DWARKA EURO
By Randive Builders and Developers
RG-MH-21990 · RERA P53000029821 · Last updated on MahaRERA portal: 20 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 15 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Kolhapur registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
DWARKA EURO is a Others project by Randive Builders and Developers in Kolhapur, Maharashtra, registered with MahaRERA as P53000029821 on 8 Jul 2021. Possession is promised by 31 Mar 2027. The completion date has moved by 15 months from the original filing. 32 of the 98 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete.
At a glance
Project
- NameDWARKA EURO
- TypeOthers
- Location
- Kolhapur Hupari road
- Uchgaon
- Uchgaon (CT)
- Karvir
- Kolhapur
- 416005
- Pincode416005
- MapView location on Google Maps (as filed on RERA)
- RERA no.P53000029821
- ReraGenie IDRG-MH-21990
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on8 Jul 2021
- Promised completion31 Mar 2027
- Revised completionRevised to 31 Mar 2027 (originally 31 Dec 2025)
- Buildings1 building record
- Documents filed114 files
Current status
Figures as on 20 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Dwarka Euro | NA | 10 | 10 | 71 | 27 | 98 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 20 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
9 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 96%.
Dwarka Euro: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 96% |
Progress on shared amenities15
As on 20 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 60% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 20% |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed126
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| EUROTEX INDUSTRIED AND EXPORTS LTD | Mumbai City | Mumbai City |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Dwarka Euro | NA | Rs 10.05 cr | Rs 10.04 cr |
| - | NA | Rs 25.00 lakh | Rs 15.58 lakh |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | GAP Architects and Interior Designers |
| Engineer | Anu Abaji Construction and Swara Consultancy through Ashutosh Powar |
| Chartered Accountant | Shankar Patil and Associates |
| Chartered Accountant | Nitish Vandure Patil and Associates |
| Partner | Role in project |
|---|---|
| Randive Builders and Developers | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe have obtained the revised Building Plan as per UDCPR. Accordingly, the project work is in progress, and therefore, an extension is required for the said purpose
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 3 Jul 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 30 Jun 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 4 Sep 2025 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 28 Jul 2025Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Mar 2027
Documents filed114
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 114 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: form 1.pdf | 20 Jul 2026 |
| Withdrawal Update Form 2File: form 2.pdf | 20 Jul 2026 |
| Withdrawal Update Form 3File: form 3.pdf | 20 Jul 2026 |
| Withdrawal Update Form 1File: form 1.pdf | 6 May 2026 |
| Withdrawal Update Form 2File: 31122025.pdf | 6 May 2026 |
| Withdrawal Update Form 3File: FORM 3_DWARAKA EURO_MAR2026.pdf | 6 May 2026 |
| Form 2A (FY 2025-2026)File: form 2A 31032026.pdf | 30 Apr 2026 |
| Withdrawal Update Form 1File: Architect Certificate 15102025.pdf | 12 Feb 2026 |
| Withdrawal Update Form 1File: Architect Certificate 15102025.pdf | 12 Feb 2026 |
| Withdrawal Update Form 1File: Architect Certificate13012026.pdf | 12 Feb 2026 |
| Withdrawal Update Form 1File: Architect Certificate13012026.pdf | 12 Feb 2026 |
| Withdrawal Update Form 2File: 30092025.pdf | 12 Feb 2026 |
| Withdrawal Update Form 2File: 30092025.pdf | 12 Feb 2026 |
| Withdrawal Update Form 2File: 30092025.pdf | 12 Feb 2026 |
| Withdrawal Update Form 2File: 31122025.pdf | 12 Feb 2026 |
| Withdrawal Update Form 3File: ilovepdf_merged (1).pdf | 12 Feb 2026 |
| Withdrawal Update Form 3File: ilovepdf_merged (1).pdf | 12 Feb 2026 |
| Withdrawal Update Form 3File: ilovepdf_merged.pdf | 12 Feb 2026 |
| Withdrawal Update Form 3File: ilovepdf_merged.pdf | 12 Feb 2026 |
| Building plan approvalFile: Sanctioned Plan 1.pdf | 4 Sep 2025 |
| Building plan approvalFile: Sanctioned Plan 2.pdf | 4 Sep 2025 |
| Building plan approvalFile: Sanctioned Plan 3.pdf | 4 Sep 2025 |
| Building plan approvalFile: Sanctioned Plan 4.pdf | 4 Sep 2025 |
| Withdrawal Update Form 1File: Form 1.pdf | 4 Sep 2025 |
| Withdrawal Update Form 2File: Form 2.pdf | 4 Sep 2025 |
| Withdrawal Update Form 3File: Form 3.pdf | 4 Sep 2025 |
| Withdrawal Update Form 1File: form 1 31-03-23.pdf | 3 Sep 2025 |
| Withdrawal Update Form 1File: Form 1.pdf | 3 Sep 2025 |
| Withdrawal Update Form 2File: form-2 23-24.pdf | 3 Sep 2025 |
| Withdrawal Update Form 2File: Form 2.pdf | 3 Sep 2025 |
| Withdrawal Update Form 3File: Form-3 (7)_compressed.pdf | 3 Sep 2025 |
| Withdrawal Update Form 3File: Form 3.pdf | 3 Sep 2025 |
| Building plan approvalFile: scan0444_compressed.pdf | 28 Jul 2025 |
| Building plan approvalFile: scan0443_compressed.pdf | 28 Jul 2025 |
| Building plan approvalFile: scan0442_compressed.pdf | 28 Jul 2025 |
| Building plan approvalFile: scan0441_compressed.pdf | 28 Jul 2025 |
| Commencement certificateFile: sudharit pramanpatra.pdf | 28 Jul 2025 |
| Form 1File: form 1 31032025.pdf | 26 Jul 2025 |
| Form 2File: form 2 31032025.pdf | 26 Jul 2025 |
| Form 3File: form 3 31032025.pdf | 26 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: sold unsold 31032025.pdf | 26 Jul 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: from 1 december 2024.pdf | 24 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 31122024(1)_compressed.pdf | 24 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: sold unsold 31122024_11zon.pdf | 24 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 31032024-compressed.pdf | 22 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 31122024-compressed.pdf | 22 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: sold unsold 31032020_compressed.pdf | 15 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: sold unsold 31032021_compressed.pdf | 15 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: sold unsold 31032022_compressed.pdf | 15 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: sold unsold 31032023_compressed.pdf | 15 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: sold unsold 31032024_compressed.pdf | 15 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 (7)_compressed.pdf | 1 Aug 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form-5.pdf | 1 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA-Form-3 ( 23-24 )_compressed.pdf | 29 Jul 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: RERA Form-5 ( 23-24 ).pdf | 29 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form-2 23-24.pdf | 20 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Scan form 2A 23-24.pdf | 3 Jul 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: dwarka euro form 5 22-23.pdf | 22 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form_3_31032023 Dwarka Euro.pdf | 3 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 22-23.pdf | 4 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A 22-23.pdf | 4 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA Form 3.pdf | 24 Jul 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: RERA Form 5 21-22.pdf | 24 Jul 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: RERA Form 5 22-23.pdf | 24 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form_3_Dwarka_Euro_11zon.pdf | 6 Jun 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: form 5 21-22_11zon.pdf | 6 Jun 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 31-03-23.pdf | 13 Apr 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1- 01-01-22.pdf | 7 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 31-01-22.pdf | 7 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 1-27-05-22.pdf | 7 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: form 2 A 19-20.pdf | 4 Mar 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: form 2a 20-21.pdf | 4 Mar 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2a 21-22.pdf | 4 Mar 2023 |
| OtherFile: Bank Account for RERA.pdf | 26 Jul 2022 |
| OtherFile: Form B Eurotex.pdf | 22 Dec 2021 |
| Proforma of Allotment letterFile: DWARKA EURO Flat No 107 salokhe-converted.pdf | 27 Oct 2021 |
| Proforma of Allotment letterFile: EIEL-Flat Agreement -.pdf | 27 Oct 2021 |
| Proforma of Allotment letterFile: Letter of intent - Eurotex.pdf | 27 Oct 2021 |
| OtherFile: Supplemrntary Development Agreement -compressed.pdf | 3 Aug 2021 |
| Copy of the legal title reportFile: Search Report.pdf | 3 Jul 2021 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Kolhapur
Computed across the 880+ Kolhapur projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 114 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep DWARKA EURO on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Uchgaon880+ in Kolhapur
Filed coordinates, straight-line distance. 18 registered projects within 2 km.
GATEWAY RESIDENCIES
SIDDHIVINAYAK DEVELOPERS
Suryoday Nagar Layout-B
Suraj Land Developments
Atharva Sky Line Wing-B
Sanjay Prabhakar Kulkarni
PUNYA SHLOK TOWER I AND TOWER II
RAMSINA CONSTRUCTIONS PVT LTD
NOBLE POINT
Masute and Patil Builders
ATHARVA SPANDAN
HEMANT PRABHAKAR KULKARNI
See every Kolhapur project, with the district possession charts
Builder: Randive Builders and Developers
Randive Builders and Developers has 3 registrations on MahaRERA, including GRANDSTAND and DWARKA EURO. Its filings disclose 5 earlier MahaRERA projects: declares 4 of 4 past projects completed on time. Read the full track record. See more projects on the Kolhapur district page.
Frequently asked questions
What are my rights if DWARKA EURO is delayed beyond 31 Mar 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of DWARKA EURO?
The registered promoter entity is Randive Builders and Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in DWARKA EURO?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for DWARKA EURO?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at DWARKA EURO?
The professionals named in the filing: Architect: GAP Architects and Interior Designers; Engineer: Anu Abaji Construction and Swara Consultancy through Ashutosh Powar; Chartered Accountant: Shankar Patil and Associates; Chartered Accountant: Nitish Vandure Patil and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in DWARKA EURO?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback