New projects and RERA data in Kolhapur district, Maharashtra
880 projects are registered in Kolhapur district: 14,903 units across them, 70 registered in the last 12 months. Sales and inventory trends accumulate from each future quarterly update; this page shows the first one.
Of the 880 covered registrations, 153 have revised their promised completion date and 8 declare litigation. The median project here is 19% booked as of the current data. Every figure comes from the projects' own MahaRERA filings.
Also free on ReraGenie: a monthly RERA report for the seven biggest markets in Maharashtra (Pune, Mumbai, Thane, Navi Mumbai, Nagpur, Nashik and Vasai-Virar): what registered that month, the possession pipeline and the busiest pincodes, from the filings. See the latest editions.
When Kolhapur projects promise possession
Promised possession year as filed by the builder with MahaRERA, split by what the registration says today. Of 880 projects with a promised date, 390 are recorded delivered, 269 are still on the register and 221 have a registration that has lapsed or been cancelled.
DeliveredOn the registerRegistration lapsed or cancelled
349 projects promise possession in 2026 or later. Facts as per filings on RERA website.
12,228 flats are promised in 2026 or later, across the 73% of those projects that file a flat count. Hatched years are ones where most builders never filed a count, so the bar understates real supply and cannot be compared with the years beside it. Facts as per filings on RERA website.
How far Kolhapur possession dates have moved
Builders may revise the possession date they filed at registration. Each bar is the year a project first promised, split by how far that date has since moved. 152 of 880 projects (17%) have moved at least once; the median move is 18 months and the longest is 90 months.
Kept the original dateMoved by under 2 yearsMoved by 2 years or more
Read down a bar to see how much of that year's cohort held its promise. Facts as per filings on RERA website.
Hatched years are ones where most builders never filed a flat count, so the bar understates the real total. Read down a bar to see how much of that year's cohort held its promise. Facts as per filings on RERA website.
Permissions and land in Kolhapur
Who sanctions building in Kolhapur
284 of the 880 registrations on this page name the body that sanctioned their building plan. The rest leave that box empty, which is a gap in the filing and not a project without permission: the commencement certificate is filed as a separate document and is on the file for most projects. The body named here is where a commencement or occupancy certificate is verified.
| Sanctioning authority | Projects |
|---|---|
| Kolhapur Municipal Corporation | 196 |
| Kolhapur Urban Area Development Authority | 17 |
| 34 other bodies | 71 |
One body is often filed under several spellings, and those are counted together. Acronyms that could mean two different bodies are not: PMC is Pune or Pimpri Chinchwad depending who typed it, so it is counted as filed.
Whose name the land is in
Every one of the 880 registrations on this page answers this: on 513 the promoter is the only owner named; on 315 the promoter is an owner with other names on the file, which is what a joint development looks like on paper; on 52 the promoter is not an owner. Where other names are on the file, ask which of them signs your agreement for sale. A landowner who is not a party to it is a question for your lawyer before you pay, not a defect in the project.
Where in Kolhapur: projects by taluka
880 of the 880 registrations on this page name their taluka.
| Taluka | Projects | Share |
|---|---|---|
| Karvir | 601 | 68% |
| Hatkanangle | 100 | 11% |
| Gadhinglaj | 87 | 10% |
| Shirol | 46 | 5% |
| 8 other talukas | 46 | 5% |
Projects in Kolhapur
Showing 1 to 60 of 880 projects.
Largest first, by the unit count in the filing.
