Red flags

  • Completion date moved by 30 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Kolhapur registration emailed to you, free during the pilot beta.
Jun 2025Possession promisedregistration recorded completed
41 of 55Construction stages doneacross 5 buildings; furthest along: Internal walls, 95%
50 of 334Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 315 documents Report an error

ELIXA PARK is a Others project by AJAYSINH V DESAI BUILDERS & DEVELOPERS in Kolhapur, Maharashtra, registered with MahaRERA as P53000001735 on 29 Jul 2017. The registration is recorded completed; possession was promised by 30 Jun 2025. The completion date has moved by 30 months from the original filing. 284 of the 334 units on this registration are recorded sold or booked, and 41 of 55 construction stages are filed complete.

At a glance

Project

  • NameELIXA PARK
  • TypeOthers
  • Location
    • Old Pune Bangalore Road
    • ‘E’ Ward
    • Kolhapur (M Corp.)
    • Karvir
    • Kolhapur
    • 416001
  • Pincode416001
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P53000001735
  • ReraGenie IDRG-MH-10676

Builder

  • NameAJAYSINH V DESAI BUILDERS & DEVELOPERS
  • Entity typePartnership
  • PartnersAnjali Ajaysinh Desai, Rahul Radhakrishana Dodiya
  • PArtnerAjaysinh Desai

Key dates

this monthRegisteredJul 2017First promiseDec 2022Revised toJun 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on29 Jul 2017
  • Promised completion30 Jun 2025
  • Revised completionRevised to 30 Jun 2025 (originally 30 Dec 2022)
  • Buildings5 building records
  • Documents filed315 files

Current status

85%284 of 334 units booked

Figures as on 5 Jul 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Commercial BuildingNA14120132132
ARISTO Tower Wing ANA191565065
BLISS Tower Wing BNA191584084
CELEST Tower Wing CNA191528028
IVAA Tower Wing DNA201525025

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building5

As on 5 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

41 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Internal walls, at 95%.

Commercial Building79%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
ARISTO Tower Wing A90%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)90%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BLISS Tower Wing B90%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)90%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
CELEST Tower Wing C90%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)90%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
IVAA Tower Wing D82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 5 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes95%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes90%
Street LightingYes80%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes90%
Electrical meter room, sub-station, receiving stationYes90%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable

Parking filed274

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots274
Closed/Covered274
BuildingClosed/CoveredTotal
Commercial Building124124
ARISTO Tower Wing A3737
BLISS Tower Wing B3737
CELEST Tower Wing C3838
IVAA Tower Wing D3838

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area12,319 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on5 Jul 2025
LandownerVillageDistrict
Ghatge Patil Transports LtdKolhapur (M Corp.)Kolhapur

Approvals and building plan

Sanctioning authorityKolhapur Municipal Corporation
Permissible FSI52577.85
Proposed, not sanctioned52,578 sq m
Buildings approved5
Buildings sanctioned5

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShop No B4-B8 Ground Floor, Royal Prestige, Sykes Extension, City Survey Kolhapur 416001

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectA Square Mr Amar Upadhye
ArchitectMetaphors Mr Anand Bhagat
EngineerShantadurga Consultants Mr Sadanand Sabnis
EngineerDr A B Kulkarni & Associates Mr Pranav Kulkarni
Chartered AccountantV T and Associates
Chartered AccountantSakshi Jaisinghani and Associates
PartnerRole in project
AJAYSINH V DESAI BUILDERS & DEVELOPERS-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT53000013025Dec 2022 → Jun 2024

Reason as filed by the promoterThe promoter is applying for revised sanction of the project by loading amenity TDR on the project. The process of TDR issue is being delayed and it will be completed soon. The Promoter will upload the revised sanctioned plans as soon as it is approved from the Kolhapur Municipal Corporation.

EXT53000024136Dec 2022 → Jun 2025

Reason as filed by the promoterThat the Completion Certificate will be issued by Kolhapur Municipal Corporation after construction of common road and Gutter as per layout Plan and NOC regarding the same. Hence for the said Project needs extension. I request MahaRERA authority please approve extension as eary.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 22 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 22 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 9 Oct 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 14 Oct 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 8 Nov 2023

Documents filed315

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 315 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Form 1.pdf5 Jul 2025
Form 2File: Form 2.pdf5 Jul 2025
Form 3File: Form 3_compressed (63).pdf5 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold Inventory.pdf5 Jul 2025
Form 1File: Form 1.pdf5 Jul 2025
Form 2File: Form 2.pdf5 Jul 2025
Form 3File: Form 3.pdf5 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold Inventory.pdf5 Jul 2025
Occupational CertificateFile: Completion Certificates along with Request Letter.pdf5 Jul 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf11 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf11 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold Inventory_compressed (5).pdf11 Jan 2025
Certificates of CA (Form 3)File: Form 3_compressed (43).pdf11 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf11 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf11 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold Inventory_compressed (5).pdf11 Jan 2025
Certificates of CA (Form 3)File: Form 3_compressed (43).pdf11 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf11 Jan 2025
Certificates of CA (Form 3)File: Form 3_compressed (43).pdf11 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf11 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold Inventory_compressed (5).pdf11 Jan 2025
Details of encumbrancesFile: ilovepdf_merged (2).pdf7 Jan 2025
Certificates of CA (Form 3)File: Form 3_11zon.pdf7 Jan 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A.pdf7 Jan 2025
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B.pdf7 Jan 2025
Details of encumbrancesFile: ilovepdf_merged (2).pdf7 Jan 2025
Certificates of CA (Form 3)File: Form 3_11zon.pdf7 Jan 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A.pdf7 Jan 2025
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B.pdf7 Jan 2025
Details of encumbrancesFile: ilovepdf_merged (2).pdf7 Jan 2025
Certificates of CA (Form 3)File: Form 3_11zon.pdf7 Jan 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A.pdf7 Jan 2025
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B.pdf7 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf22 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf22 Oct 2024
Disclosure of sold/ booked inventoryFile: Sold Inventory.pdf22 Oct 2024
Certificates of CA (Form 3)File: Sold Inventory.pdf22 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf22 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf22 Oct 2024
Disclosure of sold/ booked inventoryFile: Sold Inventory.pdf22 Oct 2024
Certificates of CA (Form 3)File: Sold Inventory.pdf22 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf22 Oct 2024
Certificates of CA (Form 3)File: Sold Inventory.pdf22 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf22 Oct 2024
Disclosure of sold/ booked inventoryFile: Sold Inventory.pdf22 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Elixa Park Form 5.pdf7 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Elixa Park Form 5.pdf7 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Elixa Park Form 5.pdf7 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf13 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf13 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 3 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23) (5).pdf13 Aug 2024
Disclosure of sold/ booked inventoryFile: Sold Inventory_compressed (3).pdf13 Aug 2024
Certificates of CA (Form 3)File: Form 3_compressed (23).pdf13 Aug 2024
Details of encumbrancesFile: Finance Declaration.pdf26 Jun 2024
Details of encumbrancesFile: Mortgage Deed.pdf26 Jun 2024
Declaration in FORM BFile: Form B Declaration.pdf26 Jun 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf26 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf26 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A.pdf26 Apr 2024
Disclosure of sold/ booked inventoryFile: Sold Invenory.pdf26 Apr 2024
Certificates of CA (Form 3)File: Form 3.pdf26 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf3 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf3 Feb 2024
Disclosure of sold/ booked inventoryFile: Sold Inventory.pdf3 Feb 2024
Certificates of CA (Form 3)File: Form 3.pdf3 Feb 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: PART COMPLETION CERTIFICATE 11-10-2023.pdf8 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 2022-23 Elixa.pdf28 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Architect.pdf25 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Engineer.pdf25 Oct 2023
Disclosure of sold/ booked inventoryFile: Sold Inventory.pdf25 Oct 2023
Certificates of CA (Form 3)File: Form 3 - CA.pdf25 Oct 2023
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE_compressed (2).pdf14 Oct 2023
Building plan approvalFile: Built up area Highlighted Plan.pdf9 Oct 2023
Building Plan Approval (IOD)File: Built up area Highlighted Plan.pdf9 Oct 2023
Commencement Certificates / NA Order for plotted developmentFile: Highlighted Commencement Certificate.pdf9 Oct 2023
Disclosure of sold/ booked inventoryFile: sOLD UNSOLD INVENTORY09182023.pdf9 Oct 2023
Building plan approvalFile: 1.pdf18 Sep 2023
Building plan approvalFile: 2.pdf18 Sep 2023
Building plan approvalFile: 3.pdf18 Sep 2023
Building plan approvalFile: 4.pdf18 Sep 2023

How this compares with Kolhapur

85%of this project is bookeddistrict median 19%
17%of Kolhapur projects moved their completion datethis one moved by 30 months
25%of Kolhapur registrations have lapsed or been cancelledthis one is completed

Computed across the 880+ Kolhapur projects on ReraGenie, from their own filings.

Keep ELIXA PARK on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near ‘E’ Ward880+ in Kolhapur

2 kmELIXA PARKCompleted 53Lapsed / revoked 27Other 60Dot size: filed unitsN

Filed coordinates, straight-line distance. 140 registered projects within 2 km.

Builder: AJAYSINH V DESAI BUILDERS & DEVELOPERS

AJAYSINH V DESAI BUILDERS & DEVELOPERS has 1 registration on MahaRERA, including ELIXA PARK. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Kolhapur district page.

Frequently asked questions

What are my rights if ELIXA PARK is delayed beyond 30 Jun 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ELIXA PARK?

The registered promoter entity is AJAYSINH V DESAI BUILDERS & DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ELIXA PARK?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ELIXA PARK?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ELIXA PARK?

The professionals named in the filing: Architect: A Square Mr Amar Upadhye; Architect: Metaphors Mr Anand Bhagat; Engineer: Shantadurga Consultants Mr Sadanand Sabnis; Engineer: Dr A B Kulkarni & Associates Mr Pranav Kulkarni; Chartered Accountant: V T and Associates; Chartered Accountant: Sakshi Jaisinghani and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ELIXA PARK?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ELIXA PARK. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ELIXA PARK to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.