Home / Browse projects / Kolhapur, Maharashtra / INDRANAND GREENS

Registered No litigation declared Residential / Group Housing project

INDRANAND GREENS

By Satish Anandrao Ghorpade

RG-MH-26110 · RERA P53000013471 · Last updated on MahaRERA portal: 23 Jul 2025

Source: official MahaRERA filing

Red flags

  • Possession 1 months past the filed date
  • Completion date moved by 57 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Kolhapur registration emailed to you, free during the pilot beta.
Sep 2026Possession promised1 month past this date
9 of 22Construction stages doneacross 2 buildings; furthest along: Internal walls, 95%
32 of 77Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 171 documents Report an error

INDRANAND GREENS is a Residential / Group Housing project by Satish Anandrao Ghorpade in Kolhapur, Maharashtra, registered with MahaRERA as P53000013471 on 7 Oct 2017. Possession was promised by 30 Sep 2026 and is now 1 months past that date. The completion date has moved by 57 months from the original filing. 45 of the 77 units on this registration are recorded sold or booked, and 9 of 22 construction stages are filed complete.

At a glance

Project

  • NameINDRANAND GREENS
  • TypeResidential / Group Housing
  • Location
    • Kolhapur
    • Kolhapur (M Corp.)
    • Karvir
    • 416004
  • Pincode416004
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P53000013471
  • ReraGenie IDRG-MH-26110

Builder

  • NameSatish Anandrao Ghorpade
  • Entity typeIndividual

Key dates

1 months past promisethis monthRegisteredOct 2017First promiseDec 2021Revised toSep 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on7 Oct 2017
  • Promised completion30 Sep 2026
  • Revised completionRevised to 30 Sep 2026 (originally 30 Dec 2021)
  • Buildings2 building records
  • Documents filed171 files

Current status

58%45 of 77 units booked

Figures as on 23 Jul 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building -ANA11038038
Building -BNA5539039

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 23 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 95%.

Building -A87%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.85%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
Building -B57%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor90%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 23 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsYes50%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes50%
Water conservation /Rain water harvestingYes50%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes50%
Electrical meter room, sub-station, receiving stationYes75%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed39

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots39
Closed/Covered29
Open Space10
BuildingClosed/CoveredOpen SpaceTotal
Building -A18018
Building -B111021

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,865 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on24 Jul 2025

Approvals and building plan

Sanctioning authorityKOLHAPUR MUNICIPAL CORPORATION
Permissible FSI9154.58
Proposed, not sanctioned9,155 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchRenuka Sadan E Ward 6th Lane Kolhapur

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMr Gajendra Sabale
EngineerMr Jaysinh Deshamukh
EngineerSnehalata Ghorpade
EngineerShashikant Bajirao Dinde
EngineerSwapnil Anandrao Surve
Chartered AccountantDipak Pore and Associates
Chartered AccountantRavindra S Chavan and Co
PartnerRole in project
Satish Anandrao Ghorpade-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT53000011710Dec 2021 → Mar 2025

Reason as filed by the promoterDue to Revised Plan and market condition we can not complete the project within specified period.

EA28072502226Dec 2021 → Sep 2026

Reason as filed by the promoterAs per New UDCPR Rules I have applied for revised building Plan before Kolhapur Municipal Corporation and for the same reason project will not complete within stipulated time

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Sep 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Sep 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 5 Apr 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 5 Apr 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed171

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 171 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Form 1.pdf23 Jul 2025
Form 2File: Form 2.pdf23 Jul 2025
Form 3File: Form 3.pdf23 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold Inventory.pdf23 Jul 2025
Form 1File: FORM 1 DEC 24.pdf23 Jul 2025
Form 2File: FORM 2 DEC 24.pdf23 Jul 2025
Form 3File: FORM 3 DEC 24.pdf23 Jul 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD DEC 24.pdf23 Jul 2025
Form 1File: FORM 1 SEPT 24.pdf23 Jul 2025
Form 2File: FORM 2 SEPT 24.pdf23 Jul 2025
Form 3File: FORM 3 SEPT 24.pdf23 Jul 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD SEPT 24.pdf23 Jul 2025
Form 1File: FORM 1 JUNE 24.pdf23 Jul 2025
Form 2File: FORM 2 JUNE 24.pdf23 Jul 2025
Form 3File: FORM 3 JUNE 24.pdf23 Jul 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD JUNE 24.pdf23 Jul 2025
Form 1File: FORM 1 MARCH 24.pdf23 Jul 2025
Form 2File: FORM 2 MARCH 24.pdf23 Jul 2025
Form 3File: FORM 3 MARCH 24.pdf23 Jul 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD MARCH 24.pdf23 Jul 2025
Form 1File: FORM 1 DEC 2023.pdf23 Jul 2025
Form 2File: FORM 2 DEC 2023.pdf23 Jul 2025
Form 3File: FORM 3 DEC 2023.pdf23 Jul 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD DEC 2023.pdf23 Jul 2025
Form 1File: FORM 1 SEPT 2023.pdf23 Jul 2025
Form 2File: FORM 2 SEPT 2023.pdf23 Jul 2025
Form 3File: FORM 3 SEPT 2023.pdf23 Jul 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD SEPT 2023.pdf23 Jul 2025
Form 1File: FORM 1 JUNE 2023.pdf23 Jul 2025
Form 2File: FORM 2 JUNE 2023.pdf23 Jul 2025
Form 3File: FORM 3 JUNE 2023.pdf23 Jul 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD JUNE 2023.pdf23 Jul 2025
Form 1File: Architect Certificate10062023.pdf23 Jul 2025
Form 2File: Engineer Certificate10062023.pdf23 Jul 2025
Form 3File: CA Certificate Form 310062023.pdf23 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold Booked Inventory.pdf23 Jul 2025
OthersFile: Form 2A10062023.pdf23 Jul 2025
Form 1File: Architect Certificate10062023.pdf23 Jul 2025
Form 2File: EngineerCertificate10062023.pdf23 Jul 2025
Form 3File: CA Certificate Form 310062023.pdf23 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold Booked Inventory.pdf23 Jul 2025
Form 1File: Architect Certificate10062023.pdf23 Jul 2025
Form 2File: Engineer Certificate10062023.pdf23 Jul 2025
Form 3File: CA Certificate Form 310062023.pdf23 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold Booked Inventory.pdf23 Jul 2025
Form 1File: Architect Certificate.pdf23 Jul 2025
Form 2File: Engineer Certificate.pdf23 Jul 2025
Form 3File: CA Certificate Form 3.pdf23 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold Booked Inventory.pdf23 Jul 2025
Form 1File: Architect Certificate.pdf23 Jul 2025
Form 2File: Engineer Certificate.pdf23 Jul 2025
Form 3File: CA Certificate Form 3.pdf23 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold Booked Inventory.pdf23 Jul 2025
OthersFile: Form 2A.pdf23 Jul 2025
Form 2A (FY 2024-2025)File: Form 2A - 2024-2025.pdf23 Jul 2025
Form 2A (FY 2023-2024)File: Form 2A - 2023-2024.pdf23 Jul 2025
Form 2A (FY 2022-2023)File: Form 2A - 2022-2023.pdf23 Jul 2025
Form 2A (FY 2021-2022)File: Form 2A - 2021-2022.pdf23 Jul 2025
Form 2A (FY 2020-2021)File: Form 2A - 2020-2021.pdf23 Jul 2025
Form 2A (FY 2019-2020)File: Form 2A - 2019-2020.pdf23 Jul 2025
Form 5 (FY 2024-2025)File: Form 5 - 2024-2025.pdf23 Jul 2025
Form 5 (FY 2023-2024)File: Form 5 - 2023-2024.pdf23 Jul 2025
Form 5 (FY 2022-2023)File: Form 5 - 2022-2023.pdf23 Jul 2025
Form 5 (FY 2021-2022)File: Form 5 - 2021 -2022.pdf23 Jul 2025
Form 5 (FY 2020-2021)File: Form 5 - 2020-2021.pdf23 Jul 2025
Form 5 (FY 2019-2020)File: Form 5 - 2019-2020.pdf23 Jul 2025
Form 5 (FY 2018-2019)File: Form 5 - 2018-2019.pdf23 Jul 2025
Form 5 (FY 2017-2018)File: Form 5 - 2017-2018.pdf23 Jul 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 SEPT 2023.pdf29 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 DEC 2023.pdf29 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 MARCH 24.pdf29 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 JUNE 24.pdf29 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 SEPT 24.pdf29 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 DEC 24.pdf29 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 JUNE 2023.pdf29 Mar 2025
Certificates of CA (Form 3)File: FORM 3 DEC 2023.pdf29 Mar 2025
Certificates of CA (Form 3)File: FORM 3 DEC 24.pdf29 Mar 2025
Certificates of CA (Form 3)File: FORM 3 SEPT 24.pdf29 Mar 2025
Certificates of CA (Form 3)File: FORM 3 JUNE 24.pdf29 Mar 2025
Certificates of CA (Form 3)File: FORM 3 MARCH 24.pdf29 Mar 2025

How this compares with Kolhapur

58%of this project is bookeddistrict median 19%
17%of Kolhapur projects moved their completion datethis one moved by 57 months
25%of Kolhapur registrations have lapsed or been cancelledthis one is on the register

Computed across the 880+ Kolhapur projects on ReraGenie, from their own filings.

Keep INDRANAND GREENS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kolhapur880+ in Kolhapur

2 kmINDRANAND GREENSCompleted 19Lapsed / revoked 10Other 38Dot size: filed unitsN

Filed coordinates, straight-line distance. 67 registered projects within 2 km.

Builder: Satish Anandrao Ghorpade

Satish Anandrao Ghorpade has 1 registration on MahaRERA, including INDRANAND GREENS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Kolhapur district page.

Frequently asked questions

What are my rights if INDRANAND GREENS is delayed beyond 30 Sep 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of INDRANAND GREENS?

The registered promoter entity is Satish Anandrao Ghorpade, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in INDRANAND GREENS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for INDRANAND GREENS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at INDRANAND GREENS?

The professionals named in the filing: Architect: Mr Gajendra Sabale; Engineer: Mr Jaysinh Deshamukh; Engineer: Snehalata Ghorpade; Engineer: Shashikant Bajirao Dinde; Engineer: Swapnil Anandrao Surve; Chartered Accountant: Dipak Pore and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in INDRANAND GREENS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About INDRANAND GREENS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save INDRANAND GREENS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.