| Project | Developer | Units | Booked | Registered | Status |
|---|---|---|---|---|---|
| HIGHSTREET CBD - TOWER AKARVEER, 416007 | HIGHSTREET DEVELOPERS | 531 | 9% | 2 Feb 2026 | Registered |
| ELIXA PARKāEā Ward, 416001 | AJAYSINH V DESAI BUILDERS & DEVELOPERS | 334 | 85% | 29 Jul 2017 | Completed |
| GATEWAY RESIDENCIESUchgaon (CT), 416005 | SIDDHIVINAYAK DEVELOPERS | 314 | 10% | 29 Jan 2026 | Registered |
| 24 KEYWEST EAST AND WEST AVENUEIN FRONT OF INCOME TAX OFFICE, 416003 | KEYWEST INFRA | 307 | 4% | 14 Jul 2025 | Registered |
| SHAMRAO SHELKE COMMERCIAL AND RESIDENTIAL COMPLEXBAMBAWADE, 416015 | TRIVENI INFRAPROJECT PVT LTD | 257 | 51% | 10 Aug 2017 | Registered |
| PRATHAM PRASAD GARDENSPHULEWADI, 416010 | GURUPRASAD DEVELOPERS AND BUILDERS | 250 | 47% | 22 Dec 2022 | Registered |
| Loknagari Karande MalaKarande Mala, Kasaba Bawada E Ward, Kadamwadi Road, 416003 | VIKESH ABHAYKUMAR OSWAL | 230 | 0% | 25 May 2026 | Registered |
| GRUHALAXMI RACHANASambhaji Nagar, 416012 | BATU BUILDERS | 198 | 54% | 29 Nov 2021 | Registered |
| SHRI MAHALAXMI RESIDENCYMOUJE WADIPIR, 416001 | SUPRIYA SACHIN MANGALE | 169 | 38% | 6 Feb 2024 | Registered |
| WESTERN GATEWAYPhulewadi, 416010 | Harmony Vision | 168 | 18% | 21 Aug 2023 | Registered |
| M/S. BALAJI PROPERTIESUCHGAON, 416004 | VISHAL KANTILAL CHORDIA HUF | 161 | 0% | 11 Sep 2023 | Completed |
| SRI SRI RESIDENCYSambhaji Nagar 'B' Ward Near Magdum Lawn, Kolhapur, 416012 | SRI SRI BUILDERS AND DEVELOPERS PROPRIETOR VIJAY KISANLAL AGARWAL | 158 | 68% | 18 Feb 2021 | Registration lapsed |
| THE BALSAMA Ward Sane Guruji Vasahat KII Karveer, 416011 | M/S JOTIRADITYA BUILDERS | 144 | 0% | 29 May 2026 | Registered |
| ONE EARTHKolhapur (M Corp.), 416012 | DESHPANDE INFRA | 135 | 5% | 10 Dec 2025 | Registered |
| KRYSTAL TOWERSE WARD, 416003 | RAYSONS CONSTRUCTIONS | 131 | 41% | 31 May 2024 | Registered |
| HIGHSTREET CBD - TOWER EHockey Stadium Chowk, 416007 | HIGHSTREET DEVELOPERS | 128 | 38% | 2 Feb 2026 | Registered |
| DRONAGIRIJIWBA NANA JADHAV PARK, 416012 | ASHTIN INDIA PVT LTD | 126 | 81% | 11 Apr 2022 | Registered |
| HIGHSTREET CBD - TOWER DHOCKEY STADIUM CHOWK, 416007 | HIGHSTREET DEVELOPERS | 126 | 66% | 27 Mar 2025 | Registered |
| plotted development scheme on gat no 417 at Radhanagri taluka Radhanagri dist KolhapurRadhanagari, 416212 | Pune Housing and Area Development Board Pune | 123 | 72% | 14 Aug 2017 | Completed |
| JEWEL SQUAREB WARD MANGALWAR PETH, 416012 | RATNARAJ BUILDERS AND DEVELOPERS | 120 | 6% | 16 May 2024 | Registered |
| Eminent SquareRing Road, 416008 | SHRI SIDDHIVINAYAK ASSOCIATES | 113 | 26% | 19 Jul 2023 | Registered |
| AMEY HI LIFEnana patil nagar, 416010 | AMEY ESTATE | 109 | 90% | 28 Jul 2017 | Completed |
| ROYAL PLANETE ward Opp Rajesh Motors, 416001 | SURAJ ESTATE DEVELOPERS | 108 | 61% | 12 Dec 2022 | Completed |
| BEEZHIVEE WARD, SHAHUPURI, 416001 | BEDEKAR LIFESPACES LLP | 106 | 26% | 29 May 2021 | Completed |
| Mixed-B 3 MayyzChafodi T.tarale, 242342 | Rupal as Companyz | 104 | 2% | 1 Jan 2024 | Registration lapsed |
| PunyaSrushti Tower B and CPratibhanagar, 416008 | Punyasrushti Sahakari Gruhnirman Sanstha Maryadit | 103 | 3% | 27 Jun 2023 | Registered |
| DWARKA EUROUchgaon, 416005 | Randive Builders and Developers | 98 | 33% | 8 Jul 2021 | Registered |
| SANJAY GHODAWAT INDUSTRIAL PARKMouje Majale, 416109 | Ghodawat Eduserve Limited Liability Partnership | 97 | 0% | 30 Mar 2022 | Registration lapsed |
| Suryoday Nagar Layout-Buchgaon, 416005 | Suraj Land Developments | 96 | 0% | 14 Dec 2020 | Completed |
| ANANT PRIDE PHASE IIIBANK SHIPAI COLONY, 416007 | VIVEKANAND VASANTRAO PATIL | 90 | 0% | 11 May 2026 | Registered |
| NIMBALKAR HERITAGETarabai Road, 416008 | MORBALE INFRA PROJECT PRIVATE LIMITED | 90 | 0% | 21 May 2026 | Registered |
| SAPPHIRE SKYDevkar Panand, 416012 | S.S.Builders and Developers | 89 | 18% | 24 May 2022 | Registered |
| ROYAL 09 TOURIST BUSINESS HUBE ward, 416001 | SURAJ ESTATE DEVELOPERS | 88 | 44% | 6 Aug 2022 | Completed |
| EMH - 2-, 416145 | Padmavati Developers | 86 | 0% | 10 Oct 2022 | Registration lapsed |
| GAYATRI-BHAWANI APARTMENTTARABAI PARK, 416003 | Vijaykumar Vasudev Patki | 86 | 38% | 17 Aug 2017 | Registration lapsed |
| CRYSTAL SKYLINESALOKHE NAGAR, 416007 | Build Angle Builders and Developers | 85 | 22% | 17 Dec 2024 | Registered |
| Gajalaxmi ParkHatkanagle, 416115 | Amit Yashwant Singh and Others | 85 | 0% | 23 May 2020 | Registration lapsed |
| YASHSHRI - GRAND LAKE VISTAA WARD, 416012 | DESTINY BUILDERS | 85 | 0% | 1 Oct 2026 | Registered |
| Atharva Sky Line Wing-BUjalaiwadi, 416005 | Sanjay Prabhakar Kulkarni | 84 | 74% | 14 Nov 2019 | Registered |
| IDEAL ELITEMorewadi, 416013 | IDEAL PROPERTIES | 84 | 6% | 21 Jan 2026 | Registered |
| SEQUOIA RISEE WARD, 416013 | AMAR PANDURANG JADHAV | 84 | 0% | 27 Apr 2026 | Registered |
| RADHA REGENCYRamanand nagar, 416007 | VJ AND SPACE REALTORS | 83 | 0% | 11 Sep 2026 | Registered |
| PUNYA SHLOK TOWER I AND TOWER IIE WARD KOLHAPUR, 416005 | RAMSINA CONSTRUCTIONS PVT LTD | 80 | 19% | 19 Jan 2024 | Registration lapsed |
| TIME SQUAREGavat Mandai Kolhapur, 416001 | GREY BRICKS REALITY | 80 | 0% | 1 Oct 2026 | Registered |
| Viraj City Building FKagal, 416216 | Bhuyekar Patil Construction Company | 80 | 46% | 28 Apr 2022 | Registered |
| INDRANAND GREENSKolhapur, 416004 | Satish Anandrao Ghorpade | 77 | 58% | 7 Oct 2017 | Registered |
| PUNYA ARPITTAKALA, 416008 | RAMSINA CONSTRUCTIONS PVT LTD | 77 | 79% | 20 Apr 2022 | Registration lapsed |
| SHREE SAMARTH HEIGHTSGADHINGLAJ, 416502 | SHREE SAMARTH HEIGHTS | 72 | 12% | 25 Aug 2023 | Registered |
| HARMONY MADHUBANE WARD, KATKAR MAL, TAKALA, 416008 | M/S HARMONY INFRA | 71 | 27% | 2 Feb 2024 | Registered |
| OM SAI PARADISENA, 416502 | SHREE BALAJI BUILDERS AND DEVELOPERS | 71 | 14% | 15 Apr 2024 | Completed |
| plotted development at Gat no 49 Gaganbavda taluka Gaganbavda district KolhapurGagan Bavda, 416206 | Pune Housing and Area Development Board Pune | 71 | 94% | 1 Sep 2017 | Completed |
| RAJARAM SHIVGONDA GORULEHARALI BUDRUK, 416502 | RAJARAM SHIVGONDA GORULE | 70 | 79% | 6 Dec 2020 | Registration lapsed |
| Gajanan Venkatesh ComplexNagala Park, 416012 | Vishal Developers | 69 | 83% | 29 Dec 2021 | Registered |
| HARIPRIYA SANKULNIRMAN CHOWK, 416012 | DATTA SAI BUILDERS AND DEVELOPERS | 69 | 43% | 19 Jul 2023 | Registered |
| LAVANGONDA SHIVGONDA PATILA/P- HARALI, 416502 | LAVANGONDA SHIVGONDA PATILL | 69 | 33% | 20 Jan 2020 | Registered |
| AMBAI RESIDENCYRankala west, 416012 | M/S HARMONY INFRA | 67 | 81% | 4 Jan 2022 | Completed |
| Jainapur Industrial ParkJainapur, 416101 | Jainapur Vikas Industrial Association and Samruddhi Industries Ltd. | 66 | 0% | 21 Oct 2020 | Registration lapsed |
| Vrindavan ParadiseDHARMRAJ CHOWK, 416115 | HBD DEVELOPERS | 66 | 27% | 21 Feb 2024 | Registered |
