2 not delivered by the promised date
ProjectLocationRegisteredStatusPromisedDelivered
Mandke Advantage HomesP52100003587MUNJERI BIBVEWADI, PuneAug 2017Certificate SignedAug 2024Not delivered
Mandke AffluenceMandke Affluence, Opposite Krishna Hospital, Kothrud, Pune - 411038-CompletedDec 2022Oct 2021
Mandke Armaan 4th to 7th floorP52100003465VIMANNAGAR, PuneAug 2017Certificate SignedSep 2018Not delivered
Mandke AnubhavMandke Anubhav, MIT College front Gate, Pune - 411038-CompletedDec 2009Jun 2009

How this compares with Ratnagiri

0%of this project is bookeddistrict median 23%
15%of Ratnagiri projects moved their completion datethis one has not
30%of Ratnagiri registrations have lapsed or been cancelledthis one is on the register

Computed across the 1,100+ Ratnagiri projects on ReraGenie, from their own filings.

Keep Mandke Lighthouse on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near ASGOLI GOAN1,100+ in Ratnagiri

2 kmMandke LighthouseCompleted 4Lapsed / revoked 8Other 2Dot size: filed unitsN

Filed coordinates, straight-line distance. 14 registered projects within 2 km.

Builder: Mandke and Mandke Infrastructure Pvt. Ltd.

Mandke and Mandke Infrastructure Pvt. Ltd. has 1 registration on MahaRERA, including Mandke Lighthouse. Its filings disclose 4 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Ratnagiri district page.

Frequently asked questions

What are my rights if Mandke Lighthouse is delayed beyond 30 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Mandke Lighthouse?

The registered promoter entity is Mandke and Mandke Infrastructure Pvt. Ltd., a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Mandke Lighthouse?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Mandke Lighthouse?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Mandke Lighthouse?

The professionals named in the filing: Architect: Agharkar Consultants; Engineer: Mayur Lakhe; Chartered Accountant: Nitin Inamdar. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Mandke Lighthouse?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Mandke Lighthouse. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Mandke Lighthouse to a free account