Home / Developers / Sunteck Realty Limited

Sunteck Realty Limited: RERA track record

CIN L32100MH1981PLC025346 · GSTIN 27AAACI0336E1Z3 · Company · attribution by exact filing name, entity resolution in progress

Sunteck Realty Limited has 25 registrations in this build, including Sunteck City Avenue 1 and Sunteck City Avenue 2. Its filings disclose 6 earlier MahaRERA projects: 4 of 6 past projects completed on time. Litigation is declared on 12 of its registrations.

25Registrations in this build
6Past projects disclosed
on timeMedian delivery slip
12Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
Sunteck City Avenue 1Mumbai Suburban, Maharashtra--Completed
Sunteck City Avenue 2Mumbai Suburban, Maharashtra--Completed
Signia High, Magathane, Western Express Highway, Borivali EastMumbai Suburban, Maharashtra--Completed
Redevelopment of MCGB Staff Gilbird CHSL, Gilbird Hill Road, Andheri WestMumbai Suburban, Maharashtra--Completed
Sunteck Icon, Kolekalyan, CST Road, Kalina, Santacruz East, MumbaiMumbai Suburban, Maharashtra620%Completed
Sunteck West World 1, Tivri, Naigaon EastPalghar, Maharashtra--Completed
Sunteck West World 2, Tivri, Naigaon EastPalghar, Maharashtra--Completed
Sunteck MaxxWorld 1, Tivri, Naigaon EastPalghar, Maharashtra--Completed
Sunteck MaxxWorld 2, Tivri, Naigaon EastPalghar, Maharashtra--Registration lapsed
Sunteck MaxxWorld 3, Tivri, Naigaon EastPalghar, Maharashtra--Completed
Sunteck MaxxWorld 4, Tivri, Naigaon EastPalghar, Maharashtra--Registration lapsed
Sunteck MaxxWorld 5, Tivri, Naigaon EastPalghar, Maharashtra60%Registered
Sunteck HillView 2Palghar, Maharashtra1850%Registered
Sunteck PinnacleMumbai Suburban, Maharashtra--Completed
Sunteck Pinnacle 1Mumbai Suburban, Maharashtra12753%Registered
Sunteck ONEWorld 1, Tivri, Naigaon EastPalghar, Maharashtra18761%Registered
Sunteck ONEWorld 2, Tivri, Naigaon EastPalghar, Maharashtra37056%Registered
Sunteck ONEWorld 3, Tivri, Naigaon EastPalghar, Maharashtra35048%Registered
Sunteck ONEWorld 4, Tivri, Naigaon EastPalghar, Maharashtra35860%Registered
Sunteck ONEWorld 5, Tivri, Naigaon EastPalghar, Maharashtra38660%Registered
Sunteck City Avenue 1- Phase 2Mumbai Suburban, Maharashtra--Registration revoked
Sunteck HillView 5Palghar, Maharashtra1810%Registered
Sunteck HillView 3Palghar, Maharashtra18358%Registered
Sunteck HillView 4Palghar, Maharashtra18038%Registered
Sunteck OneWorld -Tower 1Palghar, Maharashtra1830%Registered

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
Sunteck Centre
30 Sep 200931 Dec 2009+3 months
Sunteck Grandeur
28 Mar 201311 Jul 2014+15 months
Signia High
7 Sep 202026 Jun 2019On time
Redevelopment of MCGB Staff Gilbird CHSL
30 Oct 202215 Dec 2020On time
Sunteck West World 1
30 Sep 202320 May 2022On time
Sunteck West World 2
30 Dec 202320 May 2022On time

Frequently asked questions

How do I verify Sunteck Realty Limited as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its CIN L32100MH1981PLC025346 and GSTIN 27AAACI0336E1Z3 on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with Sunteck Realty Limited?

Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

Does the declared litigation make Sunteck Realty Limited unsafe to buy from?

Not by itself. Litigation on a registration ranges from a boundary dispute to an allottee case about delay; what matters is the case type, which court or forum, and whether it touches the land title of the project you are buying. The case list is in each project's filed documents. Treat litigation as a question to resolve in writing before booking, not as a verdict either way.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.