ReraGenieLog inGet a buyer report

Home / Browse projects / Kolhapur, Maharashtra / HIGHSTREET CBD - TOWER A

Registered No litigation declared Commercial project

HIGHSTREET CBD - TOWER A

By HIGHSTREET DEVELOPERS

RG-MH-38905 · RERA PC1150002502228 · Last updated on MahaRERA portal: 2 May 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 4 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Kolhapur registration emailed to you, free during the pilot beta.
Dec 2031Possession promisedno revision filed
0 of 10Construction stages donefurthest along: Excavation, 40%
481 of 531Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 16 documents Report an error

HIGHSTREET CBD - TOWER A is a Commercial project by HIGHSTREET DEVELOPERS in Kolhapur, Maharashtra, registered with MahaRERA as PC1150002502228 on 2 Feb 2026. Possession is promised by 31 Dec 2031. 50 of the 531 units on this registration are recorded sold or booked, and 0 of 10 construction stages are filed complete.

At a glance

Project

  • NameHIGHSTREET CBD - TOWER A
  • TypeCommercial
  • Location
    • B WARD HOCKEY STADIUM CHOWK
    • KARVEER
    • Kolhapur (M Corp.)
    • Karvir
    • Kolhapur
    • 416007
  • Pincode416007
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PC1150002502228
  • ReraGenie IDRG-MH-38905

Builder

  • NameHIGHSTREET DEVELOPERS
  • Entity typePartnership
  • PartnersAbhijit Mahavir Magdum, Dhananjay Bhimrao Mahadik, Shamlal Amarlal Notani, Shankar Hindurao Patil
  • PartnerSUMIT PRAKASH MEDSHINGE
  • Other registrations4 more →

Key dates

this monthRegisteredFeb 2026PromisedDec 2031

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on2 Feb 2026
  • Promised completion31 Dec 2031
  • Revised completionNone
  • Buildings1 building record
  • Documents filed16 files

Current status

9%50 of 531 units booked
0.7%Work done, per cost certificate

Figures as on 2 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
HIGHSTREET CBD - TOWER ANA1290531531

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 2 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 10 construction stages are filed complete. The stage furthest along is Excavation, at 40%.

HIGHSTREET CBD - TOWER A: 4% average across the applicable activities

ActivityProgress
Excavation40%
Basement (if any)0%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 2 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyNo0%
Sewerage (Chamber, Lines, Septic Tank , STP)No0%
Storm Water DrainsNo0%
Landscaping & Tree PlantingNo0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNo0%
Solid Waste Management And DisposalNo0%
Water conservation /Rain water harvestingNo0%
Energy managemcntNo0%
Fire protection and fire safety requirementsNo0%
Electrical meter room, sub-station, receiving stationNo0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1899

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1,899
Basement1,899

Land and ownership9

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area28,702 sq m
Land owned byNot the promoter
Named landowners9
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on22 Jan 2026
LandownerVillageDistrict
Jyoti Dhananjay SabaneKolhapur (M Corp.)Kolhapur
Shubhananda Balasaheb MaharajKolhapur (M Corp.)Kolhapur
Sunetra Chandrahas PatilKolhapur (M Corp.)Kolhapur
Rashmi Ravikant AphalePune (M Corp.)Pune
Rajesh Balasaheb MaharajKolhapur (M Corp.)Kolhapur
Shankar Hindurao PatilKolhapur (M Corp.)Kolhapur
Sumit Prakash MedshingeKolhapur (M Corp.)Kolhapur
Abhijit Mahavir MagdumKolhapur (M Corp.)Kolhapur
Dhananjay Bhimrao MahadikKolhapur (M Corp.)Kolhapur

Approvals and building plan

Permissible FSI35654.17
Proposed, not sanctioned35,654 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchDIST KOLHAPUR, MAHARASHTRA 416002
Estimated costRs 132.27 cr
Cost incurredRs 92.40 lakh
Work done0.7%
BuildingWingEstimatedIncurred
HIGHSTREET CBD - TOWER ANARs 104.32 crRs 92.40 lakh
-NARs 27.95 cr-

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVISION ASSOCIATE Prashant Kapdi
EngineerDEEPAK B WAGHULE
EngineerABHIJIT ABHIMANYU KUMBHAR
Chartered AccountantSHANKAR PATIL AND ASSOCIATES
Chartered AccountantAmit Madanrao Shinde
PartnerRole in project
HIGHSTREET DEVELOPERS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportNot on the file

    A lawyer's report on who owns the land and what is registered against it.

  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 6 Jan 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 Jan 2026
  4. Commencement CertificateNot on the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2031

Documents filed16

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 - Tower-A.pdf2 May 2026
Withdrawal Update Form 2File: Tower-A-Form 2.pdf2 May 2026
Withdrawal Update Form 3File: Form_3_Tower_A_Highstreet-Developers_31032026.pdf2 May 2026
Form 2A (FY 2025-2026)File: Tower A Form 2-A.pdf2 May 2026
Declaration and undertaking (Annexure A)File: Annexure A - One Plot One Registration.pdf22 Jan 2026
Building plan approvalFile: Plan 7.pdf22 Jan 2026
Layout approvalFile: Final IOD Layout Plan.pdf6 Jan 2026
Layout approvalFile: Final Layout after KJP.pdf6 Jan 2026
Layout approvalFile: Final Layout Mojani Nakasha.pdf6 Jan 2026
Layout approvalFile: Final Layout Sanction Plan.pdf6 Jan 2026
Building plan approvalFile: Tower A-1.pdf6 Jan 2026
Building plan approvalFile: Tower A-2.pdf6 Jan 2026
Building plan approvalFile: Tower A-3.pdf6 Jan 2026
Building plan approvalFile: Tower A-4.pdf6 Jan 2026
Building plan approvalFile: Tower A-5.pdf6 Jan 2026
Building plan approvalFile: Tower A-6.pdf6 Jan 2026

How this compares with Kolhapur

9%of this project is bookeddistrict median 19%
17%of Kolhapur projects moved their completion datethis one has not
25%of Kolhapur registrations have lapsed or been cancelledthis one is on the register

Computed across the 880+ Kolhapur projects on ReraGenie, from their own filings.

Keep HIGHSTREET CBD - TOWER A on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KARVEER880+ in Kolhapur

2 kmHIGHSTREET CBD - TOWER ACompleted 22Lapsed / revoked 9Other 46Dot size: filed unitsN

Filed coordinates, straight-line distance. 77 registered projects within 2 km.

Builder: HIGHSTREET DEVELOPERS

HIGHSTREET DEVELOPERS has 5 registrations on MahaRERA, including HIGHSTREET CBD - TOWER D and HIGHSTREET CBD - TOWER C. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Kolhapur district page.

Frequently asked questions

What are my rights if HIGHSTREET CBD - TOWER A is delayed beyond 31 Dec 2031?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of HIGHSTREET CBD - TOWER A?

The registered promoter entity is HIGHSTREET DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in HIGHSTREET CBD - TOWER A?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for HIGHSTREET CBD - TOWER A?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at HIGHSTREET CBD - TOWER A?

The professionals named in the filing: Architect: VISION ASSOCIATE Prashant Kapdi; Engineer: DEEPAK B WAGHULE; Engineer: ABHIJIT ABHIMANYU KUMBHAR; Chartered Accountant: SHANKAR PATIL AND ASSOCIATES; Chartered Accountant: Amit Madanrao Shinde. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in HIGHSTREET CBD - TOWER A?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About HIGHSTREET CBD - TOWER A. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save HIGHSTREET CBD - TOWER A to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.