Home / Browse projects / Kolhapur, Maharashtra / Atharva Sky Line Wing-B
Atharva Sky Line Wing-B
RG-MH-14590 · RERA P53000023030 · Last updated on MahaRERA portal: 27 Feb 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 25 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Kolhapur registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Atharva Sky Line Wing-B is a Residential / Group Housing project by Sanjay Prabhakar Kulkarni in Kolhapur, Maharashtra, registered with MahaRERA as P53000023030 on 14 Nov 2019. Possession is promised by 31 Dec 2026. The completion date has moved by 25 months from the original filing. 62 of the 84 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.
At a glance
Project
- NameAtharva Sky Line Wing-B
- TypeResidential / Group Housing
- Location
- E ward
- Ujalaiwadi
- Ujalaiwadi (CT)
- Karvir
- Kolhapur
- 416005
- Pincode416005
- MapView location on Google Maps (as filed on RERA)
- RERA no.P53000023030
- ReraGenie IDRG-MH-14590
Builder
- NameSanjay Prabhakar Kulkarni
- Entity typeIndividual
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on14 Nov 2019
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 29 Nov 2024)
- Buildings1 building record
- Documents filed102 files
Current status
Figures as on 27 Feb 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Atharva Sky Line Wing-B | NA | 14 | 12 | 84 | 0 | 84 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 27 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 99%.
Atharva Sky Line Wing-B: 90% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 99% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 98% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 98% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 98% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 98% |
Progress on shared amenities15
As on 27 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 94% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 97% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 95% |
| Energy managemcnt | Yes | 80% |
| Fire protection and fire safety requirements | Yes | 95% |
| Electrical meter room, sub-station, receiving station | Yes | 97% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed355
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Atharva Sky Line Wing-B | NA | Rs 20.50 cr | Rs 16.26 cr |
| - | NA | Rs 79.00 lakh | - |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Vision Associates Through Prashant Kapdi |
| Engineer | Mukund Sarnaik |
| Chartered Accountant | MMApastamabh & Co |
| Chartered Accountant | Aniruddha Shirasekar and Co |
| Partner | Role in project |
|---|---|
| Sanjay Prabhakar Kulkarni | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterI have applied for Revised sanction for Kolhapur Municipal Corporation. I have completed 98% construction work of my project it will require more time to complete my project and to receive completion certificate from Authority. hence I have applied for extension for one year. we request to authority please grant me extension for one year.
Reason as filed by the promoterI have obtained the Revised Sanctioned Plan dated 11/06/2026 in respect of the said project. Due to certain technical reasons, I will not be able to complete the said project within the stipulated time. I have completed approximately 98% of the construction work of the project; however, additional time is required to complete the project as per the Revised Sanctioned Plan and to obtain the Completion Certificate from the competent Authority. After grant of extension of the project, I shall apply for a correction application as per the Revised Sanctioned Plan. Hence, I have applied for extensio
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 12 Oct 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 12 Oct 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 17 Oct 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 28 Nov 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2026
Documents filed102
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 102 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2024-2025)File: Form 2A - Atharva Skyline.pdf | 27 Feb 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 20 Feb 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 20 Feb 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 20 Feb 2026 |
| Form 1File: Form 1.pdf | 14 Jan 2026 |
| Form 2File: Form 2.pdf | 14 Jan 2026 |
| Form 3File: Form 3.pdf | 14 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory.pdf | 14 Jan 2026 |
| Withdrawal Update Form 1File: Form 1 June.pdf | 14 Jan 2026 |
| Withdrawal Update Form 1File: Form 1 June.pdf | 14 Jan 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 14 Jan 2026 |
| Withdrawal Update Form 2File: Form 2 June.pdf | 14 Jan 2026 |
| Withdrawal Update Form 2File: Form 2 June.pdf | 14 Jan 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 14 Jan 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 14 Jan 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 14 Jan 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 14 Jan 2026 |
| Form 5 (FY 2024-2025)File: Form 5 - 2024-2025.pdf | 14 Jan 2026 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dec.pdf | 21 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Dec.pdf | 10 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 dec_compressed.pdf | 10 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dec.pdf | 10 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Sold unsold inventory dec.pdf | 10 Jan 2025 |
