Home / Browse projects / Pune, Maharashtra / FOREST GROVE AT GODREJ PARK GREENS
FOREST GROVE AT GODREJ PARK GREENS
By Godrej Skyline Developers Limited
RG-MH-15212 · RERA P52100023129 · Last updated on MahaRERA portal: 20 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Litigation declared, 4 cases
- 38 complaints at MahaRERA
- Completion date moved by 30 months
- 2 extensions taken
- Rs 250.00 crore secured on the land, in favour of BAJAJ HOUSING FINANCE LIMITED
Clear
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
FOREST GROVE AT GODREJ PARK GREENS is a Others project by Godrej Skyline Developers Limited in Pune, Maharashtra, registered with MahaRERA as P52100023129 on 2 Dec 2019. Possession is promised by 30 Sep 2027. The completion date has moved by 30 months from the original filing. 1,125 of the 1,139 units on this registration are recorded sold or booked, and 39 of 77 construction stages are filed complete. 38 complaints are on record with the regulator.
At a glance
Project
- NameFOREST GROVE AT GODREJ PARK GREENS
- TypeOthers
- Location
- Service road to Pune Mumbai Expressway
- MAMURDI VILLAGE
- Haveli
- Pune
- 412101
- Pincode412101
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100023129
- ReraGenie IDRG-MH-15212
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on2 Dec 2019
- Promised completion30 Sep 2027
- Revised completionRevised to 30 Sep 2027 (originally 30 Mar 2025)
- Buildings7 building records
- Documents filed142 files
Current status
Figures as on 20 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| TOWER A1 | NA | 21 | 20 | 154 | 0 | 154 |
| TOWER A2 | NA | 18 | 17 | 132 | 0 | 132 |
| TOWER A4 | NA | 23 | 22 | 170 | 0 | 170 |
| TOWER A5 | NA | 23 | 22 | 170 | 0 | 170 |
| TOWER A6 | NA | 23 | 22 | 170 | 0 | 170 |
| TOWER A7 | NA | 23 | 22 | 170 | 0 | 170 |
| TOWER A3 | NA | 23 | 22 | 173 | 0 | 173 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building7
As on 20 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
39 of 77 construction stages are filed complete across 7 buildings. The stage furthest along is External plumbing and external plaster, at 99%.
TOWER A160%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 35% |
| Sanitary Fittings within the flats / premises | 41% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 56% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 10% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 14% |
TOWER A258%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 24% |
| Sanitary Fittings within the flats / premises | 35% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 66% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 14% |
TOWER A459%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 32% |
| Sanitary Fittings within the flats / premises | 40% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 63% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 15% |
TOWER A582%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 98% |
| Sanitary Fittings within the flats / premises | 79% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 88% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 98% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 39% |
TOWER A687%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 91% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 96% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 99% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 69% |
TOWER A787%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 95% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 96% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 69% |
TOWER A373%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 97% |
| Sanitary Fittings within the flats / premises | 71% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 30% |
Progress on shared amenities15
As on 20 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 52% |
| Water Supply | Yes | 80% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 70% |
| Storm Water Drains | Yes | 70% |
| Landscaping & Tree Planting | Yes | 10% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 40% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 50% |
| Water conservation /Rain water harvesting | Yes | 70% |
| Energy managemcnt | Yes | 30% |
| Fire protection and fire safety requirements | Yes | 50% |
| Electrical meter room, sub-station, receiving station | Yes | 60% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed364
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| TOWER A1 | 37 | 1 | 38 |
| TOWER A2 | 37 | 4 | 41 |
| TOWER A4 | 44 | 21 | 65 |
| TOWER A5 | 44 | 15 | 59 |
| TOWER A6 | 44 | 10 | 54 |
| TOWER A7 | 41 | 0 | 41 |
| TOWER A3 | 44 | 22 | 66 |
Land and ownership
A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| TOWER A5 | NA | Rs 59 | Rs 44 |
| TOWER A3 | NA | Rs 59 | Rs 44 |
| TOWER A4 | NA | Rs 54 | Rs 36 |
| TOWER A7 | NA | Rs 52 | Rs 44 |
| TOWER A6 | NA | Rs 51 | Rs 43 |
| TOWER A1 | NA | Rs 46 | Rs 34 |
| TOWER A2 | NA | Rs 41 | Rs 28 |
| - | NA | Rs 11 | Rs 5 |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Studio 30 Architects and Planners |
| Engineer | ANIL POWAR |
| Chartered Accountant | M D Deshpande & Co. |
| Chartered Accountant | B S R & Co. LLP |
| Partner | Role in project |
|---|---|
| Godrej Skyline Developers Limited | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterIn view of the application, request developer be granted extension for project timelines from 31st March 2025 to 30th March 2026
Reason as filed by the promoterIn light of the reasons mentioned in our application, requesting you to grant us extension for a period of 1.5 years from 30th March 2026 to 30th September 2027
Litigation declared4
| Case | Court | Status |
|---|---|---|
| 593/2023 | Joint CJSD AND Additional CJM Pune | Closed |
| 758/2023 | Joint CJSD AND Additional CJM Pune | Closed |
| 22/294/2022 | District Consumer Dispute Redressal Commission Pune | PENDING |
| 593/2023/2023 | Pune District and Sessions Court | Closed |
Complaints filed with MahaRERA38
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000064485 | ASHOK BABAJI SABLE | GODREJ SKYLINE DEVELOPERS PVT LTD | 08/08/2020 |
| CC005000000075204 | DEVENDRA NATH TRIPATHI & DEESHA GORASIA | GODREJ SKYLINE DEVELOPERS PRIVATE LTD | 11/02/2021 |
| CC12500457 | ASHISH SHRIVASTAVA | GODREJ SKYLINE DEVELOPERS PRIVATE LIMITED | 11/02/2025 |
| CC12500545 | Dilip Sardesai | GODREJ SKYLINE DEVELOPERS PRIVATE LIMITED | 17/02/2025 |
| CC12500549 | Sangam Sardesai | GODREJ SKYLINE DEVELOPERS PRIVATE LIMITED | 17/02/2025 |
| CC12501584 | ABHAY KUMAR DHUWE | GODREJ SKYLINE DEVELOPERS PRIVATE LIMITED | 14/05/2025 |
| CC12502125 | Jitendra Pathak | GODREJ SKYLINE DEVELOPERS PRIVATE LIMITED | 28/06/2025 |
| CC12502533 | Deepankar Dilip Sheet | Godrej Skyline Developers Limited | 23/07/2025 |
| CC12504288 | NIHAR SUBRATO BANERJEE | Godrej Skyline Developers Limited | 04/12/2025 |
| CC12504092 | Prasad Pralhad Khamkar | Godrej Skyline Developers Limited | 20/11/2025 |
| CC12504235 | KAPIL ASHOKRAO GAHUKAR | Godrej Skyline Developers Limited | 30/11/2025 |
| CC12504663 | Nihit Pramod Chauhan | Godrej Skyline Developers Limited | 29/12/2025 |
| CC12602128 | Vittal Kishan Jakore | Godrej Skyline Developers Limited | 11/04/2026 |
| CC12602216 | Sachitanand Chandradeo Singh | Godrej Skyline Developers Limited | 15/04/2026 |
| CC12602211 | Pranit Pramod Nikam | Godrej Skyline Developers Limited | 15/04/2026 |
| CC12602426 | Ranganath Krishna Bhat | Godrej Skyline Developers Limited | 25/04/2026 |
| CC12602463 | Mohit Rajiv Badhe | Godrej Skyline Developers Limited | 27/04/2026 |
| CC12602928 | Subodh Anand | Godrej Skyline Developers Limited | 18/05/2026 |
| CC12603031 | SUDHIR KADAM | Godrej Skyline Developers Limited | 22/05/2026 |
| CC12603062 | Vivek Digwani | Godrej Skyline Developers Limited | 23/05/2026 |
| CC12603848 | Rupali Hari Khot | Godrej Skyline Developers Limited | 21/06/2026 |
| CC12604114 | Anahita Siroos Najmi | Godrej Skyline Developers Limited | 01/07/2026 |
| CC12604116 | Priya Santlal Patel | Godrej Skyline Developers Limited | 01/07/2026 |
| CC12604138 | Abhishek Gaurishankar Singh | Godrej Skyline Developers Limited | 02/07/2026 |
| CC12604141 | Tej Pratap Pandey | Godrej Skyline Developers Limited | 02/07/2026 |
| CC12604150 | Ganesh Vidyadhar Nimbargi | Godrej Skyline Developers Limited | 02/07/2026 |
| CC12604160 | Parag Arvind Kshirsagar | Godrej Skyline Developers Limited | 03/07/2026 |
| CC12604179 | Sumit Ashokrao Umekar | Godrej Skyline Developers Limited | 04/07/2026 |
| CC12604231 | Vaibhav Bhagwan Singh Patel | Godrej Skyline Developers Limited | 06/07/2026 |
| CC12604234 | Pankaj Krishan Kumar Rajput | Godrej Skyline Developers Limited | 06/07/2026 |
| CC12604260 | Snehal Subhashrao Rajurkar | Godrej Skyline Developers Limited | 07/07/2026 |
| CC12604253 | Siddhant Sanjay Shah | Godrej Skyline Developers Limited | 07/07/2026 |
| CC12604262 | Shadaab Mohiuddin | Godrej Skyline Developers Limited | 07/07/2026 |
| CC12604391 | Praveen Omprakash Kumar | Godrej Skyline Developers Limited | 14/07/2026 |
| CC12604535 | Arnaz Keki Bhesania | Godrej Skyline Developers Limited | 19/07/2026 |
| CC12604573 | Bharati Tanaji Shedge | Godrej Skyline Developers Limited | 21/07/2026 |
| CC12604669 | Shyamveer singh Parihar | godrej skyline developers | 25/07/2026 |
| CC12605024 | Nitin Ramesh Birajdar | Godrej Skyline Developers Limited | 07/08/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 13 Nov 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 13 Nov 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 9 Sep 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 8 Sep 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Sep 2027
Documents filed142
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 142 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Arch RERA Certificate GFG Q1FY27.pdf | 20 Jul 2026 |
| Withdrawal Update Form 2File: Engg Certificate GFG Q1FY27.pdf | 20 Jul 2026 |
| Withdrawal Update Form 3File: MDD_RERA certificate Forest Grove_June_26_Signed.pdf | 20 Jul 2026 |
| Withdrawal Update Form 1File: Architect Certificate Godrej Forest Grove Q4FY26.pdf | 24 Apr 2026 |
| Withdrawal Update Form 2File: Eng_Certificate_GFG.pdf | 24 Apr 2026 |
| Withdrawal Update Form 3File: MDD_RERA certificate Forest Grove_March_26_Signed.pdf | 24 Apr 2026 |
| Withdrawal Update Form 1File: Architect Certificate Godrej Forest Grove Q3FY26.pdf | 24 Jan 2026 |
| Withdrawal Update Form 2File: Engineers Certificate GFG Q3FY26.pdf | 24 Jan 2026 |
| Withdrawal Update Form 3File: RERA certificate Forest Grove December 25 Signed.pdf | 24 Jan 2026 |
| Withdrawal Update Form 1File: Architect Certificate Godrej Forest Grove (1) Q2FY26.pdf | 20 Oct 2025 |
| Withdrawal Update Form 2File: Eng_certificate forest grove.pdf | 20 Oct 2025 |
| Withdrawal Update Form 3File: RERA certificate Forest Grove Sep25.pdf | 20 Oct 2025 |
| Form 5 (FY 2024-2025)File: Forest Grove Form5_compressed.pdf | 29 Aug 2025 |
| Form 1File: Architect Certificate Godrej Forest Grove (1).pdf | 20 Jul 2025 |
| Form 2File: Annexure B Forest grove.pdf | 20 Jul 2025 |
| Form 3File: CA certificate Forest Grove June 25 Signed.pdf | 20 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Forest Grove at Godrej Park Greens.pdf | 20 Jul 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: GFG.pdf | 1 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Godrej Forest Grove.pdf | 20 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Forest Grove CA Cert.pdf | 20 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Annexure B Forest Grove at Godrej Park Green.pdf | 20 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Forest Grove at Godrej Park Greens.pdf | 20 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality Assurance Certificate GFG.pdf | 20 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Godrej Forest Grove.pdf | 20 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Forest grove.pdf | 20 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Godrej Forest Grove.pdf | 20 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Forest Grove at Godrej Park Greens.pdf | 20 Jan 2025 |
| CERSAI detailsFile: CERSAI Latest.pdf | 21 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Forest Grove Form 3.pdf | 19 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Godrej Forest Grove.pdf | 15 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Forest Grove.pdf | 15 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Forest Grove at Godrej Park Greens.pdf | 15 Oct 2024 |
| CERSAI detailsFile: CERSAI.pdf | 15 Oct 2024 |
| PAN CardFile: Pan Card New.pdf | 9 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Forest Grove Form 5_compressed.pdf | 9 Oct 2024 |
| Declaration in FORM BFile: FOREST GROVE FORM B.pdf | 13 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: Forest Grove Inventory Disclosure_compressed.pdf | 13 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Forest Grove.pdf | 20 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: MDD_FOREST GROVE_JUNE 24_Signed.pdf | 20 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Forest Grove.pdf | 20 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Forest Grove at Godrej Park Greens.pdf | 19 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Forest Grove_March 2024_Signed.pdf | 16 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate Forest Grove March,2024.pdf | 15 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificat Forest Grove at Park Green - March,2024.pdf | 15 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality Certificat Forest Grove at Park Green - March,2024.pdf | 15 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: April 24_Disclosure of Sold-Forest Grove signed.pdf | 12 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Forest Grove - Architect's Certificate.pdf | 12 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Forest Grove - Enggineer's Certificate.pdf | 12 Jan 2024 |
| CERSAI detailsFile: CERSAI_Search_Report_200293339474_For_Debtor_Based_Search_12_01_2024_11_56_49_022.pdf | 12 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold-Forest-Grove_Dec 23.pdf | 12 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Forest Grove Dec-23_Signed.pdf | 12 Jan 2024 |
| Details of encumbrancesFile: Declaration _Forest Grove.pdf | 20 Oct 2023 |
| Details of encumbrancesFile: Encumbrance_Forest Grove.pdf | 20 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Forest Grove - Architects Certificate.pdf | 20 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Forest Grove Engg Cetificate.pdf | 19 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold-Forest-Grove Sept23.pdf | 19 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: MDD_RERA certificate Forest Grove-Signed.pdf | 19 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Skyline - Forest Grove at Godrej Skyline.pdf | 21 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Godrej Park Greens_7_11zon.pdf | 20 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Godrej Forest Grove_5_11zon.pdf | 20 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate Forest Groove.pdf | 20 Jul 2023 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold-Forest-Grove_Jul-23.pdf | 20 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: MDD_RERA certificate Forest Grove-Signed.pdf | 20 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: MDD_RERA certificate Forest Grove-OMD.PDF | 19 Apr 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Godrej Forest Grove.pdf | 15 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Forest Grove.pdf | 15 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality Assuarance Certificate Forest Grove.pdf | 15 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: forest grove - disclosure of sold inventory.pdf | 15 Apr 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Godrej Forest Grove.pdf | 20 Jan 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Forest Grove.pdf | 19 Jan 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Forest grove.pdf | 19 Jan 2023 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold-Forest-Grove_Dec'22.pdf | 19 Jan 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate_Forest Grove.pdf | 19 Oct 2022 |
| Disclosure of sold/ booked inventoryFile: Disclosure of inventory.pdf | 17 Oct 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FG_Sept22.pdf | 17 Oct 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Forest Grove.pdf | 14 Oct 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FOREST GROVE.pdf | 30 Sep 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate - Forest Grove.pdf | 9 Jul 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate - Forest Grove.pdf | 9 Jul 2022 |
| CERSAI detailsFile: CERSAI Search Report.pdf | 9 Jul 2022 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| GODREJ PARK GREENS | PUNE | 1,190 | Completed | Mar 2023 | Mar 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 7 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 142 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep FOREST GROVE AT GODREJ PARK GREENS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near MAMURDI VILLAGE13,700+ in Pune
Filed coordinates, straight-line distance. 36 registered projects within 2 km.
Godrej Park Greens
Godrej Skyline Developers Limited
Om Mangalam Samruddhi
NDG Homes LLP
PCMC EWS KIWALE
Pimpri Chinchwad Municipal Corporation
Godrej Nurture
Godrej Skyline Developers Limited
My Home Sanctuary Phase I
MAMURDI DEVELOPERS LLP
Presidential Towers
CERATEC CONSTRUCTION
Builder: Godrej Skyline Developers Limited
Godrej Skyline Developers Limited has 8 registrations on MahaRERA, including Godrej Park Greens and Godrej Nurture. Its filings disclose 4 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Litigation is declared on 3 of its registrations. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if FOREST GROVE AT GODREJ PARK GREENS is delayed beyond 30 Sep 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of FOREST GROVE AT GODREJ PARK GREENS?
The registered promoter entity is Godrej Skyline Developers Limited, a company as per the filing. Its CIN U45309MH2016PTC287858 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in FOREST GROVE AT GODREJ PARK GREENS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against FOREST GROVE AT GODREJ PARK GREENS?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for FOREST GROVE AT GODREJ PARK GREENS?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at FOREST GROVE AT GODREJ PARK GREENS?
The professionals named in the filing: Architect: Studio 30 Architects and Planners; Engineer: ANIL POWAR; Chartered Accountant: M D Deshpande & Co.; Chartered Accountant: B S R & Co. LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in FOREST GROVE AT GODREJ PARK GREENS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback