ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Godrej Nurture

Registered No litigation declared Residential / Group Housing project

Godrej Nurture

By Godrej Skyline Developers Limited

RG-MH-04897 · RERA P52100020686 · Last updated on MahaRERA portal: 19 Jul 2026

Source: official MahaRERA filing

Red flags

  • Possession 1 months past the filed date
  • 26 complaints at MahaRERA
  • Completion date moved by 24 months
  • 2 extensions taken
  • Rs 250.00 crore secured on the land, in favour of BAJAJ HOUSING FINANCE LIMITED

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Sep 2026Possession promised1 month past this date
53 of 55Construction stages doneacross 5 buildings; furthest along: Sanitary Fittings within the flats /..., 99%
6 of 714Units unsoldnot recorded sold or booked
26Complaints at MahaRERAon this registration
Jump to the 158 documents Report an error

Godrej Nurture is a Residential / Group Housing project by Godrej Skyline Developers Limited in Pune, Maharashtra, registered with MahaRERA as P52100020686 on 3 May 2019. Possession was promised by 30 Sep 2026 and is now 1 months past that date. The completion date has moved by 24 months from the original filing. 708 of the 714 units on this registration are recorded sold or booked, and 53 of 55 construction stages are filed complete. 26 complaints are on record with the regulator.

At a glance

Project

  • NameGodrej Nurture
  • TypeResidential / Group Housing
  • Location
    • Gahunje ROad
    • Mamurdi
    • Haveli
    • Pune
    • 412101
  • Pincode412101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100020686
  • ReraGenie IDRG-MH-04897

Builder

  • NameGodrej Skyline Developers Limited
  • Entity typeCompany
  • CINU45309MH2016PTC287858
  • DirectorAMANDEEP SINGH
  • Partner 1Subhashish Jyotishchandra Pattanaik
  • Other registrations7 more →
  • Past their filed date3
  • Declared earlier projects4 →

Key dates

1 months past promisethis monthRegisteredMay 2019First promiseSep 2024Revised toSep 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on3 May 2019
  • Promised completion30 Sep 2026
  • Revised completionRevised to 30 Sep 2026 (originally 30 Sep 2024)
  • Buildings5 building records
  • Documents filed158 files

Current status

99%708 of 714 units booked
98.8%Work done, per cost certificate

Figures as on 19 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TOWER 1NA22191420142
TOWER 2NA22191420142
TOWER 3NA22191420142
TOWER 4NA22191420142
TOWER 5NA22191460146

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building5

As on 19 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

53 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 99%.

TOWER 1100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
TOWER 2100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises99%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.99%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
TOWER 3100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
TOWER 4100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
TOWER 5100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 19 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed714

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots714
Closed/Covered457
Open Space257
BuildingClosed/CoveredOpen SpaceTotal
TOWER 17864142
TOWER 28359142
TOWER 38755142
TOWER 411329142
TOWER 59650146

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area30,307 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofBAJAJ HOUSING FINANCE LIMITED
Secured amountRs 250.00 crore
Declared on8 Sep 2025

Approvals and building plan

Sanctioning authorityPimpri Chinchwad Municipal Corporation
Permissible FSI59541.76
Proposed, not sanctioned59,542 sq m
Buildings approved5
Buildings sanctioned5

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchHDFC bank Ltd, ground Floor, Jehangir Building, MG ROad, Fort, Mumbai 400001
Estimated costRs 283
Cost incurredRs 280
Work done98.8%
BuildingWingEstimatedIncurred
TOWER 1NARs 59Rs 56
TOWER 4NARs 54Rs 54
TOWER 3NARs 53Rs 53
TOWER 2NARs 52Rs 52
TOWER 5NARs 52Rs 52
-NARs 13Rs 13

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectArchitecture Collective
EngineerANIL POWAR
Chartered AccountantB S R & Co. LLP
Chartered AccountantM D Deshpande & Co.
PartnerRole in project
Godrej Skyline Developers Limited-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100024587Sep 2024 → Sep 2025

Reason as filed by the promoterIn view of the application, request the Developer be granted extension of project timelines from 1st October 2024 to 30th September 2025.

EA08092502531Sep 2024 → Sep 2026

Reason as filed by the promoterIn light of the reasons mentioned in our application, requesting you to grant us extension for a period of 1 years from 30th September 2025 to 30th September 2026