| Declaration in FORM BFile: Form B.pdf | 6 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 6 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3_compressed (7).pdf | 6 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Sold unsold inventory.pdf | 6 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 5.pdf | 6 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 9 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 9 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 9 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 9 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 9 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 9 Aug 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 2023-2024.pdf | 9 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Inventory.pdf | 9 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Inventory.pdf | 9 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Inventory.pdf | 9 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 9 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 9 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 9 Aug 2024 |
| Building plan approvalFile: Graund Besment Floor 1new.pdf | 17 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Graund Besment Floor 1new.pdf | 17 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Form 110102023.pdf | 11 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Form 2 10102023.pdf | 11 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2 A 10102023.pdf | 11 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: Sold Booked Inventory10042023.pdf | 11 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Form 3 10102023.pdf | 11 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 2022-202310042023.pdf | 11 Oct 2023 |
| Building plan approvalFile: HPSC1418.pdf | 14 Jan 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: HPSC1418.pdf | 14 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 19-2005122022.pdf | 5 Dec 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 20-2105122022.pdf | 5 Dec 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 21-2205122022.pdf | 5 Dec 2022 |
| Building plan approvalFile: Graund Besment Floor 1.pdf | 28 Nov 2022 |
| Building plan approvalFile: First Second Floor_compressed.pdf | 28 Nov 2022 |
| Building plan approvalFile: Third Fourth Floor.pdf | 28 Nov 2022 |
| Building plan approvalFile: Fifth Sixth Floor.pdf | 28 Nov 2022 |
| Building plan approvalFile: Seventh Eigth Floor.pdf | 28 Nov 2022 |
| Building plan approvalFile: Eleven Twelve Floor_compressed.pdf | 28 Nov 2022 |
| Building plan approvalFile: Elevation.pdf | 28 Nov 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: Elevation.pdf | 28 Nov 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: Graund Besment Floor 1.pdf | 28 Nov 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: First Second Floor_compressed.pdf | 28 Nov 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: Third Fourth Floor.pdf | 28 Nov 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: Fifth Sixth Floor.pdf | 28 Nov 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: Seventh Eigth Floor.pdf | 28 Nov 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: Eleven Twelve Floor_compressed.pdf | 28 Nov 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: Sudharit Badhakam Parvana.pdf | 28 Nov 2022 |
| Declaration about Commencement CertificateFile: Format D.pdf | 28 Nov 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf | 28 Nov 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 28 Nov 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A.pdf | 28 Nov 2022 |
| Disclosure of sold/ booked inventoryFile: Soldunsold Inventory.pdf | 28 Nov 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Final.pdf | 28 Nov 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Kulkarni.pdf | 22 Dec 2021 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventary Kulkarni.pdf | 22 Dec 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate Vision Associates.pdf | 20 Dec 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate Vision Associates.pdf | 20 Dec 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Vision Associates.pdf | 20 Dec 2021 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Atharva Sunrise | Plot No 10 out of RSNo 4A-1 E Ward Tembalaiwadi Kolhapur | 16 | Completed | Jan 2016 | Nov 2015 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Kolhapur
Computed across the 880+ Kolhapur projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 102 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Atharva Sky Line Wing-B on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Ujalaiwadi880+ in Kolhapur
Filed coordinates, straight-line distance. 26 registered projects within 2 km.
GATEWAY RESIDENCIES
SIDDHIVINAYAK DEVELOPERS
DWARKA EURO
Randive Builders and Developers
Suryoday Nagar Layout-B
Suraj Land Developments
PUNYA SHLOK TOWER I AND TOWER II
RAMSINA CONSTRUCTIONS PVT LTD
NOBLE POINT
Masute and Patil Builders
ATHARVA SPANDAN
HEMANT PRABHAKAR KULKARNI
See every Kolhapur project, with the district possession charts
Builder: Sanjay Prabhakar Kulkarni
Sanjay Prabhakar Kulkarni has 1 registration on MahaRERA, including Atharva Sky Line Wing-B. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Kolhapur district page.
Frequently asked questions
What are my rights if Atharva Sky Line Wing-B is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Atharva Sky Line Wing-B?
The registered promoter entity is Sanjay Prabhakar Kulkarni, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Atharva Sky Line Wing-B?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Atharva Sky Line Wing-B?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Atharva Sky Line Wing-B?
The professionals named in the filing: Architect: Vision Associates Through Prashant Kapdi; Engineer: Mukund Sarnaik; Chartered Accountant: MMApastamabh & Co; Chartered Accountant: Aniruddha Shirasekar and Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Atharva Sky Line Wing-B?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback