ReraGenieLog inGet a buyer report

Home / Developers / RAMA SYNERGY SPACES

RAMA SYNERGY SPACES: RERA track record

Partnership ยท attribution by exact filing name, entity resolution in progress

RAMA SYNERGY SPACES has 16 registrations in this build, including MELANGE RESIDENCES - PHASE I and MELANGE RESIDENCES - PHASE II. Its filings disclose 14 earlier MahaRERA projects: 1 of 10 past projects completed on time. Litigation is declared on 3 of its registrations.

16Registrations in this build
14Past projects disclosed
+9 monthsMedian delivery slip
3Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
MELANGE RESIDENCES - PHASE IPune, Maharashtra--Completed
MELANGE RESIDENCES - PHASE IIPune, Maharashtra--Completed
MELANGE RESIDENCES - PHASE IIIPune, Maharashtra--Completed
FUSION TOWERS PHASE IPune, Maharashtra--Completed
FUSION TOWERS PHASE IIPune, Maharashtra11097%Completed
Metro Life Bizz BayPune, Maharashtra--Completed
METRO LIFE MAXIMA RESIDENCES PHASE IPune, Maharashtra--Completed
Celestial City Phase II Building A, E, HPune, Maharashtra--Completed
Metro Life Maxima Residences Phase IIPune, Maharashtra--Completed
MELANGE RESIDENCES - PHASE IVPune, Maharashtra--Completed
Metro Life Optima ResidencesPune, Maharashtra--Registration lapsed
Celestial City Phase II Building I, J, KPune, Maharashtra16292%Registration lapsed
FUSION TOWERS PHASE IIIPune, Maharashtra9185%Registered
Fusion Towers Phase IVPune, Maharashtra17575%Registered
Metro Life Ultima Residences Phase IPune, Maharashtra19480%Registered
METRO LIFE ULTIMA RESIDENCES PHASE IIPune, Maharashtra18231%Registered

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
MELANGE RESIDENCES - PHASE I
31 Dec 201829 Dec 2018On time
MELANGE RESIDENCES - PHASE II
P52100003047
30 Jun 201929 Jul 2019+1 months
FUSION TOWERS PHASE I
P52100018013
30 Jun 202124 Aug 2023+26 months
MELANGE RESIDENCES - PHASE III
P52100017090
30 Sep 202118 May 2023+20 months
MELANGE RESIDENCES - PHASE IV
P52100025451
30 Dec 202218 May 2023+5 months
FUSION TOWERS PHASE II
P52100019797
30 Dec 202210 May 2024+16 months
Celestial City Phase II Building A, E, H
P52100022487
30 Mar 202315 Feb 2024+11 months
Metro Life Bizz Bay
P52100022156
31 Jul 202323 Jul 2024+12 months
METRO LIFE MAXIMA RESIDENCES PHASE I
P52100022178
31 Jul 202311 Mar 2024+7 months
Metro Life Optima Residences
P52100026255
30 Sep 2023Not completed yetOngoing
Metro Life Maxima Residences Phase II
P52100023984
30 Dec 202319 Jul 2024+7 months
Celestial City Phase II Building I, J, K
P52100028977
30 Jun 2024Not completed yetOngoing

Frequently asked questions

How do I verify RAMA SYNERGY SPACES as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with RAMA SYNERGY SPACES?

Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

Does the declared litigation make RAMA SYNERGY SPACES unsafe to buy from?

Not by itself. Litigation on a registration ranges from a boundary dispute to an allottee case about delay; what matters is the case type, which court or forum, and whether it touches the land title of the project you are buying. The case list is in each project's filed documents. Treat litigation as a question to resolve in writing before booking, not as a verdict either way.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.