Home / Browse projects / Kolhapur, Maharashtra / SHAMRAO SHELKE COMMERCIAL AND RESIDENTIAL COMPLEX
SHAMRAO SHELKE COMMERCIAL AND RESIDENTIAL COMPLEX
By TRIVENI INFRAPROJECT PVT LTD
RG-MH-20640 · RERA P53000005181 · Last updated on MahaRERA portal: 25 Aug 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 4 complaints at MahaRERA
- Completion date moved by 86 months
- 3 extensions taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Kolhapur registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SHAMRAO SHELKE COMMERCIAL AND RESIDENTIAL COMPLEX is a Commercial project by TRIVENI INFRAPROJECT PVT LTD in Kolhapur, Maharashtra, registered with MahaRERA as P53000005181 on 10 Aug 2017. Possession is promised by 30 Sep 2028. The completion date has moved by 86 months from the original filing. 131 of the 257 units on this registration are recorded sold or booked, and 41 of 77 construction stages are filed complete. 4 complaints are on record with the regulator.
At a glance
Project
- NameSHAMRAO SHELKE COMMERCIAL AND RESIDENTIAL COMPLEX
- TypeCommercial
- Location
- BAMBAWADE
- Bambavade
- Shahuwadi
- Kolhapur
- 416015
- Pincode416015
- MapView location on Google Maps (as filed on RERA)
- RERA no.P53000005181
- ReraGenie IDRG-MH-20640
Builder
- NameTRIVENI INFRAPROJECT PVT LTD
- Entity typeCompany
- DirectorsPravin Ramrao Ghadge, Nitin Dattatray Kumbhar
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on10 Aug 2017
- Promised completion30 Sep 2028
- Revised completionRevised to 30 Sep 2028 (originally 30 Jul 2021)
- Buildings7 building records
- Documents filed211 files
Current status
Figures as on 25 Aug 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BUILDING A | NA | 1 | 0 | 0 | 11 | 11 |
| BUILDING B | NA | 5 | 0 | 13 | 21 | 34 |
| BUILDING C | NA | 5 | 0 | 18 | 54 | 72 |
| BUILDING D | NA | 1 | 0 | 0 | 12 | 12 |
| BUILDING E | NA | 5 | 0 | 22 | 44 | 66 |
| BUILDING F | NA | 6 | 0 | 39 | 23 | 62 |
| BUILDING G | NA | 1 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building7
As on 25 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
41 of 77 construction stages are filed complete across 7 buildings. The stage furthest along is Slabs of Super Structure, at 90%.
BUILDING A27%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING B91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUILDING C58%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 75% |
| Sanitary Fittings within the flats / premises | 25% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 20% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 10% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 10% |
BUILDING D91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUILDING E91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUILDING F43%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 90% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 45% |
| Sanitary Fittings within the flats / premises | 10% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 10% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 10% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 10% |
BUILDING G0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 25 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 90% |
| Water Supply | Yes | 40% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 60% |
| Storm Water Drains | Yes | 80% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 40% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 50% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 50% |
| Electrical meter room, sub-station, receiving station | Yes | 50% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed1
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| BUILDING F | NA | Rs 5.80 cr | Rs 2.79 cr |
| BUILDING C | NA | Rs 5.59 cr | Rs 3.72 cr |
| BUILDING E | NA | Rs 3.56 cr | Rs 3.56 cr |
| BUILDING B | NA | Rs 2.18 cr | Rs 2.18 cr |
| - | NA | Rs 93.16 lakh | Rs 45.00 lakh |
| BUILDING A | NA | Rs 26.45 lakh | Rs 26.45 lakh |
| BUILDING D | NA | Rs 22.87 lakh | Rs 22.87 lakh |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | ANIRUDH SAWANT & ASSOCIATES |
| Engineer | MAHENDRA AJIT PATIL |
| Chartered Accountant | CHETAN PATIL |
| Chartered Accountant | SHANKAR VITTHAL PATIL |
| Chartered Accountant | Amit Madanrao Shinde |
| Partner | Role in project |
|---|---|
| TRIVENI INFRAPROJECT PVT LTD | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe project is under lockdown since March 2020 due to COVID-19 pandemic situation. All construction activity on site is stopped as there is lockdown in Kolhapur District and Disaster Management Act is implemented and there is ban on carrying out construction activity as per order of District Magistrate. We have also submitted part completion proposal sanction to concerned sanctioning authority but as government offices are not working in full capacity approval is pending. So we need time extension till July 2022.
Reason as filed by the promoterWe, TRIVENI INFRA PROJECT PVT. LTD. promoter of the ongoing propject SHAMRAO SHELKE COMMERCIAL AND RESIDENCIAL COMPLEX. MahaRERA Registration No. P53000005181. We have registered our project in 2017 of building A,B,C,D,E,F and G. We have completed Building E and building B and received part occupancy certificate in this regard and it is uploaded in tab on portal. Meanwhile one of the director had committed fraud with company and we completed the procedure of removal that fraudulent director from the company. It was the time consuming process. The effect of this consequence the construction of
Reason as filed by the promoterAfter restarting the project, the Promoter has faced financial constraints due to inadequate customer bookings and shortage of funds for completion of the balance construction. The Promoter has also applied for project finance/loan; however, the same has not yet been sanctioned. Consequently, the construction could not progress as per the expected schedule. The Promoter is committed to completing the remaining project and therefore respectfully requests MahaRERA to grant extension of the project completion date up to 30/09/2028. The Promoter assures timely compliance and regular project update
Complaints filed with MahaRERA4
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000064813 | The Kolhapur Urban Coop Bank Ltd | Triveni Infraproject Pvt Ltd | 07/11/2020 |
| CC005000000187979 | AMMIT ASHOKRAO JADHAV | PRAVIN RAMRAO GHADGE | 23/12/2022 |
| CC005000000258897 | Vitthal Powar | TRIVENI INFRA PROJECT PVT LTD CO | 04/09/2023 |
| CC12502187 | Manoj sachanand Ahuja | TRIVENI INFRAPROJECT PVT LTD | 01/07/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 5 Jul 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 29 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 22 Feb 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 22 Feb 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 13 Jan 2024
Documents filed211
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 211 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form_1_Architect_Certificate_30062026.pdf | 25 Aug 2026 |
| Withdrawal Update Form 2File: Form_2_Engineer_Certificate_30062026.pdf | 25 Aug 2026 |
| Withdrawal Update Form 3File: Form_3_Triveni_Infra_30062026.pdf | 25 Aug 2026 |
| Form 2A (FY 2025-2026)File: Form 2A (1).pdf | 7 Aug 2026 |
| Form 5 (FY 2024-2025)File: Form 5 Trivani Infra Projects with Annexure.pdf | 4 Aug 2026 |
| Form 5 (FY 2025-2026)File: Annexure_A_Triveni_Infra with Annexure.pdf | 4 Aug 2026 |
| Form 5 (FY 2021-2022)File: Form 5 FY 21-22.pdf | 16 Jul 2026 |
| Form 5 (FY 2022-2023)File: Form 5 FY 22-23.pdf | 16 Jul 2026 |
| Form 5 (FY 2023-2024)File: Form 5 FY 23-24.pdf | 16 Jul 2026 |
| Withdrawal Update Form 1File: Form_1_March_26.pdf | 14 Jul 2026 |
| Withdrawal Update Form 1File: Form_1_March_26.pdf | 14 Jul 2026 |
| Withdrawal Update Form 2File: Form_2_March_26.pdf | 14 Jul 2026 |
| Withdrawal Update Form 2File: Form_2_March_26.pdf | 14 Jul 2026 |
| Withdrawal Update Form 3File: Form_3_Mar_2026.pdf | 14 Jul 2026 |
| Withdrawal Update Form 3File: Form_3_Mar_2026.pdf | 14 Jul 2026 |
| Withdrawal Update Form 1File: Form_1_June_25.pdf | 20 Jun 2026 |
| Withdrawal Update Form 1File: Form_1_Sep_25.pdf | 20 Jun 2026 |
| Withdrawal Update Form 1File: Form_1_Dec_25.pdf | 20 Jun 2026 |
| Withdrawal Update Form 1File: Form_1_March_26.pdf | 20 Jun 2026 |
| Withdrawal Update Form 2File: Form_2_June_25.pdf | 20 Jun 2026 |
| Withdrawal Update Form 2File: Form_2_September_25.pdf | 20 Jun 2026 |
| Withdrawal Update Form 2File: Form_2_December_25.pdf | 20 Jun 2026 |
| Withdrawal Update Form 2File: Form_2_March_26.pdf | 20 Jun 2026 |
| Withdrawal Update Form 3File: Form3_Jun_2025.pdf | 20 Jun 2026 |
| Withdrawal Update Form 3File: Form_3_SEP_2025.pdf | 20 Jun 2026 |
| Withdrawal Update Form 3File: Form3_Dec_2025.pdf | 20 Jun 2026 |
| Withdrawal Update Form 3File: Form_3_Mar_2026.pdf | 20 Jun 2026 |
| Form 1File: Form_1_Architect_Certificate.pdf | 5 Jun 2026 |
| Form 2File: Withdrawal Application Form 2.pdf | 5 Jun 2026 |
| Form 3File: Form_3_Triveni_Infra_31032025.pdf | 5 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Form_3_Triveni_Infra_31032025.pdf | 5 Jun 2026 |
| Withdrawal Update Form 1File: Form_1_Architect_Certificate.pdf | 5 Jun 2026 |
| Withdrawal Update Form 1File: Form_1_Architect_Certificate.pdf | 5 Jun 2026 |
| Withdrawal Update Form 2File: Withdrawal Application Form 2.pdf | 5 Jun 2026 |
| Withdrawal Update Form 2File: Withdrawal Application Form 2.pdf | 5 Jun 2026 |
| Withdrawal Update Form 3File: Form_3_Triveni_Infra_31032025.pdf | 5 Jun 2026 |
| Withdrawal Update Form 3File: Form_3_Triveni_Infra_31032025.pdf | 5 Jun 2026 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form_1_Architect_ Certificate.pdf | 13 Mar 2025 |
| Certificates of CA (Form 3)File: Form_3_Dec_24_Triveni_1_5.pdf | 13 Mar 2025 |
| Certificates of CA (Form 3)File: Form_3_Dec_24_Triveni_5_10.pdf | 13 Mar 2025 |
| Certificates of CA (Form 3)File: Form_3_Dec_24_Triveni_10_15.pdf | 13 Mar 2025 |
| Certificates of CA (Form 3)File: Form_3_Dec_24_Triveni_15_20.pdf | 13 Mar 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form_2_Engineers_ Certificate.pdf | 13 Mar 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate 31032023.pdf | 6 May 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate 31032024.pdf | 6 May 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf | 4 May 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate.pdf | 3 May 2024 |
| Certificates of CA (Form 3)File: Form 3 - 21-22-1-5.pdf | 3 May 2024 |
| Certificates of CA (Form 3)File: Form 3 - 21-22-6-10.pdf | 3 May 2024 |
| Certificates of CA (Form 3)File: Form 3 - 21-22-11-15.pdf | 3 May 2024 |
| Certificates of CA (Form 3)File: Form 3 - 21-22-16-20.pdf | 3 May 2024 |
| Certificates of CA (Form 3)File: Form 3- 22-23_merged_removed-1-5.pdf | 3 May 2024 |
| Certificates of CA (Form 3)File: Form 3- 22-23_merged_removed-6-10.pdf | 3 May 2024 |
| Certificates of CA (Form 3)File: Form 3- 22-23_merged_removed-11-15.pdf | 3 May 2024 |
| Certificates of CA (Form 3)File: Form 3- 22-23_merged_removed-16-20.pdf | 3 May 2024 |
| Certificates of CA (Form 3)File: Form 3 - 23-24-1-5.pdf | 3 May 2024 |
| Certificates of CA (Form 3)File: Form 3 - 23-24-6-10.pdf | 3 May 2024 |
| Certificates of CA (Form 3)File: Form 3 - 23-24-11-15.pdf | 3 May 2024 |
| Certificates of CA (Form 3)File: Form 3 - 23-24-16-20.pdf | 3 May 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 FY 21-22.pdf | 3 May 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 FY 22-23.pdf | 3 May 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 FY 23-24.pdf | 3 May 2024 |
| Certificates of CA (Form 3)File: ca certificate march 2022 01.pdf | 19 Apr 2024 |
| Certificates of CA (Form 3)File: ca certificate march 2022 03.pdf | 19 Apr 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: ca certificate march 2022 02.pdf | 19 Apr 2024 |
| Status of ConveyanceFile: Sale deed Index.pdf | 16 Apr 2024 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Declaration index.pdf | 19 Mar 2024 |
| Building plan approvalFile: Scan20220530133004.pdf | 22 Feb 2024 |
| Building plan approvalFile: A BUILDING_11zon.pdf | 22 Feb 2024 |
| Building plan approvalFile: B BUILDING_11zon.pdf | 22 Feb 2024 |
| Building plan approvalFile: C-1 BUILDG_11zon.pdf | 22 Feb 2024 |
| Building plan approvalFile: C-2 BUILDING_11zon.pdf | 22 Feb 2024 |
| Building plan approvalFile: D BUILDING_11zon.pdf | 22 Feb 2024 |
| Building plan approvalFile: E BUILDING_11zon.pdf | 22 Feb 2024 |
| Building plan approvalFile: E-2 BUILDING_11zon.pdf | 22 Feb 2024 |
| Building plan approvalFile: F-1 BUILDING_11zon.pdf | 22 Feb 2024 |
| Building plan approvalFile: F-2 BUILDING_11zon.pdf | 22 Feb 2024 |
| Building plan approvalFile: G BUILDING_11zon.pdf | 22 Feb 2024 |
| Building plan approvalFile: SITE PLAN_compressed.pdf | 22 Feb 2024 |
| Details of encumbrances concerned to FinanceFile: Concern To Letter.pdf | 22 Feb 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Kolhapur
Computed across the 880+ Kolhapur projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 211 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep SHAMRAO SHELKE COMMERCIAL AND RESIDENTIAL CO on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near BAMBAWADE880+ in Kolhapur
HIGHSTREET CBD - TOWER A
HIGHSTREET DEVELOPERS
ELIXA PARK
AJAYSINH V DESAI BUILDERS & DEVELOPERS
GATEWAY RESIDENCIES
SIDDHIVINAYAK DEVELOPERS
24 KEYWEST EAST AND WEST AVENUE
KEYWEST INFRA
PRATHAM PRASAD GARDENS
GURUPRASAD DEVELOPERS AND BUILDERS
Loknagari Karande Mala
VIKESH ABHAYKUMAR OSWAL
See every Kolhapur project, with the district possession charts
Builder: TRIVENI INFRAPROJECT PVT LTD
TRIVENI INFRAPROJECT PVT LTD has 1 registration on MahaRERA, including SHAMRAO SHELKE COMMERCIAL AND RESIDENTIAL COMPLEX. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Kolhapur district page.
Frequently asked questions
What are my rights if SHAMRAO SHELKE COMMERCIAL AND RESIDENTIAL COMPLEX is delayed beyond 30 Sep 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SHAMRAO SHELKE COMMERCIAL AND RESIDENTIAL COMPLEX?
The registered promoter entity is TRIVENI INFRAPROJECT PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SHAMRAO SHELKE COMMERCIAL AND RESIDENTIAL COMPLEX?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against SHAMRAO SHELKE COMMERCIAL AND RESIDENTIAL COMPLEX?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for SHAMRAO SHELKE COMMERCIAL AND RESIDENTIAL COMPLEX?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SHAMRAO SHELKE COMMERCIAL AND RESIDENTIAL COMPLEX?
The professionals named in the filing: Architect: ANIRUDH SAWANT & ASSOCIATES; Engineer: MAHENDRA AJIT PATIL; Chartered Accountant: CHETAN PATIL; Chartered Accountant: SHANKAR VITTHAL PATIL; Chartered Accountant: Amit Madanrao Shinde. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SHAMRAO SHELKE COMMERCIAL AND RESIDENTIAL COMPLEX?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.