| AMEY HI LIFE WING C & DKolhapur (M Corp.), 416010 | AMEY ESTATES | 65 | 0% | 11 Sep 2025 | Registered |
| AERO CITYUJALAIWADI TAL-KARVIR, 416004 | VIJAY SADHURAM PANJWANI | 64 | 0% | 11 Sep 2026 | Registered |
Developers active in Kolhapur
DESHPANDE INFRA (7), Pune Housing and Area Development Board Pune (7), BHASKAR RAMGONDA PATIL (6), Tushar Mohanrao Khatavkar (6), HIGHSTREET DEVELOPERS (5), THE IDEAL CONSTRUCTION (5). Each link opens the promoter's track record built from their own filings.
Frequently asked questions
How do I shortlist among the Kolhapur projects listed above?
Compare each project against its neighbours, not against the brochure. The median project on this page is 19% booked, which is the benchmark to hold any single project against. A project selling much slower than the district may have a pricing or credibility problem; one selling much faster deserves a look at whether construction is keeping pace with collections. Then open the developer link to check their delivery record on other projects, and compare filed carpet areas rather than super built-up marketing areas.
What does a revised completion date on a Kolhapur project actually mean?
The promoter has moved their deadline with the regulator, usually under section 6, which allows an extension of up to one year for reasons beyond their control. It does not move the date in your agreement for sale: your section 18 claim for delay interest or refund runs from the possession date you signed for. Before booking a project with a revision on record, ask which approvals or works the new date depends on.
What stamp duty will I pay on a flat in Kolhapur district?
The rate depends on the local body: roughly 6 to 7 percent inside municipal corporations, 4 percent in municipal council areas and 3 percent in gram panchayat areas, with women buying in their sole name paying 1 percent less. The registration fee is 1 percent of value, capped at Rs 30,000. Duty is charged on the higher of your agreement value and the ready reckoner value. ReraGenie has a free Maharashtra stamp duty calculator under Tools.
What does it mean that some Kolhapur registrations have lapsed?
A RERA registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then, the registration lapses and the project stops being a registered project: the promoter may not legally market or sell in it, and the Authority can act under section 7 against a defaulting promoter. It does not cancel your agreement for sale or your section 18 rights if you have already booked, and it does not mean construction has stopped. Ask the promoter for the current registration position in writing, and verify it on the MahaRERA portal before you pay any further instalment.
What if a Kolhapur project shows strong sales but slow construction?
That shape means the promoter is collecting money faster than they are building, which is fine under a disciplined promoter and dangerous under a stretched one. The law helps: withdrawals from the project account need architect, engineer and CA certificates in proportion to progress. Check the promoter's delivery record, and watch the next quarterly filing (due within 20 days of each quarter end) to see whether the construction line moves.
Does something here look wrong, or is there a number you expected to find and did not? Every figure on this page is summed from the projects' own MahaRERA filings, and we read every report.