Completed No litigation declared Residential / Group Housing project

Celestial City Phase II Building A, E, H

By RAMA SYNERGY SPACES

RG-MH-13192 · RERA P52100022487 · Last updated on MahaRERA portal: 9 Jan 2025

Source: official MahaRERA filing

Red flags

  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Mar 2023Possession promisedregistration recorded completed
32 of 33Construction stages doneacross 3 buildings; furthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 77 documents Report an error

Celestial City Phase II Building A, E, H is a Residential / Group Housing project by RAMA SYNERGY SPACES in Pune, Maharashtra, registered with MahaRERA as P52100022487 on 25 Sep 2019. The registration is recorded completed; possession was promised by 30 Mar 2023.

At a glance

Project

  • NameCelestial City Phase II Building A, E, H
  • TypeResidential / Group Housing
  • Location
    • Ravet Aundh Road
    • S No 78 P and 86/2 P
    • Ravet Aundh Road
    • Near Expressway
    • Ravet
    • Pimpri Chichwad
    • Pune
    • MH
    • Ravet
    • Haveli
    • Pune
    • 412101
  • Pincode412101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100022487
  • ReraGenie IDRG-MH-13192

Builder

  • NameRAMA SYNERGY SPACES
  • Entity typePartnership
  • PartnersRAM UDHARAM PANJABI, MANOJ RAMCHAND PANJABI, RAJKUMAR RAM PANJABI, NARESH RAMCHAND PANJABI, JITENDRA SUNDERDAS PANJABI, MOTI UDHARAM PANJABI, RONAK MOTI PANJABI, GOVIND UDHARAM PANJABI, PIYUSH GOVIND PANJABI
  • Other registrations15 more →
  • Completed10 of 16
  • No longer live3 lapsed, de-registered or revoked
  • Declared earlier projects14 →

Key dates

this monthRegisteredSep 2019PromisedMar 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on25 Sep 2019
  • Promised completion30 Mar 2023
  • Revised completionNone
  • Buildings3 building records
  • Documents filed77 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ANA140000
ENA160000
HNA160000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 9 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

32 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Podiums (if any), at 0%.

A91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
E100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
H100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 9 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed92

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots92
Closed/Covered88
Open Space4
BuildingClosed/CoveredOpen SpaceTotal
A18018
E37340
H33134

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,245 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI10032.42
Proposed, not sanctioned9,555 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMaratha Chambers, Plot No 3, Sector 25, Pradhikaran, Bhel Chowk, Nigdi, 411044 Pune MH

Certifying professionals and partners

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

PartnerRole in project
RAMA SYNERGY SPACES-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100013936Mar 2023 → Mar 2024

Reason as filed by the promoterWe hereby submit that due to the unavoidable circumstances beyond our control, we are few months behind the planned schedule for completion of the above said project. Therefore in lieu of the same, we humbly request you to kindly grant extension of time for possession of the above mentioned project and allow us to update the date of possession on MAHARERA website as 30th March 2024

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 6 Dec 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 9 Sep 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 9 Sep 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 23 Sep 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 5 Mar 2024

Documents filed77

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Disclosure of sold/ booked inventoryFile: Celestial City Ph-II (AEH).pdf9 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - F Y 2023-24 - Celestial Ph-II (AEH).pdf27 Nov 2024
Disclosure of sold/ booked inventoryFile: Celestial Ph-II (AEH).pdf19 Oct 2024
Disclosure of sold/ booked inventoryFile: Celestial City Ph-II (A,E,H).pdf16 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Celestial Ph-II.pdf16 Apr 2024
Disclosure of sold/ booked inventoryFile: Celestial Ph-II (AEH).pdf11 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A CELESTIAL CITY PH-II (A,E,H).pdf5 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Celestial City Ph-II (A,E,H Bldg).pdf30 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Celestial City Ph-II (A,E,H Bldg).pdf30 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Celestial City Ph-II (A,E,H Bldg).pdf5 Mar 2024
Disclosure of sold/ booked inventoryFile: Disclosure of inventory - Celestial Ph-II (A,E,H Bldg).pdf5 Mar 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion Certificate A Bldg.pdf5 Mar 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion Certificate E, H Bldg.pdf5 Mar 2024
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 - Celestial Ph-II (A,E,H Bldg).pdf5 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Celestial City Phase II A, E, H.pdf27 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Celestial City Phase II A, E, H.pdf23 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Celestial City Ph II A, E, H.pdf22 Jan 2024
Disclosure of sold/ booked inventoryFile: Celestial City Phase II A, E, H.pdf20 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Celestial City Ph-II.pdf16 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Celestial City Ph-II AEH Annual Report.pdf16 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CELESTIAL CITY PH-II AEH SEP-23 071023.pdf30 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Celestial City Ph-II AEH SEPTEMBER-23.pdf19 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Celestial City Ph-II AEH SEPTEMBER-23-23.pdf18 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 1 Celestial City Ph-II AEH SEPTEMBER-23.pdf18 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Celestial City AEH Ph-II SEPTEMBER-23.pdf18 Oct 2023
Disclosure of sold/ booked inventoryFile: CELESTIAL CITY PH-II AEH Inventory.pdf12 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Celestial City Ph-II AEH.pdf8 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 CELESTIAL CITY PH-II AEH 070723.pdf20 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CELESTIAL CITY PH-II AEH 070723.pdf20 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Celestial City Ph-II AEH MAR-23_11zon.pdf5 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 CELESTIAL CITY PH-II AEH_11zon.pdf18 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 CELESTIAL CITY PH-II AEH_11zon.pdf18 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Celestial City Ph-II AEH.pdf19 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 3 Celestial City Ph-II AEH DEC-22_11zon.pdf16 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Celestial City Ph-II AEH DEC-22_11zon.pdf16 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Celestial City Ph-II AEH GE 194 Rama Synergy Spaces_001891.pdf28 Oct 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Celestial City Ph-III AEH_11zon.pdf12 Oct 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 CELESTIAL CITY PH-II AEH compressed.pdf11 Oct 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Celestial City AEH 290822_11zon.pdf30 Aug 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Celestial City AEH 290822_11zon.pdf30 Aug 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Celestial City Ph-II AEH_11zon 140722.pdf14 Jul 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Celestial City Ph-II AEH 110722_11zon.pdf13 Jul 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Celestial City Ph-II AEH GE 464 Rama Synergy Spaces_001929.pdf28 Apr 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CELESTIAL CITY PH-II AEH_11zon.pdf27 Apr 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Celestial City Ph-II AEH_compressed (1).pdf14 Apr 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3_Celestial City AEH_21022022_Revised_compressed.pdf4 Mar 2022
Disclosure of sold/ booked inventoryFile: Celestial City Ph-II AEH Inventory DEC-21_compressed.pdf22 Jan 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 CELESTIAL PH II AEH_20220107_compressed.pdf12 Jan 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Celestial City Ph-II AEH Form 2A DEC-22_compressed.pdf10 Jan 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: CELESTIAL CITY PH-II AEH Arch CertIficate Form 1 DEC-21_compressed.pdf8 Jan 2022
Disclosure of sold/ booked inventoryFile: CELESTIAL CITY PH-II AEH SEP-21 INVENTORY.pdf21 Oct 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Celestial City A,E,H- Form1_compressed.pdf11 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2 Celestial City Phase-II AEH_compressed.pdf9 Oct 2021
Declaration about Commencement CertificateFile: Form - D Celestial City Ph-II AEH BLDG.pdf15 Sep 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: CELESTIAL CITY PHASE - I - A E H_11zon.pdf20 Aug 2021
Disclosure of sold/ booked inventoryFile: Celestial City AEH Inventory-min.pdf19 Aug 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Rera Certificate Celestial City AEH 16072021 20210724.pdf11 Aug 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Celestial City Ph II AEH 02 06 2021.pdf24 Jun 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Celestial City Ph II AEH 02 06 2021.pdf7 Jun 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Rera Certificate Celestial City AEH 14 04 2021.pdf29 Apr 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: RSS Celestial City Ph II.PDF23 Jan 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Celestial City Ph II_compressed.pdf17 Feb 2020
Copy of the legal title reportFile: TITLE CERTIFICATE - Celestial.pdf6 Dec 2019
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT Dtd 30 07 2019.pdf23 Sep 2019
Proforma of Allotment letterFile: DECLARATION.pdf23 Sep 2019
Layout approvalFile: Layout.pdf9 Sep 2019
Building plan approvalFile: A1 Floor Plan.pdf9 Sep 2019
Building plan approvalFile: E1 Floor Plan.pdf9 Sep 2019
Building plan approvalFile: H1 Floor Plan.pdf9 Sep 2019
Copy of the legal title reportFile: Title Report - Celestial City_compressed.pdf9 Sep 2019
Details of encumbrancesFile: Encumbrances Certificate.pdf9 Sep 2019
Copy of Layout Approval (in case of layout)File: Layout.pdf9 Sep 2019
Building Plan Approval / NA Order for plotted developmentFile: A1 Floor Plan.pdf9 Sep 2019
Building Plan Approval / NA Order for plotted developmentFile: E1 Floor Plan.pdf9 Sep 2019
Building Plan Approval / NA Order for plotted developmentFile: H1 Floor Plan.pdf9 Sep 2019
Declaration in FORM BFile: Declaration Form B.pdf9 Sep 2019
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA - Celestial City.pdf9 Sep 2019

Promoter's earlier projects13

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise8 delivered late4 not delivered by the promised date
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Fusion Towers Phase IVP52100049419Hinjewadi Phase III, Pune175Feb 2023OngoingDec 2025Not delivered
FUSION TOWERS PHASE IIIP52100049215Hinjewadi Phase III, Pune91Feb 2023OngoingJul 2025Not delivered
Celestial City Phase II Building I, J, KP52100028977S No 86, Ravet Aundh Road, Near Expressway, Ravet, MH, Pune162Apr 2021OngoingJun 2024Not delivered
Metro Life Maxima Residences Phase IIP52100023984Next to Indira College of Commerce and Science, Pune275Jan 2020CompletedDec 2023Late, Jul 2024
Metro Life Optima ResidencesP52100026255Next to Indira College of Commerce and Science, Pune199Sep 2020OngoingSep 2023Not delivered
Metro Life Bizz BayP52100022156Next to Indira College of Commerce and Science, Pune179Sep 2019CompletedJul 2023Late, Jul 2024
METRO LIFE MAXIMA RESIDENCES PHASE IP52100022178Next to Indira College of Commerce and Science, Pune276Sep 2019CompletedJul 2023Late, Mar 2024
MELANGE RESIDENCES - PHASE IVP52100025451Hinjawadi Phase III, Pune110May 2020CompletedDec 2022Late, May 2023
FUSION TOWERS PHASE IIP52100019797Hinjawadi - Phase III, Pune110Mar 2019CompletedDec 2022Late, May 2024
MELANGE RESIDENCES - PHASE IIIP52100017090Hinjawadi Phase III, Pune110Jul 2018CompletedSep 2021Late, May 2023
FUSION TOWERS PHASE IP52100018013Hinjawadi - Phase III, Pune220Oct 2018CompletedJun 2021Late, Aug 2023
MELANGE RESIDENCES - PHASE IIP52100003047Hinjawadi Phase III, Pune220Aug 2017CompletedJun 2019Late, Jul 2019
MELANGE RESIDENCES - PHASE IMIDC Phase III Main Rd Phase 3 Hinjewadi Rajiv Gandhi Infotech Park Hinjawadi Pimpri-Chinchwad Maharashtra 411057330-CompletedDec 2018Dec 2018

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Celestial City Phase II Building A, E, H on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near S No 78 P and 86/2 P, Ravet Aundh Road, Near Expressway, Ravet, Pimpri Chichwad, Pune, MH13,700+ in Pune

2 kmCelestial City Phase II Completed 102Lapsed / revoked 57Other 130Dot size: filed unitsN

Filed coordinates, straight-line distance. 289 registered projects within 2 km.

Builder: RAMA SYNERGY SPACES

RAMA SYNERGY SPACES has 16 registrations on MahaRERA, including MELANGE RESIDENCES - PHASE I and MELANGE RESIDENCES - PHASE II. Its filings disclose 14 earlier MahaRERA projects: declares 1 of 10 past projects completed on time. Litigation is declared on 3 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Celestial City Phase II Building A, E, H is delayed beyond 30 Mar 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Celestial City Phase II Building A, E, H?

The registered promoter entity is RAMA SYNERGY SPACES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Celestial City Phase II Building A, E, H?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Celestial City Phase II Building A, E, H?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

What should I check before booking in Celestial City Phase II Building A, E, H?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Celestial City Phase II Building A, E, H. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Celestial City Phase II Building A, E, H to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.