Complaints filed with MahaRERA26

Case no.ComplainantRespondentFiled
CC005000000064395Vijaykumar Govardhan PawarGodrej Skyline Developers Pvt Ltd through its Director Mr. Amandeep Singh13/07/2020
CC005000000370930Ramesh shivdasanGodrej Skyline Developers Pvt Ltd (Godrej Nurture)22/05/2024
CC12401188Arijit MukherjeeGODREJ SKYLINE DEVELOPERS PRIVATE LIMITED20/12/2024
CC12500653Surendra Kumar PandeyGODREJ SKYLINE DEVELOPERS PRIVATE LIMITED24/02/2025
CC12500719Jyotish Kumar WarrierGODREJ SKYLINE DEVELOPERS PRIVATE LIMITED01/03/2025
CC12502694Nilesh Vijaykumar DhongadeGodrej Skyline Developers Limited01/08/2025
CC12602022Arpit AgrawalGodrej Skyline Developers Limited06/04/2026
CC12503116Carolyn Condrad AndradeGodrej Skyline Developers Limited04/09/2025
CC12503117Condrad Deric AndradeGodrej Skyline Developers Limited04/09/2025
CC12503547Umesh Gopalrao PotdarGodrej Skyline Developers Limited05/10/2025
CC12503619rahul ramsing pardeshiGodrej Skyline Developers Limited11/10/2025
CC12503711Pradeep Bhagwan SonawaneGodrej Skyline Developers Limited19/10/2025
CC12504335Mahendra VyavhareGodrej Skyline Developers Limited07/12/2025
CC12600517Sachin Dinkar NaikGodrej Skyline Developers Limited29/01/2026
CC12600828Prachi Mahesh MungekarGodrej Skyline Developers Limited14/02/2026
CC12600942Sanket Suresh DaragshettiGodrej Skyline Developers Limited20/02/2026
CC12601147Varsha Pradeep IngaleGodrej Skyline Developers Limited02/03/2026
CC12601529SANTOSH KUMAR B GHADIGodrej Skyline Developers Limited20/03/2026
CC12601834HARSHIDA PARESH HIRANIGodrej Skyline Developers Limited28/03/2026
CC12602407Yogesh Kadu KshirsagarGodrej Skyline Developers Limited24/04/2026
CC12602545Chandrashekhar Umakant BudheGodrej Skyline Developers Limited01/05/2026
CC12602492Alpesh Rameshchandra VyasGodrej Skyline Developers Limited28/04/2026
CC12602995ABHJIT BANDU SHENDEGodrej Skyline Developers Limited20/05/2026
CC12604804Savita Rajendra RajageGodrej Skyline Developers Limited30/07/2026
CC12604832Himani Nihal AgrawalGodrej Skyline Developers Limited31/07/2026
CC12605045Nivedita BandekarGodrej Skyline Developers Limited08/08/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 22 Jun 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Aug 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Apr 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 9 Jul 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed158

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 158 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Arch Certificate Nurture Q1FY27.pdf19 Jul 2026
Withdrawal Update Form 2File: Engg Certificate Nurture Q1FY27.pdf19 Jul 2026
Withdrawal Update Form 3File: MDD_Godrej Nurture_June-26_Signed.pdf19 Jul 2026
Withdrawal Update Form 1File: RERA Architect Certificate Godrej Nurture Q4FY26.pdf25 Apr 2026
Withdrawal Update Form 2File: Eng_Certificate Godrej Nurture Q4FY26.pdf25 Apr 2026
Withdrawal Update Form 3File: Godrej Nurture March26 Signed.pdf25 Apr 2026
Withdrawal Update Form 1File: RERA Architect Certificate Godrej Nurture Q4FY26.pdf22 Apr 2026
Withdrawal Update Form 2File: Eng_Certificate Godrej Nurture Q4FY26.pdf22 Apr 2026
Withdrawal Update Form 3File: Godrej Nurture March26 Signed.pdf22 Apr 2026
Withdrawal Update Form 1File: Architect Certificate Sparkle Q3FY26.pdf25 Jan 2026
Withdrawal Update Form 1File: Architect Certificate Godrej Nurture Q3FY26.pdf25 Jan 2026
Withdrawal Update Form 2File: Engineers Certificate Nurture Q3FY26.pdf25 Jan 2026
Withdrawal Update Form 2File: Engineers Certificate Nurture Q3FY26.pdf25 Jan 2026
Withdrawal Update Form 3File: Godrej Nurture December25 Signed.pdf25 Jan 2026
Withdrawal Update Form 3File: Godrej Nurture December25 Signed.pdf25 Jan 2026
Withdrawal Update Form 1File: RERA Architect Certificate Godrej Nurture Q2FY26.pdf20 Oct 2025
Withdrawal Update Form 2File: Engineers Certificare Godrej Nurture.pdf20 Oct 2025
Withdrawal Update Form 3File: CA RERA Certificate Godrej Nurture Sep25.pdf20 Oct 2025
Form 5 (FY 2024-2025)File: Nurture Form 5 Annexure 1_compressed.pdf29 Aug 2025
Form 1File: RERA Architect Certificate Godrej Nurture.pdf20 Jul 2025
Form 2File: Annexure B Godrej Nurture (1).pdf20 Jul 2025
Form 3File: CA Certificate Godrej Nurture June25 Signed.pdf20 Jul 2025
Disclosure of Sold and Booked InventoryFile: Godrej Nurture (1).pdf20 Jul 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Nurture.pdf1 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Godrej Nurture.pdf20 Apr 2025
Certificates of CA (Form 3)File: Godrej Nurture CA Cert.pdf20 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Annexure B Engineering Certificate Godrej Nurture.pdf20 Apr 2025
Disclosure of sold/ booked inventoryFile: Godrej Nurture (1).pdf20 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality Assurance Godrej Nurture.pdf20 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA Architect Certificate Godrej Nurture.pdf20 Jan 2025
Certificates of CA (Form 3)File: Godrej Nurture.pdf20 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Godrej Nurture.pdf20 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Godrej Nurture 2.pdf20 Jan 2025
Disclosure of sold/ booked inventoryFile: Godrej Nurture (1).pdf20 Jan 2025
CERSAI detailsFile: CERSAI Latest.pdf21 Oct 2024
Certificates of CA (Form 3)File: Nurture Form 3.pdf19 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Godrej Nurture.pdf15 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Godrej Nurture (1).pdf15 Oct 2024
Disclosure of sold/ booked inventoryFile: Godrej Nurture.pdf15 Oct 2024
CERSAI detailsFile: CERSAI.pdf15 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Godrej Nurture Form 5_compressed.pdf15 Oct 2024
PAN CardFile: Pan Card New.pdf14 Oct 2024
Declaration in FORM BFile: Nurture FORM B.pdf12 Aug 2024
Disclosure of sold/ booked inventoryFile: NURTURE INVENTORY.pdf12 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Nurture.pdf20 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Nurture.pdf20 Jul 2024
Certificates of CA (Form 3)File: Nurture_June24.pdf20 Jul 2024
Disclosure of sold/ booked inventoryFile: Godrej Nurture.pdf18 Jul 2024
Disclosure of sold/ booked inventoryFile: April 24_Disclosure of Sold-Nurture Signed.pdf19 Apr 2024
Certificates of CA (Form 3)File: MDD_Godrej Nuture_Mar_24 ( Signed ).pdf16 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate Nurture March,2024.pdf15 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificat Nurture - March,2024.pdf15 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality Certificate Nurture March,2024.pdf15 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Nuture - Architect's Certificate.pdf12 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Nuture - Enggineer's Certificate.pdf12 Jan 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold-Nurture__Dec 23.pdf12 Jan 2024
CERSAI detailsFile: CERSAI_Search_Report_200293339474_For_Debtor_Based_Search_12_01_2024_11_56_49_022.pdf12 Jan 2024
Certificates of CA (Form 3)File: Godrej Nurture Dec-23_Signed.pdf12 Jan 2024
Details of encumbrancesFile: Declaration _Godrej Nurture.pdf20 Oct 2023
Details of encumbrancesFile: Encumbrance_Godrej Nurture.pdf20 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Nuture - Architect Certificate.pdf20 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Nuture Engg Certificate.pdf20 Oct 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Sold-Nurture Sept23.pdf20 Oct 2023
Certificates of CA (Form 3)File: MDD_Godrej Nuture_Sept_Revised_Signed.pdf20 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Skyline - Godrej Nurture.pdf21 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Nurture.pdf20 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FABS_GPL_NURTURE_ ENGINEER'S CERTIFICATE (Form-2).pdf20 Jul 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Sold-Nurture__Jul-23.pdf20 Jul 2023
Certificates of CA (Form 3)File: Godrej Nurture_June23_Signed.pdf20 Jul 2023
Certificates of CA (Form 3)File: MDD_Godrej Nuture- OMD.PDF19 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Godrej Nurture.pdf15 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Nurture.pdf15 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality Assuarance Certificate Nurture.pdf15 Apr 2023
Disclosure of sold/ booked inventoryFile: Nurture - Disclosure of Sold Inventory.pdf15 Apr 2023
Certificates of CA (Form 3)File: Godrej Nurture.pdf20 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Nurture.pdf19 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Nurture.pdf19 Jan 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Sold-Nurture__Dec-22.pdf19 Jan 2023
Disclosure of sold/ booked inventoryFile: Disclosure of inventory.pdf17 Oct 2022
Certificates of CA (Form 3)File: Nurt_Sept22.pdf17 Oct 2022

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
GODREJ CENTRAL PARKPUNE1,190CompletedMar 2023Mar 2023

How this compares with Pune

99%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 24 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Godrej Nurture on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Mamurdi13,700+ in Pune

2 kmGodrej NurtureCompleted 37Lapsed / revoked 27Other 75Dot size: filed unitsN

Filed coordinates, straight-line distance. 139 registered projects within 2 km.

Builder: Godrej Skyline Developers Limited

Godrej Skyline Developers Limited has 8 registrations on MahaRERA, including Godrej Park Greens and Godrej Nurture. Its filings disclose 4 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Litigation is declared on 3 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Godrej Nurture is delayed beyond 30 Sep 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Godrej Nurture?

The registered promoter entity is Godrej Skyline Developers Limited, a company as per the filing. Its CIN U45309MH2016PTC287858 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Godrej Nurture?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Godrej Nurture?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Godrej Nurture?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Godrej Nurture?

The professionals named in the filing: Architect: Architecture Collective; Engineer: ANIL POWAR; Chartered Accountant: B S R & Co. LLP; Chartered Accountant: M D Deshpande & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Godrej Nurture?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Godrej Nurture. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Godrej Nurture to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.