Home / Browse projects / Ratnagiri, Maharashtra / TomorrowView

Completed No litigation declared Plotted project

TomorrowView

By House of Abhinandan Lodha Estate Holdings Private Limited

RG-MH-00064 · RERA P52800050210 · Last updated on MahaRERA portal: 29 Jun 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Ratnagiri registration emailed to you, free during the pilot beta.
Dec 2025Possession promisedregistration recorded completed
108 of 494Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 104 documents Report an error

TomorrowView is a Plotted project by House of Abhinandan Lodha Estate Holdings Private Limited in Ratnagiri, Maharashtra, registered with MahaRERA as P52800050210 on 27 Mar 2023. The registration is recorded completed; possession was promised by 31 Dec 2025. 386 of the 494 units on this registration are recorded sold or booked. 1 complaint is on record with the regulator.

At a glance

Project

  • NameTomorrowView
  • TypePlotted
  • Location
    • Village Padale
    • Taluka Dapoli
    • District Ratnagiri
    • Padale
    • Dapoli
    • Ratnagiri
    • 415714
  • Pincode415714
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52800050210
  • ReraGenie IDRG-MH-00064

Builder

  • NameHouse of Abhinandan Lodha Estate Holdings Private Limited
  • Entity typeCompany
  • CINU45400MH2014PTC257395
  • CIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • DirectorsSagar Gawde, Rakesh Gupta, Rakesh Ramdas Gupta
  • Other registrations6 more →
  • Completed7 of 7
  • Declared earlier projects4 →

Key dates

this monthRegisteredMar 2023PromisedDec 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on27 Mar 2023
  • Promised completion31 Dec 2025
  • Revised completionNone
  • BuildingsNot stated in filing
  • Documents filed104 files

Current status

78%386 of 494 units booked
47.6%Work done, per cost certificate

Figures as on 29 Jun 2026, this project's latest MahaRERA filing.

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 29 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

NA Plot Without Structure:

ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 29 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes60%
Water SupplyYes27%
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes25%
Street LightingYes25%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes12%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area190,554 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on30 Sep 2024

Approvals and building plan

Sanctioning authorityAssistance Director of Town Planning Ratnagiri

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGround Floor, Industry House, Opp Ramon House, 159 H T Parekh Marg
Estimated costRs 67.55 cr
Cost incurredRs 32.18 cr
Work done47.64%
BuildingWingEstimatedIncurred
-NARs 67.55 crRs 32.18 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRajesh Ashok Rao
ArchitectBhalachandra Gothankar
EngineerDinesh Balkrishna Satam
Chartered AccountantNPSR and Associates
Chartered AccountantU S MISHRA AND ASSOCIATES
Chartered AccountantT. P. Ostwal & Associates LLP
PartnerRole in project
House of Abhinandan Lodha Estate Holdings Private Limited-

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12601475Rohan ThakkerHouse of Abhinandan Lodha Estate Holdings Private Limited17/03/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 7 Mar 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 20 Mar 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 6 Mar 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 20 Mar 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 7 Jan 2026

Documents filed104

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 104 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: Signed_Form 2A_Tomorrow View.pdf29 Jun 2026
Completion CertificateFile: Completion Certificate Confirmation email.pdf7 Jan 2026
Withdrawal Update Form 1File: Architect Certificate_TomorrowView_Signed.pdf20 Dec 2025
Withdrawal Update Form 2File: Engineer Certificate_TomorrowView_Signed.pdf20 Dec 2025
Withdrawal Update Form 3File: CA Certificate_TomorrowView_Signed.pdf20 Dec 2025
Completion CertificateFile: TomorrowView - Completion Certificate.pdf20 Dec 2025
Withdrawal Update Form 1File: AC - TomorrowView.pdf19 Dec 2025
Withdrawal Update Form 2File: EC - TomorrowView.pdf19 Dec 2025
Withdrawal Update Form 3File: CA - TomorrowView.pdf19 Dec 2025
Form 5 (FY 2024-2025)File: Form 5_TommorrowView_2024-25.pdf29 Sep 2025
Form 1File: 1 AR June 23.pdf2 Jul 2025
Form 2File: 1 ER June 23.pdf2 Jul 2025
Form 3File: 1 CA June 23.pdf2 Jul 2025
Disclosure of Sold and Booked InventoryFile: 1 Disclosure June 23.pdf2 Jul 2025
Form 1File: 3 AR Dec 23.pdf2 Jul 2025
Form 2File: 3 ER Dec 23.pdf2 Jul 2025
Form 3File: 3 CA Dec 23.pdf2 Jul 2025
Disclosure of Sold and Booked InventoryFile: 3 Disclosure Dec 23.pdf2 Jul 2025
Form 1File: 4 AR March 24.pdf2 Jul 2025
Form 2File: 4 ER March 24.pdf2 Jul 2025
Form 3File: 4 CA March 24.pdf2 Jul 2025
Disclosure of Sold and Booked InventoryFile: 4 Disclosure March 24.pdf2 Jul 2025
Form 1File: 5 AR June 24.pdf2 Jul 2025
Form 2File: 5 ER June 24.pdf2 Jul 2025
Form 3File: 5 CA June 24.pdf2 Jul 2025
Disclosure of Sold and Booked InventoryFile: 5 Disclosure June 24.pdf2 Jul 2025
Form 1File: 6 AR Sept 24.pdf2 Jul 2025
Form 2File: 6 ER Sept 24.pdf2 Jul 2025
Form 3File: 6 CA Sept 24.pdf2 Jul 2025
Disclosure of Sold and Booked InventoryFile: 6 Disclosure Sept 24.pdf2 Jul 2025
Form 1File: 7 AR Dec 24.pdf2 Jul 2025
Form 2File: 7 ER Dec 24.pdf2 Jul 2025
Form 3File: 7 CA Dec 24.pdf2 Jul 2025
Disclosure of Sold and Booked InventoryFile: 7 Disclosure Dec 24.pdf2 Jul 2025
Form 1File: 8 AR March 25.pdf2 Jul 2025
Form 2File: 8 ER March 25.pdf2 Jul 2025
Form 3File: 8 CA March 25.pdf2 Jul 2025
Disclosure of Sold and Booked InventoryFile: 8 Disclosure March 25.pdf2 Jul 2025
Form 2A (FY 2024-2025)File: Form 2A - TomorrowView.pdf30 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: TomorrowView - Achitect Certificate.pdf19 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: TomorrowView-P52800050210-CA certificate.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: TomorrowView- Engineer Certificate.pdf19 Apr 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory-TomorrowView-signed.pdf19 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AC_TV 5.pdf20 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA_H-Estate_TV-P5_(SIDPL).pdf20 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: EC_TV 5.pdf20 Jan 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory- TV.pdf20 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AC_TomorrowView.pdf19 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA_TV.pdf19 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: EC_TV Signed.pdf19 Oct 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory-Tomorrow View_signed.pdf19 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: 5 TomorrowView Certificate_Form 5_promoter signed.pdf7 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Tomorrow View - Arch certificate-signed.pdf20 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Tomorrow View - Engineer certificate.pdf20 Jul 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory- Tomorrow View.pdf20 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Tomorrow View - CA certificate.pdf20 Jul 2024
Home Buyer /Allottee Grievance Redressal CellFile: Hoabl Estate holdings.pdf5 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A_Anjarle 5_signed.pdf27 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR.pdf20 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ER.pdf20 Apr 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory-TomorrowView.pdf20 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA.pdf20 Apr 2024
Layout approvalFile: Padle 49 layout plan_P5_compressed.pdf20 Mar 2024
Copy of Layout Approval (in case of layout)File: Padle 49 layout plan_P5_compressed.pdf20 Mar 2024
Commencement Certificates / NA Order for plotted developmentFile: Padle 49 order_P5_compressed (1).pdf20 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AC_Ph 5.pdf20 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: EC_Ph 5.pdf20 Jan 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory-TomorrowView.pdf20 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SIDPL_PH5.pdf20 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AC_H_estate_P5.pdf17 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: TV.pdf17 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SIDPL Phase 5tomrrow.pdf17 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: SIDPL form5 P-5_compressed.pdf30 Sep 2023
Disclosure of sold/ booked inventoryFile: Anjarle phase 5-Sig.pdf13 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf7 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf7 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA ph5.pdf7 Sep 2023
Other - TechnicalFile: Company name change letter.pdf26 May 2023
Layout approvalFile: Revised TP_TV_compressed.pdf25 May 2023
Copy of Layout Approval (in case of layout)File: Revised TP_TV_compressed.pdf25 May 2023

Promoter's earlier projects4

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered on promise1 not delivered by the promised date
ProjectLocationFlatsStatusPromisedDelivered
Tomorroworld - Tomorrowland Phase IVGat no 341 342 343 344 347 348A 348B 349 350 351 and 352 At Padle Taluka Dapoli Dist Ratnagiri-415714-OngoingJun 2024Not delivered
Codename Tomorrowland Ph-3Gat No 138 20 139 23 137 11 At Anjarle Taluka Dapoli Dist Ratnagiri 415714-CompletedJun 2024Jun 2024
Codename Tomorrowland Ph-2Gat no 315 A 315 B 317 320 Part 321 324 209 325 326 328 329 APart and 329 BPart at Padale Dapoli Ratnagiri 415714387CompletedJun 2024Jun 2024
Codename Tomorrowland Ph-1Gat no 315 A 315 B 317 320 Part 321 324 326 209 325 328 329 A Part and 329 B Part at Padale Taluka Dapoli Dist Ratnagiri 415714119CompletedJun 2024Jun 2024

How this compares with Ratnagiri

78%of this project is bookeddistrict median 23%
15%of Ratnagiri projects moved their completion datethis one has not
30%of Ratnagiri registrations have lapsed or been cancelledthis one is completed

Computed across the 1,100+ Ratnagiri projects on ReraGenie, from their own filings.

Keep TomorrowView on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near District Ratnagiri1,100+ in Ratnagiri

2 kmTomorrowViewCompleted 1Other 2Dot size: filed unitsN

Filed coordinates, straight-line distance. 3 registered projects within 2 km.

Builder: House of Abhinandan Lodha Estate Holdings Private Limited

House of Abhinandan Lodha Estate Holdings Private Limited has 7 registrations on MahaRERA, including Codename Tomorrowland Ph-1 and Codename Tomorrowland Ph-2. Its filings disclose 4 earlier MahaRERA projects: declares 3 of 3 past projects completed on time. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Ratnagiri district page.

Frequently asked questions

What are my rights if TomorrowView is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of TomorrowView?

The registered promoter entity is House of Abhinandan Lodha Estate Holdings Private Limited, a company as per the filing. Its CIN U45400MH2014PTC257395 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in TomorrowView?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against TomorrowView?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for TomorrowView?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at TomorrowView?

The professionals named in the filing: Architect: Rajesh Ashok Rao; Architect: Bhalachandra Gothankar; Engineer: Dinesh Balkrishna Satam; Chartered Accountant: NPSR and Associates; Chartered Accountant: U S MISHRA AND ASSOCIATES; Chartered Accountant: T. P. Ostwal & Associates LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in TomorrowView?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About TomorrowView. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save TomorrowView to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.