Registered No litigation declared Residential / Group Housing project

SHREE SAMARTH HEIGHTS

By SHREE SAMARTH HEIGHTS

RG-MH-68966 · RERA P53000052425 · Last updated on MahaRERA portal: 20 Feb 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 20 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Kolhapur registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 20 months from the original
4 of 11Construction stages donefurthest along: Slabs of Super Structure, 75%
63 of 72Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 77 documents Report an error

SHREE SAMARTH HEIGHTS is a Residential / Group Housing project by SHREE SAMARTH HEIGHTS in Kolhapur, Maharashtra, registered with MahaRERA as P53000052425 on 25 Aug 2023. Possession is promised by 31 Dec 2026. The completion date has moved by 20 months from the original filing. 9 of the 72 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.

At a glance

Project

  • NameSHREE SAMARTH HEIGHTS
  • TypeResidential / Group Housing
  • Location
    • BHADGAON ROAD
    • GADHINGLAJ
    • Kolhapur
    • 416502
  • Pincode416502
  • RERA no.P53000052425
  • ReraGenie IDRG-MH-68966

Builder

  • NameSHREE SAMARTH HEIGHTS
  • Entity typePartnership
  • PartnerVILAS MARUTI PATIL

Key dates

this monthRegisteredAug 2023First promiseApr 2025Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on25 Aug 2023
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 20 Apr 2025)
  • Buildings1 building record
  • Documents filed77 files

Current status

12%9 of 72 units booked
12.5%Work done, per cost certificate

Figures as on 20 Feb 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHREE SAMARTH HEIGHTSNA74274572

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 75%.

SHREE SAMARTH HEIGHTS: 53% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure75%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks40%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 20 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes10%
Water SupplyYes20%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes30%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed33

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots33
Closed/Covered33

Land and ownership6

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,111 sq m
Land owned byThe promoter, with other names on the file
Named landowners6
Encumbrance on the landDeclared none
Declared on24 Nov 2025
LandownerVillageDistrict
HANMAMT LAXMAN PATHARVATGadhinglajKolhapur
NISHIKANT GANPATRAO CHOTHEGadhinglajKolhapur
VIMAL SURESH PATILGadhinglajKolhapur
VIRAPPA SONABA MORTIGadhinglajKolhapur
VISHWANATH GANPATI SHINTREThane (M Corp.)Thane
SHRIPATI RANABA SUTARGadhinglajKolhapur

Approvals and building plan

Sanctioning authorityGADHINGLAJ MUNCIPAL COUNSIL
Permissible FSI3392.02
Proposed, not sanctioned3,392 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBADYACHI WADI GADHINGLAJ
Estimated costRs 6.14 cr
Cost incurredRs 76.60 lakh
Work done12.47%
BuildingWingEstimatedIncurred
SHREE SAMARTH HEIGHTSNARs 6.14 crRs 76.60 lakh

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectGORULE ARCHITECTS
EngineerOMKAR VAIJANATH TARALI
Chartered AccountantSACHHIDANAD SHARAD KULKARNI
Chartered AccountantMANISH RAMAWATI
PartnerRole in project
SHREE SAMARTH HEIGHTS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA26052501256Apr 2025 → Dec 2026

Reason as filed by the promoterDear Sir/Ma’am, We, Shree Samarth Heights, hereby declare the following with respect to the project “Shree Samarth Heights” bearing registration number P53000052425 registered under MahaRERA 1. Status of Work Completed: We are pleased to inform you that we have completed the 80% of RCC (Reinforced Cement Concrete) work for the building. Currently, we are undertaking the finishing work, which includes plastering, flooring, electrical fittings, and other essential internal and external works. 2. Expected Timeline for Completion: We are committed to completing all balance works and applying for t

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 14 Feb 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Jul 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Jul 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 26 Jul 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed77

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 Final.pdf20 Feb 2026
Withdrawal Update Form 2File: Form 2 Final.pdf20 Feb 2026
Withdrawal Update Form 3File: Form 3 Latest.pdf20 Feb 2026
Form 2A (FY 2023-2024)File: FORM 2A 31.3.2024.pdf4 Nov 2025
Form 2A (FY 2024-2025)File: FORM 2A 31.3.2025.pdf4 Nov 2025
Form 1File: form 1.pdf8 Oct 2025
Form 2File: FORM 2.pdf8 Oct 2025
Form 3File: FORM 3.pdf8 Oct 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSER INVENTORY.pdf8 Oct 2025
Form 1File: FORM 1.pdf8 Oct 2025
Form 2File: FORM 2.pdf8 Oct 2025
Form 3File: FORM 3 CA.pdf8 Oct 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSER INVENTORY.pdf8 Oct 2025
Form 1File: FORM 1.pdf8 Oct 2025
Form 2File: FORM 2.pdf8 Oct 2025
Form 3File: FORM 3.pdf8 Oct 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSER INVENTORY.pdf8 Oct 2025
Form 1File: FORM 1.pdf8 Oct 2025
Form 2File: FORM 2.pdf8 Oct 2025
Form 3File: FORM 3.pdf8 Oct 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSER INVENTORY.pdf8 Oct 2025
Form 1File: FORM 1.pdf8 Oct 2025
Form 2File: FOMR 2.pdf8 Oct 2025
Form 3File: FORM 3 CA.pdf8 Oct 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSER INVENTORY.pdf8 Oct 2025
Form 5 (FY 2023-2024)File: FORM 5.pdf8 Oct 2025
Form 5 (FY 2024-2025)File: FORM 5.pdf8 Oct 2025
Form 1File: FORM 1.pdf15 Aug 2025
Form 2File: FORM 2.pdf15 Aug 2025
Form 3File: form 3_compressed.pdf15 Aug 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSER OF INVENTORY.pdf15 Aug 2025
Form 1File: FORM 1.pdf15 Aug 2025
Form 2File: FORM 2.pdf15 Aug 2025
Form 3File: FORM 3_compressed.pdf15 Aug 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSERS OF INVENTORY.pdf15 Aug 2025
Form 1File: FORM 1.pdf15 Aug 2025
Form 2File: FORM 2.pdf15 Aug 2025
Form 3File: FORM 3_compressed.pdf15 Aug 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSERS OF INVENTORY.pdf15 Aug 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE JUNE 24.pdf26 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE SEPT 24.pdf26 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE DEC 24.pdf26 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE NOV 2023.pdf10 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE FEB 2024.pdf10 May 2024
Building plan approvalFile: 1 Copy of Layout Approval (in case of layout).pdf27 Jul 2023
Building Plan Approval / NA Order for plotted developmentFile: 1 Copy of Layout Approval (in case of layout).pdf27 Jul 2023
Other - LegalFile: Title.pdf27 Jul 2023
Details of encumbrances concerned to FinanceFile: ENCUMBRANCES LEGAL.pdf26 Jul 2023
Details of encumbrances concerned to LegalFile: ENCUMBRANCES LEGAL.pdf26 Jul 2023
Commencement Certificates / NA Order for plotted developmentFile: plinth certificate.pdf26 Jul 2023
Other - LegalFile: ENCUMBRANCES LEGAL.pdf26 Jul 2023
Other - TechnicalFile: plinth certificate.pdf26 Jul 2023
Other - FinanceFile: ENCUMBRANCES_20230711_0001.pdf5 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Latest.pdf27 Apr 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: din shrikant dadu patil_20230421_0001.pdf21 Apr 2023
CERSAI detailsFile: CERSAI DECLERATION_20230711_0001.pdf16 Mar 2023
Declaration about Commencement CertificateFile: DECLERATION OF FORMAT D_20230711_0001.pdf11 Mar 2023
Declaration in FORM BFile: FORM B_11zon.pdf11 Mar 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: DIN VILAS PATIL_20230421_0001.pdf15 Feb 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: format a bank decleration_20230705_0001.pdf15 Feb 2023
Building plan approvalFile: NA ORDER.pdf14 Feb 2023
Layout approvalFile: PLAN.pdf14 Feb 2023
PAN CardFile: PAN CARD.pdf14 Feb 2023
Copy of the legal title reportFile: LEGAL TITILE REPORT_11zon.pdf14 Feb 2023
Details of encumbrances concerned to FinanceFile: ENCUMBRANCES_20230711_0001.pdf14 Feb 2023
Details of encumbrances concerned to FinanceFile: ENCUMBRANCES LEGAL_20230421_0001.pdf14 Feb 2023
Details of encumbrances concerned to LegalFile: ENCUMBRANCES_20230711_0001.pdf14 Feb 2023
Details of encumbrances concerned to LegalFile: ENCUMBRANCES LEGAL_20230421_0001.pdf14 Feb 2023
Copy of Layout Approval (in case of layout)File: PLAN.pdf14 Feb 2023
Building Plan Approval / NA Order for plotted developmentFile: NA ORDER.pdf14 Feb 2023
Commencement Certificates / NA Order for plotted developmentFile: BUILDING PERMISSION.pdf14 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf14 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf14 Feb 2023
Proforma of Agreement for saleFile: AGREEMENT TO SALE_11zon.pdf14 Feb 2023
Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf14 Feb 2023
Deviation Report with respect to Allotment letterFile: NO DEVIATION OF ALLOTMENT TO LETTER_20230711_0001.pdf14 Feb 2023
Deviation Report with respect to model copy of AgreementFile: DEVIATION AGREEMENT TO SALE_20230711_0001.pdf14 Feb 2023

How this compares with Kolhapur

12%of this project is bookeddistrict median 19%
17%of Kolhapur projects moved their completion datethis one moved by 20 months
25%of Kolhapur registrations have lapsed or been cancelledthis one is on the register

Computed across the 880+ Kolhapur projects on ReraGenie, from their own filings.

Keep SHREE SAMARTH HEIGHTS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near GADHINGLAJ880+ in Kolhapur

Builder: SHREE SAMARTH HEIGHTS

SHREE SAMARTH HEIGHTS has 1 registration on MahaRERA, including SHREE SAMARTH HEIGHTS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Kolhapur district page.

Frequently asked questions

What are my rights if SHREE SAMARTH HEIGHTS is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHREE SAMARTH HEIGHTS?

The registered promoter entity is SHREE SAMARTH HEIGHTS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHREE SAMARTH HEIGHTS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHREE SAMARTH HEIGHTS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHREE SAMARTH HEIGHTS?

The professionals named in the filing: Architect: GORULE ARCHITECTS; Engineer: OMKAR VAIJANATH TARALI; Chartered Accountant: SACHHIDANAD SHARAD KULKARNI; Chartered Accountant: MANISH RAMAWATI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHREE SAMARTH HEIGHTS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHREE SAMARTH HEIGHTS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHREE SAMARTH HEIGHTS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.