Home / Browse projects / Kolhapur, Maharashtra / AMEY HI LIFE WING C & D
AMEY HI LIFE WING C & D
By AMEY ESTATES
RG-MH-38217 · RERA PR1151012500763 · Last updated on MahaRERA portal: 14 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 12 months
- 1 extension taken
- Allotment letter deviates from the model form
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- All 6 earlier projects delivered on promise
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Kolhapur registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
AMEY HI LIFE WING C & D is a Residential / Group Housing project by AMEY ESTATES in Kolhapur, Maharashtra, registered with MahaRERA as PR1151012500763 on 11 Sep 2025. Possession is promised by 31 Dec 2032. The completion date has moved by 12 months from the original filing. 0 of the 65 units on this registration are recorded sold or booked, and 0 of 22 construction stages are filed complete.
At a glance
Project
- NameAMEY HI LIFE WING C & D
- TypeResidential / Group Housing
- Location
- Nana Patil Nager
- Kolhapur (M Corp.)
- Karvir
- Kolhapur
- 416010
- Pincode416010
- MapView location on Google Maps (as filed on RERA)
- RERA no.PR1151012500763
- ReraGenie IDRG-MH-38217
Builder
- NameAMEY ESTATES
- Entity typePartnership
- PartnerPRAVIN NISHIKANT NASHTE
- PartnerAMEY PRAVIN NASHTE
- Declared earlier projects6 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on11 Sep 2025
- Promised completion31 Dec 2032
- Revised completionRevised to 31 Dec 2032 (originally 21 Dec 2031)
- Buildings2 building records
- Documents filed16 files
Current status
Figures as on 14 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| AMEY HI LIFE WING C & D | WING C | 7 | 5 | 55 | 0 | 55 |
| AMEY HI LIFE WING C & D | WING D | 7 | 5 | 10 | 0 | 10 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 14 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
0 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Excavation, at 16%.
AMEY HI LIFE WING C & D · wing WING C1%
| Activity | Progress |
|---|---|
| Excavation | 16% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
AMEY HI LIFE WING C & D · wing WING D1%
| Activity | Progress |
|---|---|
| Excavation | 16% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 14 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | 0% |
| Water Supply | No | 10% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | No | 10% |
| Storm Water Drains | No | 0% |
| Landscaping & Tree Planting | No | 0% |
| Street Lighting | No | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | 0% |
| Solid Waste Management And Disposal | No | 0% |
| Water conservation /Rain water harvesting | No | 0% |
| Energy managemcnt | No | 0% |
| Fire protection and fire safety requirements | No | 0% |
| Electrical meter room, sub-station, receiving station | No | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed54
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| AMEY HI LIFE WING C & D WING C | 27 | 27 |
| AMEY HI LIFE WING C & D WING D | 27 | 27 |
Land and ownership5
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Hrushikesh Kavale | Pune (M Corp.) | Pune |
| Girish Shivshankar kattshetti | Others | Belgaum |
| Shivaji Anant kavale | Pune (M Corp.) | Pune |
| Gurudatta Rajiv kavale | Pune (M Corp.) | Pune |
| Kashinath Vasant Kavale | Others | Belgaum |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| AMEY HI LIFE WING C & D | WING C | Rs 19.91 cr | Rs 1.02 cr |
| AMEY HI LIFE WING C & D | WING D | Rs 19.91 cr | Rs 1.02 cr |
| - | NA | Rs 19.91 cr | Rs 1.02 cr |
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | PRASHANT WADANGEKAR |
| Engineer | Prashant S Hadkar |
| Chartered Accountant | Prashant Hirawdekar |
| Partner | Role in project |
|---|---|
| AMEY ESTATES | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe had registered the above-mentioned project on 11/09/2025; however, due to material shortages, labor shortages, and insufficient funding, the construction work could not proceed as planned. We are now planning to resume the project work and complete the construction along with society formation and all other statutory requirements. Therefore, we respectfully request that an extension be granted up to 31/12/2032 to enable us to complete the project in all respects. We assure you that we will make every sincere effort to complete the project within the extended period and comply with all appli
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportNot on the file
A lawyer's report on who owns the land and what is registered against it.
- Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 26 Aug 2025 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 26 Aug 2025 - Commencement CertificateNot on the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
- Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2032
Documents filed16
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: FORM 1.pdf | 14 Jul 2026 |
| Withdrawal Update Form 2File: Form 2 30-06-26 (1).pdf | 14 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 C A 30-06-26 (2).pdf | 14 Jul 2026 |
| Withdrawal Update Form 1File: FORM 1.pdf | 8 Apr 2026 |
| Withdrawal Update Form 2File: Form 2 Engineer 31-03-26.pdf | 8 Apr 2026 |
| Withdrawal Update Form 3File: FORM 3.pdf | 8 Apr 2026 |
| Withdrawal Update Form 1File: Architect Form 1 30092025.pdf | 25 Mar 2026 |
| Withdrawal Update Form 1File: Architect Form 1 31122025.pdf | 25 Mar 2026 |
| Withdrawal Update Form 2File: Form 2 30092025.pdf | 25 Mar 2026 |
| Withdrawal Update Form 2File: Form 2 31122025.pdf | 25 Mar 2026 |
| Withdrawal Update Form 3File: f3.pdf | 25 Mar 2026 |
| Withdrawal Update Form 3File: f3 12.pdf | 25 Mar 2026 |
| Declaration and undertaking (Annexure A)File: Annexure A Undertaking.pdf | 29 Aug 2025 |
| Layout approvalFile: Layout Approval.pdf | 26 Aug 2025 |
| Building plan approvalFile: Building Plan Approval 1.pdf | 26 Aug 2025 |
| Building plan approvalFile: Building Plan Approval 2.pdf | 26 Aug 2025 |
Promoter's earlier projects6
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| AMEY VAIBHAV RESIDANCY | R S NO 262 E WARD PATOLE WADI KOLHAPUR | 4 | Completed | Nov 2016 | Nov 2016 |
| BABASO PATIL VHEELA | CTS NO 17928 TO 17931 SANGLI NAKA ICHALKARANJI | 3 | Completed | Aug 2015 | Aug 2015 |
| AMEY PRASAD | CTS NO 571-1 571-2 E WARD SHAHUPURI KOLHAPUR | 1 | Completed | Feb 2010 | Feb 2010 |
| AMEY TIRTH | E WARD SHAHUPURI KOLHAPUR | 1 | Completed | Jun 2009 | Jun 2009 |
| AMEY PALACE | NAGALA PARK KOLHAPUR | 1 | Completed | Apr 2009 | Apr 2009 |
| AMEY NISARG | NAGALA PARK KOLHAPUR | 1 | Completed | Mar 2008 | Mar 2008 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Kolhapur
Computed across the 880+ Kolhapur projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 16 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep AMEY HI LIFE WING C & D on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Kolhapur (M Corp.)880+ in Kolhapur
Filed coordinates, straight-line distance. 35 registered projects within 2 km.
PRATHAM PRASAD GARDENS
GURUPRASAD DEVELOPERS AND BUILDERS
WESTERN GATEWAY
Harmony Vision
AMEY HI LIFE
AMEY ESTATE
BRAHMANDNAYAK SANKUL
LANDMARK DEVELOPERS
RK S CRYSTAL CROWN
VISION INFRA
ALKA HEIGHTS
Parag Krishnarao Mane
See every Kolhapur project, with the district possession charts
Builder: AMEY ESTATES
AMEY ESTATES has 1 registration on MahaRERA, including AMEY HI LIFE WING C & D. Its filings disclose 6 earlier MahaRERA projects: declares 6 of 6 past projects completed on time. Read the full track record. See more projects on the Kolhapur district page.
Frequently asked questions
What are my rights if AMEY HI LIFE WING C & D is delayed beyond 31 Dec 2032?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of AMEY HI LIFE WING C & D?
The registered promoter entity is AMEY ESTATES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in AMEY HI LIFE WING C & D?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for AMEY HI LIFE WING C & D?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at AMEY HI LIFE WING C & D?
The professionals named in the filing: Architect: PRASHANT WADANGEKAR; Engineer: Prashant S Hadkar; Chartered Accountant: Prashant Hirawdekar. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in AMEY HI LIFE WING C & D?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback