Home / Browse projects / Kolhapur, Maharashtra / SHAMRAO SHELKE COMMERCIAL AND RESIDENTIAL COMPLEX

Registered No litigation declared Commercial project

SHAMRAO SHELKE COMMERCIAL AND RESIDENTIAL COMPLEX

By TRIVENI INFRAPROJECT PVT LTD

RG-MH-20640 · RERA P53000005181 · Last updated on MahaRERA portal: 25 Aug 2026

Source: official MahaRERA filing

Red flags

  • 4 complaints at MahaRERA
  • Completion date moved by 86 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Kolhapur registration emailed to you, free during the pilot beta.
Sep 2028Possession promisedmoved 86 months from the original
41 of 77Construction stages doneacross 7 buildings; furthest along: Slabs of Super Structure, 90%
126 of 257Units unsoldnot recorded sold or booked
4Complaints at MahaRERAon this registration
Jump to the 211 documents Report an error

SHAMRAO SHELKE COMMERCIAL AND RESIDENTIAL COMPLEX is a Commercial project by TRIVENI INFRAPROJECT PVT LTD in Kolhapur, Maharashtra, registered with MahaRERA as P53000005181 on 10 Aug 2017. Possession is promised by 30 Sep 2028. The completion date has moved by 86 months from the original filing. 131 of the 257 units on this registration are recorded sold or booked, and 41 of 77 construction stages are filed complete. 4 complaints are on record with the regulator.

At a glance

Project

  • NameSHAMRAO SHELKE COMMERCIAL AND RESIDENTIAL COMPLEX
  • TypeCommercial
  • Location
    • BAMBAWADE
    • Bambavade
    • Shahuwadi
    • Kolhapur
    • 416015
  • Pincode416015
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P53000005181
  • ReraGenie IDRG-MH-20640

Builder

  • NameTRIVENI INFRAPROJECT PVT LTD
  • Entity typeCompany
  • DirectorsPravin Ramrao Ghadge, Nitin Dattatray Kumbhar

Key dates

this monthRegisteredAug 2017First promiseJul 2021Revised toSep 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on10 Aug 2017
  • Promised completion30 Sep 2028
  • Revised completionRevised to 30 Sep 2028 (originally 30 Jul 2021)
  • Buildings7 building records
  • Documents filed211 files

Current status

51%131 of 257 units booked
71.1%Work done, per cost certificate

Figures as on 25 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING ANA1001111
BUILDING BNA50132134
BUILDING CNA50185472
BUILDING DNA1001212
BUILDING ENA50224466
BUILDING FNA60392362
BUILDING GNA10000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building7

As on 25 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

41 of 77 construction stages are filed complete across 7 buildings. The stage furthest along is Slabs of Super Structure, at 90%.

BUILDING A27%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING B91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUILDING C58%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises75%
Sanitary Fittings within the flats / premises25%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks20%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.10%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
BUILDING D91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUILDING E91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUILDING F43%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure90%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises45%
Sanitary Fittings within the flats / premises10%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.10%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
BUILDING G0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 25 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes90%
Water SupplyYes40%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes60%
Storm Water DrainsYes80%
Landscaping & Tree PlantingYes0%
Street LightingYes40%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes50%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes50%
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area10,701 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on26 Feb 2026

Approvals and building plan

Permissible FSI21557.54
Proposed, not sanctioned10,779 sq m
Buildings approved7
Buildings sanctioned7

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBAMBAWADE TALUKA SHAHUWADI DISTRICT KOLHAPUR
Estimated costRs 18.56 cr
Cost incurredRs 13.19 cr
Work done71.1%
BuildingWingEstimatedIncurred
BUILDING FNARs 5.80 crRs 2.79 cr
BUILDING CNARs 5.59 crRs 3.72 cr
BUILDING ENARs 3.56 crRs 3.56 cr
BUILDING BNARs 2.18 crRs 2.18 cr
-NARs 93.16 lakhRs 45.00 lakh
BUILDING ANARs 26.45 lakhRs 26.45 lakh
BUILDING DNARs 22.87 lakhRs 22.87 lakh

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectANIRUDH SAWANT & ASSOCIATES
EngineerMAHENDRA AJIT PATIL
Chartered AccountantCHETAN PATIL
Chartered AccountantSHANKAR VITTHAL PATIL
Chartered AccountantAmit Madanrao Shinde
PartnerRole in project
TRIVENI INFRAPROJECT PVT LTD-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT53000010288Jul 2021 → Jul 2022

Reason as filed by the promoterThe project is under lockdown since March 2020 due to COVID-19 pandemic situation. All construction activity on site is stopped as there is lockdown in Kolhapur District and Disaster Management Act is implemented and there is ban on carrying out construction activity as per order of District Magistrate. We have also submitted part completion proposal sanction to concerned sanctioning authority but as government offices are not working in full capacity approval is pending. So we need time extension till July 2022.

EXT53000018901Jul 2021 → Mar 2026

Reason as filed by the promoterWe, TRIVENI INFRA PROJECT PVT. LTD. promoter of the ongoing propject SHAMRAO SHELKE COMMERCIAL AND RESIDENCIAL COMPLEX. MahaRERA Registration No. P53000005181. We have registered our project in 2017 of building A,B,C,D,E,F and G. We have completed Building E and building B and received part occupancy certificate in this regard and it is uploaded in tab on portal. Meanwhile one of the director had committed fraud with company and we completed the procedure of removal that fraudulent director from the company. It was the time consuming process. The effect of this consequence the construction of

EA08082622062Jul 2021 → Sep 2028

Reason as filed by the promoterAfter restarting the project, the Promoter has faced financial constraints due to inadequate customer bookings and shortage of funds for completion of the balance construction. The Promoter has also applied for project finance/loan; however, the same has not yet been sanctioned. Consequently, the construction could not progress as per the expected schedule. The Promoter is committed to completing the remaining project and therefore respectfully requests MahaRERA to grant extension of the project completion date up to 30/09/2028. The Promoter assures timely compliance and regular project update

Complaints filed with MahaRERA4

Case no.ComplainantRespondentFiled
CC005000000064813The Kolhapur Urban Coop Bank LtdTriveni Infraproject Pvt Ltd07/11/2020
CC005000000187979AMMIT ASHOKRAO JADHAVPRAVIN RAMRAO GHADGE23/12/2022
CC005000000258897Vitthal PowarTRIVENI INFRA PROJECT PVT LTD CO04/09/2023
CC12502187Manoj sachanand AhujaTRIVENI INFRAPROJECT PVT LTD01/07/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 5 Jul 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 Feb 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 22 Feb 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 13 Jan 2024

Documents filed211

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 211 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form_1_Architect_Certificate_30062026.pdf25 Aug 2026
Withdrawal Update Form 2File: Form_2_Engineer_Certificate_30062026.pdf25 Aug 2026
Withdrawal Update Form 3File: Form_3_Triveni_Infra_30062026.pdf25 Aug 2026
Form 2A (FY 2025-2026)File: Form 2A (1).pdf7 Aug 2026
Form 5 (FY 2024-2025)File: Form 5 Trivani Infra Projects with Annexure.pdf4 Aug 2026
Form 5 (FY 2025-2026)File: Annexure_A_Triveni_Infra with Annexure.pdf4 Aug 2026
Form 5 (FY 2021-2022)File: Form 5 FY 21-22.pdf16 Jul 2026
Form 5 (FY 2022-2023)File: Form 5 FY 22-23.pdf16 Jul 2026
Form 5 (FY 2023-2024)File: Form 5 FY 23-24.pdf16 Jul 2026
Withdrawal Update Form 1File: Form_1_March_26.pdf14 Jul 2026
Withdrawal Update Form 1File: Form_1_March_26.pdf14 Jul 2026
Withdrawal Update Form 2File: Form_2_March_26.pdf14 Jul 2026
Withdrawal Update Form 2File: Form_2_March_26.pdf14 Jul 2026
Withdrawal Update Form 3File: Form_3_Mar_2026.pdf14 Jul 2026
Withdrawal Update Form 3File: Form_3_Mar_2026.pdf14 Jul 2026
Withdrawal Update Form 1File: Form_1_June_25.pdf20 Jun 2026
Withdrawal Update Form 1File: Form_1_Sep_25.pdf20 Jun 2026
Withdrawal Update Form 1File: Form_1_Dec_25.pdf20 Jun 2026
Withdrawal Update Form 1File: Form_1_March_26.pdf20 Jun 2026
Withdrawal Update Form 2File: Form_2_June_25.pdf20 Jun 2026
Withdrawal Update Form 2File: Form_2_September_25.pdf20 Jun 2026
Withdrawal Update Form 2File: Form_2_December_25.pdf20 Jun 2026
Withdrawal Update Form 2File: Form_2_March_26.pdf20 Jun 2026
Withdrawal Update Form 3File: Form3_Jun_2025.pdf20 Jun 2026
Withdrawal Update Form 3File: Form_3_SEP_2025.pdf20 Jun 2026
Withdrawal Update Form 3File: Form3_Dec_2025.pdf20 Jun 2026
Withdrawal Update Form 3File: Form_3_Mar_2026.pdf20 Jun 2026
Form 1File: Form_1_Architect_Certificate.pdf5 Jun 2026
Form 2File: Withdrawal Application Form 2.pdf5 Jun 2026
Form 3File: Form_3_Triveni_Infra_31032025.pdf5 Jun 2026
Disclosure of Sold and Booked InventoryFile: Form_3_Triveni_Infra_31032025.pdf5 Jun 2026
Withdrawal Update Form 1File: Form_1_Architect_Certificate.pdf5 Jun 2026
Withdrawal Update Form 1File: Form_1_Architect_Certificate.pdf5 Jun 2026
Withdrawal Update Form 2File: Withdrawal Application Form 2.pdf5 Jun 2026
Withdrawal Update Form 2File: Withdrawal Application Form 2.pdf5 Jun 2026
Withdrawal Update Form 3File: Form_3_Triveni_Infra_31032025.pdf5 Jun 2026
Withdrawal Update Form 3File: Form_3_Triveni_Infra_31032025.pdf5 Jun 2026
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form_1_Architect_ Certificate.pdf13 Mar 2025
Certificates of CA (Form 3)File: Form_3_Dec_24_Triveni_1_5.pdf13 Mar 2025
Certificates of CA (Form 3)File: Form_3_Dec_24_Triveni_5_10.pdf13 Mar 2025
Certificates of CA (Form 3)File: Form_3_Dec_24_Triveni_10_15.pdf13 Mar 2025
Certificates of CA (Form 3)File: Form_3_Dec_24_Triveni_15_20.pdf13 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form_2_Engineers_ Certificate.pdf13 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate 31032023.pdf6 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate 31032024.pdf6 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf4 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate.pdf3 May 2024
Certificates of CA (Form 3)File: Form 3 - 21-22-1-5.pdf3 May 2024
Certificates of CA (Form 3)File: Form 3 - 21-22-6-10.pdf3 May 2024
Certificates of CA (Form 3)File: Form 3 - 21-22-11-15.pdf3 May 2024
Certificates of CA (Form 3)File: Form 3 - 21-22-16-20.pdf3 May 2024
Certificates of CA (Form 3)File: Form 3- 22-23_merged_removed-1-5.pdf3 May 2024
Certificates of CA (Form 3)File: Form 3- 22-23_merged_removed-6-10.pdf3 May 2024
Certificates of CA (Form 3)File: Form 3- 22-23_merged_removed-11-15.pdf3 May 2024
Certificates of CA (Form 3)File: Form 3- 22-23_merged_removed-16-20.pdf3 May 2024
Certificates of CA (Form 3)File: Form 3 - 23-24-1-5.pdf3 May 2024
Certificates of CA (Form 3)File: Form 3 - 23-24-6-10.pdf3 May 2024
Certificates of CA (Form 3)File: Form 3 - 23-24-11-15.pdf3 May 2024
Certificates of CA (Form 3)File: Form 3 - 23-24-16-20.pdf3 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 FY 21-22.pdf3 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 FY 22-23.pdf3 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 FY 23-24.pdf3 May 2024
Certificates of CA (Form 3)File: ca certificate march 2022 01.pdf19 Apr 2024
Certificates of CA (Form 3)File: ca certificate march 2022 03.pdf19 Apr 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: ca certificate march 2022 02.pdf19 Apr 2024
Status of ConveyanceFile: Sale deed Index.pdf16 Apr 2024
Status of Formation of Legal Entity (Society/Co Op etc.)File: Declaration index.pdf19 Mar 2024
Building plan approvalFile: Scan20220530133004.pdf22 Feb 2024
Building plan approvalFile: A BUILDING_11zon.pdf22 Feb 2024
Building plan approvalFile: B BUILDING_11zon.pdf22 Feb 2024
Building plan approvalFile: C-1 BUILDG_11zon.pdf22 Feb 2024
Building plan approvalFile: C-2 BUILDING_11zon.pdf22 Feb 2024
Building plan approvalFile: D BUILDING_11zon.pdf22 Feb 2024
Building plan approvalFile: E BUILDING_11zon.pdf22 Feb 2024
Building plan approvalFile: E-2 BUILDING_11zon.pdf22 Feb 2024
Building plan approvalFile: F-1 BUILDING_11zon.pdf22 Feb 2024
Building plan approvalFile: F-2 BUILDING_11zon.pdf22 Feb 2024
Building plan approvalFile: G BUILDING_11zon.pdf22 Feb 2024
Building plan approvalFile: SITE PLAN_compressed.pdf22 Feb 2024
Details of encumbrances concerned to FinanceFile: Concern To Letter.pdf22 Feb 2024

How this compares with Kolhapur

51%of this project is bookeddistrict median 19%
17%of Kolhapur projects moved their completion datethis one moved by 86 months
25%of Kolhapur registrations have lapsed or been cancelledthis one is on the register

Computed across the 880+ Kolhapur projects on ReraGenie, from their own filings.

Keep SHAMRAO SHELKE COMMERCIAL AND RESIDENTIAL CO on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BAMBAWADE880+ in Kolhapur

Builder: TRIVENI INFRAPROJECT PVT LTD

TRIVENI INFRAPROJECT PVT LTD has 1 registration on MahaRERA, including SHAMRAO SHELKE COMMERCIAL AND RESIDENTIAL COMPLEX. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Kolhapur district page.

Frequently asked questions

What are my rights if SHAMRAO SHELKE COMMERCIAL AND RESIDENTIAL COMPLEX is delayed beyond 30 Sep 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHAMRAO SHELKE COMMERCIAL AND RESIDENTIAL COMPLEX?

The registered promoter entity is TRIVENI INFRAPROJECT PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHAMRAO SHELKE COMMERCIAL AND RESIDENTIAL COMPLEX?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SHAMRAO SHELKE COMMERCIAL AND RESIDENTIAL COMPLEX?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for SHAMRAO SHELKE COMMERCIAL AND RESIDENTIAL COMPLEX?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHAMRAO SHELKE COMMERCIAL AND RESIDENTIAL COMPLEX?

The professionals named in the filing: Architect: ANIRUDH SAWANT & ASSOCIATES; Engineer: MAHENDRA AJIT PATIL; Chartered Accountant: CHETAN PATIL; Chartered Accountant: SHANKAR VITTHAL PATIL; Chartered Accountant: Amit Madanrao Shinde. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHAMRAO SHELKE COMMERCIAL AND RESIDENTIAL COMPLEX?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHAMRAO SHELKE COMMERCIAL AND RESIDENTIAL COMPLEX. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHAMRAO SHELKE COMMERCIAL AND RESIDENTIAL CO to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.